13 C.F.R. § 126.617 – Who decides contract disputes arising between a qualified HUBZone SBC and a contracting activity after the award of a HUBZone contract? | Midpage
§ 126.617
13 C.F.R. § 126.617
Who decides contract disputes arising between a qualified HUBZone SBC and a contracting activity after the award of a HUBZone contract?
Effective Jun 23, 2004Published May 24, 200469 FR 29426
Viewing an earlier version · effective Jun 23, 2004View current
For purposes of the Disputes Clause of a specific HUBZone contract, the contracting activity will decide disputes arising between a qualified HUBZone SBC and the contracting activity.