D.C. Mun. Regs. tit. 15, § 4003
4003.1 The EDC shall review interconnection requests using one (1) or more of the four (4) levels of review procedures established by this Chapter. The EDC shall first use the level of agreement specified by the interconnection customer in the application form. The EDC may not impose additional requirements not specifically authorized unless the EDC and the interconnection customer mutually agree to do so in writing.
Source: As amended by Final Rulemaking published at 56 DCR 1415, 1418 (February 13, 2009).