Link to an amendment published at 82 FR 29390, June 29, 2017.
- (a) Prior to submission of an application pursuant to § 806.13, a project sponsor seeking approval to withdraw or increase a withdrawal of groundwater shall perform a constant-rate aquifer test in accordance with this section.
- (b) The project sponsor shall prepare a constant-rate aquifer test plan for prior review and approval by Commission staff before testing is undertaken. Such plan shall include a groundwater availability analysis to determine the availability of water during a 1-in-10-year recurrence interval.
- (c) Unless otherwise specified, approval of a test plan is valid for two years from the date of approval.
- (d) Approval of a test plan shall not be construed to limit the authority of the Commission to require additional testing or monitoring.
- (e) The project sponsor may be required, at its expense, to provide temporary water supply if an aquifer test results in interference with an existing water use.