13 C.F.R. § 305.6
(a) Recipients shall seek EDA's prior written approval to use alternate construction procurement methods to the traditional design/bid/build procedures (including lump sum or unit price-type construction contracts). These alternate methods may include design/build, construction management at risk, and force account. If an alternate method is used, the Recipient shall submit to EDA for approval a construction services procurement plan and the Recipient must use a design professional to oversee the process. The Recipient shall submit the plan to EDA prior to advertisement for bids and shall include the following, as applicable:
[71 FR 56675, Sept. 27, 2006, as amended at 73 FR 62866, Oct. 22, 2008; 79 FR 76131, Dec. 19, 2014; 82 FR 57054, Dec. 1, 2017]