- (a) The BLM may conduct a competitive process for solar and wind energy development grants or leases on its own initiative; or
- (b) The BLM may solicit nominations for public lands to be included in a competitive process by publishing a call for nominations under § 2809.11(a); or
- (c) You may request that the BLM conduct a competitive process by submitting a request in writing that complies with § 2809.11(b); or
- (d) The BLM may conduct a competitive process if it receives two or more competing applications.
- (e) Except where an applicant has failed to timely provide information requested by the BLM under § 2804.25(c), the BLM will not offer lands in a competitive process for which the BLM has accepted a complete application, received a Plan of Development, and entered into a cost recovery agreement.
[89 FR 35682, May 1, 2024]