(b) Manufacturer requirements. To seek Coast Guard approval of a release mechanism, the manufacturer must submit an application to the Commandant meeting the requirements of 46 CFR 159.005-5 for preapproval review. To meet the requirements of 46 CFR 159.005-5(a)(2), the manufacturer must submit—
- (1) A list of drawings, specifications, manuals, and any other documentation submitted, with each document identified by number, title, revision issue, and date;
- (2) General arrangement and assembly drawings, including principal dimensions;
- (3) Stress calculations for all load carrying parts, including the release hooks, release mechanisms, and connections;
- (4) Hydraulic systems drawings and specifications, if installed;
- (5) Drawings of all signs and placards showing actual inscription, format, color, and size;
- (6) An operation, maintenance, and training manual as described in §§ 160.170-19 and 160.170-21 of this subpart;
(7) A description of the quality control procedures and recordkeeping that will apply to the production of the release mechanism, which must include but is not limited to—
- (i) The system for checking material certifications received from suppliers;
- (ii) The method for controlling the inventory of materials;
- (iii) The method for checking quality of fabrication and joints, including welding inspection procedures; and
- (iv) The inspection checklists used during various stages of fabrication to assure that the approved release mechanism complies with the approved plans and the requirements of this subpart;
- (8) Full details of any other unique capability;
- (9) Any other drawing(s) necessary to show that the release mechanism complies with the requirements of this subpart;
- (10) The location or address of all manufacturing sites, including the name and address of any subcontractors, where the release mechanism will be constructed; and
- (11) The name of the independent laboratory that will perform the duties prescribed in § 160.170-15 of this subpart.