18 C.F.R. § 50.5
(b) Initial consultation. An applicant must meet and consult with the Director concerning the proposed project.
(c) Contents of the initial filing. An applicant's pre-filing request will be filed after the initial consultation and must include the following information:
(3) A list of the permitting entities responsible for conducting separate Federal permitting and environmental reviews and authorizations for the project, including contact names and telephone numbers, and a list of local entities with local authorization requirements. The filing must include information concerning:
(d) Director's notice.
(1) When the Director finds that an applicant seeking authority to site and construct an electric transmission facility has adequately addressed the requirements of paragraphs (a), (b), and (c) of this section, and any other requirements determined at the Initial Consultation meeting, the Director will so notify the applicant.
(e) Subsequent filing requirements. Upon the Director's issuance of a notice commencing an applicant's pre-filing process, the applicant must:
(3) Within 14 days:
(6) Within 30 days, file an updated list of all Federal, State, Tribal, and local agencies permits and authorizations that are necessary to construct the proposed facilities. The list must include: