(a) A complete application package for PE consists of the following:
- (1) The certification checklist;
- (2) Tribal Transportation Program (TTP) transportation improvement program (TIP);
- (3) Project scope of work;
- (4) Detailed cost for PE;
- (5) NBI data; and
- (6) An acknowledgment by the Tribe of the project specific funding requirements and that any excess funds will be returned to FHWA for further distribution.
- (b) For non-BIA/non-Tribally owned TTF bridges, the application package must also include a Tribal resolution supporting the project.
- (c) Incomplete application packages will be disapproved and returned for revision and resubmission along with an explanation providing the reason for disapproval.
- (d) The TTF bridge projects for PE will be placed in the queue and determined as eligible for funding after receipt by FHWA of a complete application package.
- (e) Funding for the approved eligible projects on the queues will be made available to the Tribes, under a TTP Program agreement between FHWA and a Tribal government, or the Secretary of the Interior upon availability of program funding at FHWA.