18 C.F.R. § 5.18
(a) General content requirements. Each license application filed pursuant to this part must:
(2) Identify (providing names and mailing addresses):
(ii) Every city, town, or similar local political subdivision:
(iii) Every irrigation district, drainage district, or similar special purpose political subdivision:
(3)
(i) For a license (other than a license under section 15 of the Federal Power Act) state that the applicant has made, either at the time of or before filing the application, a good faith effort to give notification by certified mail of the filing of the application to:
(4)
(ii) This application is executed in the:
State of County of By: (Name) (Address) being duly sworn, depose(s) and say(s) that the contents of this application are true to the best of (his or her) knowledge or belief. The undersigned Applicant(s) has (have) signed the application this ____ day of __________________, 2______. (Applicant(s)) By: Subscribed and sworn to before me, a [Notary Public, or title of other official authorized by the state to notarize documents, as appropriate] this ____ day of ____________________, 2______. /SEAL [if any] (Notary Public, or other authorized official)
(5) Contain the information and documents prescribed in the following Sections of this chapter, except as provided in paragraph (b) of this Section, according to the type of application:
(b) Exhibit E—Environmental Exhibit. The specifications for Exhibit E in §§ 4.41, 4.51, or 4.61 of this chapter shall not apply to applications filed under this part. The Exhibit E included in any license application filed under this part must address the resources listed in the Pre-Application Document provided for in § 5.6; follow the Commission's “Preparing Environmental Assessments: Guidelines for Applicants, Contractors, and Staff,” as they may be updated from time-to-time; and meet the following format and content requirements:
(3) Applicable laws. Include a discussion of the status of compliance with or consultation under the following laws, if applicable:
(4) Project facilities and operation. Provide a description of the project to include:
(5) Proposed action and action alternatives.
(i) The environmental document must explain the effects of the applicant's proposal on resources. For each resource area addressed include:
(ii) The environmental document must contain, with respect to the resources listed in the Pre-Application Document provided for in § 5.6, and any other resources identified in the Commission's scoping document prepared pursuant to the National Environmental Policy Act and § 5.8, the following information, commensurate with the scope of the project:
(iii) The applicant must also provide in the Environmental Document:
(c) Exhibit H. The information required to be provided by this paragraph (c) must be included in the application as a separate exhibit labeled “Exhibit H.”
(1) Information to be provided by an applicant for new license: Filing requirements—(i) Information to be supplied by all applicants. All Applicants for a new license under this part must file the following information with the Commission:
(A) A discussion of the plans and ability of the applicant to operate and maintain the project in a manner most likely to provide efficient and reliable electric service, including efforts and plans to:
(1) Increase capacity or generation at the project;
(2) Coordinate the operation of the project with any upstream or downstream water resource projects; and
(3) Coordinate the operation of the project with the applicant's or other electrical systems to minimize the cost of production.
(B) A discussion of the need of the applicant over the short and long term for the electricity generated by the project, including:
(1) The reasonable costs and reasonable availability of alternative sources of power that would be needed by the applicant or its customers, including wholesale customers, if the applicant is not granted a license for the project;
(2) A discussion of the increase in fuel, capital, and any other costs that would be incurred by the applicant or its customers to purchase or generate power necessary to replace the output of the licensed project, if the applicant is not granted a license for the project;
(3) The effect of each alternative source of power on:
(i) The applicant's customers, including wholesale customers;
(ii) The applicant's operating and load characteristics; and
(iii) The communities served or to be served, including any reallocation of costs associated with the transfer of a license from the existing licensee.
