Tank Tightness Testing Upon Upgrade
Effective Feb 21, 202067 DCR 1778Authority: Section 107 of the District Department of the Environment Establishment Act of 2005, effective February 15, 2006 (D.C. Law 16-51; D.C. Official Code § 8-151.07 (2013 Repl. & 2019 Supp.)); the District of Columbia Underground Storage Tank Management Act of 1990, effective March 8, 1991 (D.C. Law 8-242; D.C. Official Code §§ 8-113.01 et seq. (2013 Repl.)); Sections 11 and 21 of the Water Pollution Control Act of 1984, effective March 16, 1985 (D.C. Law 5-188; D.C. Official Code §§ 8-103.10 & 8-103.20 (2013 Repl.)); and Mayor's Order 2006-61, dated June 14, 2006. Source: Final Rulemaking published at 40 DCR 7835, 7862 (November 12, 1993); as amended by Final Rulemaking published at 46 DCR 7699 (October 1, 1999); as amended by Final Rulemaking published at 67 DCR 1778 (February 21, 2020).District of Columbia, Office of the Secretary
5804.1 Before beginning to operate an upgraded UST system, the owner or operator shall have a tightness test performed in accordance with the requirements of § 6007, unless the tank is upgraded by cathodic protection and the owner or operator complies with § 5801.7(c).
SOURCE: Final Rulemaking published at 40 DCR 7835 (November 12, 1993); as amended by Final Rulemaking published at 46 DCR 7699 (October 1, 1999); as amended by Final Rulemaking published at 67 DCR 1778 (February 21, 2020).