D.C. Mun. Regs. tit. 27, § 1925
1925.1 Contracts for dismantling, demolition, or removal of structures shall be awarded in accordance with either the Service Contract Act 1965 (41 U.S.C. §§351-358) or the Davis-Bacon Act (40 U.S.C. §§276a-276a-7).
1925.2 When the contract is solely for dismantling, demolition, or removal of structures, the provisions of the Service Contract Act shall be followed.
1925.3 When the contract is for dismantling, demolition, or removal of structures and further work will result in the construction, alteration, or repair of a public building or public work at the same location even though by separate contract, the provisions of the Davis-Bacon Act shall be followed with respect to the contract for dismantling, demolition, or removal.
1925.4 The contracting officer shall comply with the requirements of the Service Contract Act and the Davis-Bacon Act in accordance with chapter 43 of this title.
1925.5 When a contract is solely for dismantling, demolition, or removal of structures, the contracting officer may require the contractor to furnish a performance bond or other security in accordance with the provisions of chapter 27 of this title in an amount that the contracting officer considers adequate to do the following:
(a) Ensure completion of the work;
(b) Protect property to be retained by the District;
(c) Protect property to be provided as compensation to the contractor; and
(d) Protect the District against damage to adjoining property.
1925.6 Any requirement for a bond under this section shall be documented by the contracting officer in accordance with the provisions of chapter 27 of this title.
SOURCE: Final Rulemaking published at 35 DCR 1504 (February 26, 1988); as amended by Emergency rulemaking published at 47 DCR 8590 (October 20, 2000) [EXPIRED].