(a) BLM may deny your application if:
- (1) The proposed use is inconsistent with the purpose for which BLM or other Federal agencies manage the lands described in your application;
- (2) The proposed use would not be in the public interest;
- (3) You are not qualified to hold a grant or TUP;
- (4) Issuing the grant or TUP would be inconsistent with the Act, other laws, or these or other regulations;
- (5) You do not have or cannot demonstrate the technical or financial capability to construct the pipeline or operate facilities within the right-of-way or TUP area; or
- (6) You do not comply with a deficiency notice (see § 2804.25(c)) or with any requests from the BLM for additional information needed to process the application.
- (b) If you are unable to meet any of the requirements in this section you may request an alternative from the BLM (see § 2884.30).
- (c) If BLM denies your application, you may appeal the decision under § 2881.10 of this part.
[70 FR 21078, Apr. 22, 2005, as amended at 81 FR 92227, Dec. 19, 2016; 89 FR 25975, Apr. 12, 2024]