Link to an amendment published at 82 FR 29390, June 29, 2017.
(a) An existing Commission approval may be transferred to a new project sponsor by the Executive Director provided:
- (1) The application for transfer is submitted within 90 days of a transfer or change in ownership of a project.
- (2) The new project sponsor operates the project subject to the same terms and conditions of the existing approval pending approval of the transfer application.
- (3) Any noncompliance by the existing project sponsor associated with the project or by the new project sponsor associated with other projects is resolved to the Commission's satisfaction.
- (4) If the existing approval is greater than 10 years old, the transfer shall be conditioned to require the submission of an updated metering and monitoring plan consistent with the requirements of § 806.30.
- (5) If the existing project has an unapproved withdrawal, consumptive use and/or diversion listed in paragraph (b) of this section, the transfer shall be conditioned to require the submission of a new application for review and approval of the unapproved withdrawal, consumptive use and/or diversion consistent with §§ 806.4 and 806.14.
- (6) Any modifications proposed by the new project sponsor shall be subject to a separate application and review process under §§ 806.14 and 806.18.
(b) Previously unapproved activities associated with a project subject to transfer under paragraph (a) of this section include:
- (1) The project has an associated pre-compact consumptive water use that has not been subject to approval or had mitigation approved by the Commission.
- (2) The project has an associated diversion that was initiated prior to January 23, 1971.
- (3) The project has an associated groundwater withdrawal that was initiated prior to July 13, 1978, and that has not been approved by the Commission.
- (4) The project has an associated surface water withdrawal that was initiated prior to November 11, 1995, and that has not been approved by the Commission.
- (5) The project has a consumptive water use approval and has an associated withdrawal that has not been approved by the Commission.
- (c) Upon undergoing a change of name that does not affect ownership or control of the project, the project sponsor must request a reissuance of the project's approval by the Executive Director within 90 days from the date of the change.
[80 FR 76857, Dec. 11, 2015]