Conn. Gen. Stat. § 16-245w
(a) As used in this section, “self-generation facility” means a facility that generates electricity, is owned or operated by an entity other than an electric distribution company, as defined in section 16-1, or electric supplier, as defined in said section 16-1, and operates in parallel with other generation on the distribution system of an electric distribution company and which reduces or eliminates the purchase of electricity through the distribution network.
*(b) The Public Utilities Regulatory Authority shall design a process for determining a fee to be paid by customers who have installed self-generation facilities in order to offset any loss or potential loss in revenue from such facilities toward the competitive transition assessment, the systems benefits charge the conservation and load management assessment collected under section 16-245m and the Clean Energy Fund assessment collected under section 16-245n. Except as provided in subsection (c) of this section, such fee shall apply to customers who have installed self-generation facilities that begin operation on or after July 1, 1998.
(e) Not later than January 1, 1999, the authority shall submit its findings and recommendations to the joint standing committee of the General Assembly having cognizance of matters relating to energy.
*Note: On and after January 1, 2020, subsection (b) of this section, as amended by section 23 of public act 18-50, is to read as follows:
“(b) The Public Utilities Regulatory Authority shall design a process for determining a fee to be paid by customers who have installed self-generation facilities in order to offset any loss or potential loss in revenue from such facilities toward the competitive transition assessment, the systems benefits charge, the conservation adjustment mechanisms collected under section 16-245m and the Clean Energy Fund assessment collected under section 16-245n. Except as provided in subsection (c) of this section, such fee shall apply to customers who have installed self-generation facilities that begin operation on or after July 1, 1998.”
(P.A. 98-28, S. 69, 117; P.A. 11-80, S. 1; P.A. 18-50, S. 23.)
History: P.A. 98-28 effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, and “Renewable Energy Investment Fund” was changed editorially by the Revisors to “Clean Energy Fund”, effective July 1, 2011; P.A. 18-50 amended Subsec. (b) by replacing “the conservation and load management assessment” with “the conservation adjustment mechanisms” and making a conforming change, effective January 1, 2020.