D.C. Mun. Regs. tit. 21, § 533
Stormwater Management: Ownership of Stormwater Retention Credits
Authority: Department of Consumer and Regulatory Affairs Civil Infractions Act of 1985, effective October 5, 1985, as amended (D.C. Law 6-42; D.C. Official Code §§ 2-1801.01 et seq. (2007 Repl. & 2012 Supp.)); District Department of the Environment Establishment Act of 2005, §§ 101 et seq., effective February 15, 2006, as amended (D.C. Law 16-51; D.C. Official Code §§ 8-151.01 et seq. (2008 Repl. & 2012 Supp.)); National Capital Revitalization Corporation and Anacostia Waterfront Corporation Reorganization Act of 2008, effective March 26, 2008 (D.C. Law 17-138; 55 DCR 1689), as amended by the Anacostia Waterfront Environmental Standards Amendment Act of 2012, effective October 23, 2012 (D.C. Law 19-192; D.C. Official Code §§ 2-1226.31 et seq.) (2012 Supp.)); The Soil Erosion and Sedimentation Control Act of 1977, effective September 28, 1977 (D.C. Law 2-23; 24 DCR 792), as amended by the Soil Erosion and Sedimentation Control Amendment Act of 1994, effective August 26, 1994, (D.C. Law 10-166; 41 DCR 4892; 21 DCMR §§ 500-15); Uniform Environmental Covenants Act of 2005, effective May 12, 2006, as amended (D.C. Law 16-95; D.C. Official Code §§ 8-671.01 et seq. (2008 Repl.)); Water Pollution Control Act of 1984, effective March 16, 1985, as amended (D.C. Law 5-188; D.C. Official Code §§ 8-103.01 et seq. (2008 Repl. & 2012 Supp.)); and Mayor’s Order 2006-61, dated June 14, 2006, and its delegations of authority. Source: Final Rulemaking published at 35 DCR 21 (January 1, 1988); as amended by Final Rulemaking published at 60 DCR 10640 (July 19, 2013).District of Columbia, Office of the Secretary
533 STORM WATER MANAGEMENT: INSPECTION
533.1 The Department, through its authorized representative, shall conduct on-site inspections at stages of construction as determined by the Department.
533.2 The developer shall notify the Department twenty-four (24) hours prior to beginning the construction of any on-site or off-site storm water management facility subject to these regulations.
533.3 The professional engineer for the project shall accompany the Department representative on all on-site inspections.
533.4 No scheduled storm water management work shall proceed until the Department's authorized representative, accompanied by the professional engineer responsible for certifying the "As-Built" plans, inspects and approves the work previously completed.
533.5 The applicant shall promptly correct in the manner specified any portion of the work which does not comply with the approved plans.
533.6 A final inspection shall be conducted by the Department upon completion of the storm water management facility to determine if the completed work is constructed in accordance with approved plans.