(C) The following data showing need and the reasonable cost and availability of alternative sources of power:
(1) The average annual cost of the power produced by the project, including the basis for that calculation;
(2) The projected resources required by the applicant to meet the applicant's capacity and energy requirements over the short and long term including:
(i) Energy and capacity resources, including the contributions from the applicant's generation, purchases, and load modification measures (such as conservation, if considered as a resource), as separate components of the total resources required;
(ii) A resource analysis, including a statement of system reserve margins to be maintained for energy and capacity; and
(iii) If load management measures are not viewed as resources, the effects of such measures on the projected capacity and energy requirements indicated separately;
(iv) For alternative sources of power, including generation of additional power at existing facilities, restarting deactivated units, the purchase of power off-system, the construction or purchase and operation of a new power plant, and load management measures such as conservation: The total annual cost of each alternative source of power to replace project power; the basis for the determination of projected annual cost; and a discussion of the relative merits of each alternative, including the issues of the period of availability and dependability of purchased power, average life of alternatives, relative equivalent availability of generating alternatives, and relative impacts on the applicant's power system reliability and other system operating characteristics; and the effect on the direct providers (and their immediate customers) of alternate sources of power.
(F) A comparison of the impact on the operations and planning of the applicant's transmission system of receiving or not receiving the project license, including:
(1) An analysis of the effects of any resulting redistribution of power flows on line loading (with respect to applicable thermal, voltage, or stability limits), line losses, and necessary new construction of transmission facilities or upgrading of existing facilities, together with the cost impact of these effects;
(2) An analysis of the advantages that the applicant's transmission system would provide in the distribution of the project's power; and
(3) Detailed single-line diagrams, including existing system facilities identified by name and circuit number, that show system transmission elements in relation to the project and other principal interconnected system elements. Power flow and loss data that represent system operating conditions may be appended if applicants believe such data would be useful to show that the operating impacts described would be beneficial.
(K) The applicant's electricity consumption efficiency improvement program, as defined under Section 10(a)(2)(C) of the Federal Power Act, including:
(1) A statement of the applicant's record of encouraging or assisting its customers to conserve electricity and a description of its plans and capabilities for promoting electricity conservation by its customers; and
(2) A statement describing the compliance of the applicant's energy conservation programs with any applicable regulatory requirements.
(ii) Information to be provided by an applicant licensee. An existing licensee that applies for a new license must provide:
(B) A statement of measures taken or planned by the licensee to ensure safe management, operation, and maintenance of the project, including:
(1) A description of existing and planned operation of the project during flood conditions;
(2) A discussion of any warning devices used to ensure downstream public safety;
(3) A discussion of any proposed changes to the operation of the project or downstream development that might affect the existing Emergency Action Plan, as described in subpart C of part 12 of this chapter, on file with the Commission;
(4) A description of existing and planned monitoring devices to detect structural movement or stress, seepage, uplift, equipment failure, or water conduit failure, including a description of the maintenance and monitoring programs used or planned in conjunction with the devices; and
(5) A discussion of the project's employee safety and public safety record, including the number of lost-time accidents involving employees and the record of injury or death to the public within the project boundary.
(iii) Information to be provided by an applicant who is not an existing licensee. An applicant that is not an existing licensee must provide:
(B) A statement of the applicant's plans to manage, operate, and maintain the project safely, including:
(1) A description of the differences between the operation and maintenance procedures planned by the applicant and the operation and maintenance procedures of the existing licensee;
(2) A discussion of any measures proposed by the applicant to implement the existing licensee's Emergency Action Plan, as described in subpart C of part 12 of this chapter, and any proposed changes;
(3) A description of the applicant's plans to continue safety monitoring of existing project instrumentation and any proposed changes; and
(4) A statement indicating whether or not the applicant is requesting the licensee to provide transmission services under section 15(d) of the Federal Power Act.
[Order 2002, 68 FR 51121, Aug. 25, 2003; 68 FR 61742, Oct. 30, 2003; 68 FR 69957, Dec. 16, 2003; Order 699, 72 FR 45324, Aug. 14, 2007; Order 756, 77 FR 4894, Feb. 1, 2012; Order 877, 86 FR 42715, Aug. 5, 2021]