49 C.F.R. § 192.619
(a) No person may operate a segment of steel or plastic pipeline at a pressure that exceeds a maximum allowable operating pressure (MAOP) determined under paragraph (c), (d), or (e) of this section, or the lowest of the following:
(1) The design pressure of the weakest element in the segment, determined in accordance with subparts C and D of this part. However, for steel pipe in pipelines being converted under § 192.14 or uprated under subpart K of this part, if any variable necessary to determine the design pressure under the design formula (§ 192.105) is unknown, one of the following pressures is to be used as design pressure:
(2) The pressure obtained by dividing the pressure to which the pipeline segment was tested after construction as follows:
(ii) For steel pipe operated at 100 psi (689 kPa) gage or more, the test pressure is divided by a factor determined in accordance with the Table 1 to paragraph (a)(2)(ii):
| Class location | Installed before(Nov. 12, 1970) | Factors,1 2 segment— | ||
|---|---|---|---|---|
| Installed after(Nov. 11, 1970)and beforeJuly 1, 2020 | Installed on orafter July 1, 2020 | Converted under§ 192.14 | ||
| 1 | 1.1 | 1.1 | 1.25 | 1.25 |
| 2 | 1.25 | 1.25 | 1.25 | 1.25 |
| 3 | 1.4 | 1.5 | 1.5 | 1.5 |
| 4 | 1.4 | 1.5 | 1.5 | 1.5 |
| 1 For offshore pipeline segments installed, uprated or converted after July 31, 1977, that are not located on an offshore platform, the factor is 1.25. For pipeline segments installed, uprated or converted after July 31, 1977, that are located on an offshore platform or on a platform in inland navigable waters, including a pipe riser, the factor is 1.5. | ||||
| 2 For a component with a design pressure established in accordance with § 192.153(a) or (b) installed after July 14, 2004, the factor is 1.3. |
(3) The highest actual operating pressure to which the segment was subjected during the 5 years preceding the applicable date in the second column. This pressure restriction applies unless the segment was tested according to the requirements in paragraph (a)(2) of this section after the applicable date in the third column or the segment was uprated according to the requirements in subpart K of this part:
| Pipeline segment | Pressure date | Test date |
|---|---|---|
| (i) Onshore regulated gathering pipeline (Type A or Type B under § 192.9(d)) that first became subject to this part (other than § 192.612) after April 13, 2006 | March 15, 2006, or date pipeline becomes subject to this part, whichever is later | 5 years preceding applicable date in second column. |
| (ii) Onshore regulated gathering pipeline (Type C under § 192.9(d)) that first became subject to this part (other than § 192.612) on or after May 16, 2022 | May 16, 2023, or date pipeline becomes subject to this part, whichever is later | 5 years preceding applicable date in second column. |
| (iii) Onshore transmission pipeline that was a gathering pipeline not subject to this part before March 15, 2006 | March 15, 2006, or date pipeline becomes subject to this part, whichever is later | 5 years preceding applicable date in second column. |
| (iv) Offshore gathering pipelines | July 1, 1976 | July 1, 1971. |
| (v) All other pipelines | July 1, 1970 | July 1, 1965. |
(c) The requirements on pressure restrictions in this section do not apply in the following instances:
(2) For any Type C gas gathering pipeline under § 192.9 existing on or before May 16, 2022, that was not previously subject to this part and the operator cannot determine the actual operating pressure of the pipeline for the 5 years preceding May 16, 2023, the operator may establish MAOP using other criteria based on a combination of operating conditions, other tests, and design with approval from PHMSA. The operator must notify PHMSA in accordance with § 192.18. The notification must include the following information:
(f) Operators of onshore steel transmission pipelines must make and retain records necessary to establish and document the MAOP of each pipeline segment in accordance with paragraphs (a) through (e) of this section as follows:
(3) Operators of pipelines placed in operation after July 1, 2020 must make and retain records establishing MAOP for the life of the pipeline.
Editorial Note:For Federal Register citations affecting § 192.619, see the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and at www.govinfo.gov.
[35 FR 13257, Aug. 19, 1970]