(b) The agency official initially authorized to take any of the following actions shall provide the contractor with a written statement of the basis for his or her action at the time the action is taken, including any relevant facts that were relied upon in taking the action.
- (1) A refusal to grant an extension under paragraph (c)(4) of the standard clauses.
- (2) A request for a conveyance of title under paragraph (d) of the standard clauses.
- (3) A refusal to grant a waiver under paragraph (i) of the standard clauses.
- (4) A refusal to approve an assignment under paragraph (k)(1) of the standard clauses.
- (5) A refusal to grant an extension of the exclusive license period under paragraph (k)(2) of the clauses prescribed by either OMB Circular A-124 or OMB Bulletin 81-22.