D.C. Mun. Regs. tit. 22-B, § 4008
4008.1 A CON holder shall make quarterly progress reports to SHPDA.
4008.2 A progress report shall include the following information, if applicable:
4008.3 The Director may request additional information after receiving a progress report if the Director determines that the report is not complete.
4008.4 The Director may approve or deny a request for a CON extension without submitting the extension request to the SHCC, unless the request would require submission of a new application and full review.4008.5 SHPDA staff shall prepare a memorandum of the progress made by the CON holder receiving the complete progress report for the third (3rd) quarter of each CON year. The analysis shall include the following:- (a) The project's rate of progress according to the most recent SHPDA-approved schedule for the project;
- (b) Whether any reported delay is beyond the control of the CON holder;
- (c) Whether the CON holder will complete the project on schedule;
- (d) Whether any change in the proposed schedule is reasonable with respect to the health requirements of District residents and visitors;
- (e) Whether any cost changes exceed the rate of inflation for construction projects in the District;
- (f) Whether the CON holder has minimized costs;
- (g) Whether financing for the project continues to be adequate;
- (h) Whether the CON holder is continuing to comply with any conditions of the CON; and
- (i) Whether the project continues to be adequate with respect to all review criteria, except those for need and conformance to the State Health Plan.4008.6 SHPDA staff shall make a recommendation to the Director about whether to issue an extension for a CON under Section 4007 or to take action under Section 4010 to revoke a CON.
SOURCE: Final Rulemaking published at 29 DCR 5569 (December 17, 1982), enacting Proposed Rulemaking published at 29 DCR 4742 (October 29, 1982); as amended by Final Rulemaking published at 61 DCR 1666 (February 28, 2014).