D.C. Mun. Regs. tit. 11, § 2711
2711.1 The Zoning Administrator shall not take final action on an application to permit an antenna tower, a monopole, or an antenna not exempted by § 2707 until a report is received from the Office of Planning or thirty (30) days have passed since the application was submitted to the director of the Office of Planning, whichever occurs first.
2711.2 The director of the Office of Planning and the Zoning Administrator may agree to lengthen the time period indicated in § 2711.1, but in no event shall the review period exceed sixty (60) days.
2711.3 The report of the Office of Planning shall provide specific criteria and information sufficient to enable the Zoning Administrator to determine whether the antenna complies with the applicable requirements of this chapter.
SOURCE: Final Rulemaking published at 55 DCR 34 (January 4, 2008).