(a) Corrective measures. For items identified during a periodic inspection or comprehensive assessment as requiring corrective action, the following conditions apply:
(1) Corrective plan and schedule.
- (i) Not later than 60 days after a report on a periodic inspection or comprehensive assessment is filed with the Regional Engineer, the licensee must submit to the Regional Engineer a plan and schedule for addressing the recommendations of the independent consultant(s) and for investigating, designing, and carrying out any corrective measures that the licensee proposes to implement.
- (ii) The plan and schedule may include any proposal, including taking no action, that the licensee considers a preferable alternative to any corrective measure recommended in the report of the independent consultant(s). Any proposed alternative must be accompanied by the licensee's complete justification and detailed analysis and evaluation in support of that alternative.
- (2) Carrying out the plan. The licensee must complete all corrective measures in accordance with the plan and schedule submitted to, and approved or modified by, the Regional Engineer, and on an annual basis must submit a status report on the corrective measures until all have been completed.
- (3) Extension of time. For good cause shown, the Regional Engineer may extend the time for filing the plan and schedule required by this section.