D.C. Mun. Regs. tit. 11, § 2607
2607.1 The Board of Zoning Adjustment is authorized to permit some or all of the set-aside requirements of § 2603 to be constructed off-site upon proof, based upon a specific economic analysis, that compliance on-site would impose an economic hardship. Among the factors that may be considered by the BZA in determining the existence of economic hardship are:
2607.2 An applicant who has demonstrated the existence of economic hardship shall further demonstrate that the off-site development:
2607.3 The requirement of § 2607.2 (a) may be waived upon a showing that the off-site development is owned by the Applicant, is located in the District of Columbia, and meets the requirements of § 2607.2.
2607.4 Inclusionary units constructed off-site shall not be counted toward any set-aside requirement separately applicable to the off-site development pursuant to § 2603.
2607.5 No order granting off-site compliance shall become effective until a covenant, found legally sufficient by the Office of the Attorney General, has been recorded in the land records of the District of Columbia between the owner of the off-site development and the Mayor. A draft
covenant, executed by the owner of the offsite property, shall be attached to an application for relief under this section.
2607.6 The covenant shall bind the owner and all future owners of the off-site development to:
(a) Construct and reserve the number of inclusionary units allowed to be accounted for off-site, in accordance with the plans approved by the Board and the conditions of the Board's order;
(b) Sell or rent, as applicable, such units in accordance with the provisions of this Chapter and the Act for so long as the off-site development remains in existence;
(c) Neither apply for nor accept any development subsidies from federal or District government programs established to provide affordable housing;
(d) Acknowledge that the owners are legally responsible for the set-aside requirement accepted as if the requirement had been imposed directly on the off-site development; and
(e) Not request special exception or variance relief with respect to the obligations accepted or its own obligations under this Chapter.
2607.7 Upon the recordation of the covenant, the set-aside requirements permitted to be accounted off-site shall be deemed to be the legal obligation of the current and future owners of the off-site development. All dwelling units as are required to be reserved in the off-site development in accordance with the BZA order shall be deemed inclusionary units for the purposes of this Chapter and the Act.
2607.8 No application for a certificate of occupancy for a market-rate unit on the inclusionary development shall be granted unless construction of the off-site inclusionary units is progressing at a rate roughly proportional to the construction of the on-site market-rate units.
SOURCE: Final Rulemaking published at 53 DCR 7013 (August 25, 2006); as amended by Final Rulemaking published at 55 DCR 2604 (March 14, 2008).