A complete record that shows the following must be maintained by the operator involved for the life of each pipeline facility:
- (a) The total number of girth welds and the number nondestructively tested, including the number rejected and the disposition of each rejected weld.
- (b) The amount, location; and cover of each size of pipe installed.
- (c) The location of each crossing of another pipeline.
- (d) The location of each buried utility crossing.
- (e) The location of each overhead crossing.
- (f) The location of each valve and corrosion test station.
[Amdt. 195-22, 46 FR 38360, July 27, 1981, as amended by Amdt. 195-34, 50 FR 34474, Aug. 26, 1985]