30 C.F.R. § 285.702
(a) Your Fabrication and Installation Report must describe how your facilities will be fabricated and installed in accordance with the design criteria identified in the Facility Design Report; your BOEM-approved SAP, COP, or GAP; and generally accepted industry standards and practices. Your Fabrication and Installation Report must demonstrate how your facilities will be fabricated and installed in a manner that conforms to your responsibilities listed in § 285.105(a). You must include the following items in your Fabrication and Installation Report:
| Required documents | Required contents |
|---|---|
| (1) Cover letter | (i) Proposed facility designation, lease, ROW grant, or RUE grant number; (ii) Area, name, and block number; and (iii) The type of facility. |
| (2) Schedule | Fabrication and installation schedule information. |
| (3) Fabrication information | The industry standards you will use to ensure the facilities are fabricated to the design criteria identified in your Facility Design Report. |
| (4) Installation process information | Details associated with the deployment activities, equipment, and materials, including onshore and offshore equipment and support, and anchoring and mooring patterns. |
| (5) Federal, State, and local permits (e.g., EPA, Army Corps of Engineers) | Either one copy of the permit or information on the status of the application. |
| (6) Quality assurance | Certificates ensuring adherence to a nationally or internationally recognized quality assurance standard. Alternate means of compliance must be approved on a case-by-case basis. |
| (7) Environmental information | Information about: (i) Water discharge; (ii) Waste disposal; (iii) Vessel information; (iv) Onshore waste receiving treatment or disposal facilities; and (v) If you submitted this data as part of your SAP, COP, or GAP, you may incorporate the information by reference. |
| (8) Commissioning procedures for Critical Safety Systems and Equipment | Original equipment manufacturer procedures or other BSEE accepted engineering practices for commissioning of Critical Safety Systems and Equipment as identified in § 285.701(a)(12). |
| (9) Project easement | Information about installation of any cables, pipelines, or facilities. Information on burial methods and vessels. |
| (10) Other information | Additional information required by BSEE. |