12 C.F.R. § 217.403
(a) General. Subject to § 217.400(b)(2), a company identified as a global systemically important BHC pursuant to § 217.402 must calculate its GSIB surcharge on an annual basis by December 31 of each year. For any given year, subject to paragraph (d) of this section, the GSIB surcharge is equal to the greater of:
(b) Method 1 surcharge—(1) General. The method 1 surcharge of a global systemically important BHC is the amount set forth in Table 1 of this section that corresponds to the global systemically important BHC's method 1 score, calculated pursuant to § 217.404.
| Method 1 score | Method 1 surcharge |
|---|---|
| Below 130 | 0.0 percent. |
| 130—229 | 1.0 percent. |
| 230—329 | 1.5 percent. |
| 330—429 | 2.0 percent. |
| 430—529 | 2.5 percent. |
| 530—629 | 3.5 percent. |
(2) Higher method 1 surcharges. To the extent that the method 1 score of a global systemically important BHC equals or exceeds 630 basis points, the method 1 surcharge equals the sum of:
(c) Method 2 surcharge—(1) General. The method 2 surcharge of a global systemically important BHC is the amount set forth in Table 2 of this section that corresponds to the global systemically important BHC's method 2 score, calculated pursuant to § 217.405.
| Method 2 score | Method 2 surcharge |
|---|---|
| Below 130 | 0.0 percent. |
| 130—229 | 1.0 percent. |
| 230—329 | 1.5 percent. |
| 330—429 | 2.0 percent. |
| 430—529 | 2.5 percent. |
| 530—629 | 3.0 percent. |
| 630—729 | 3.5 percent. |
| 730—829 | 4.0 percent. |
| 830—929 | 4.5 percent. |
| 930—1029 | 5.0 percent. |
| 1030—1129 | 5.5 percent. |
(2) Higher method 2 surcharges. To the extent that the method 2 score of a global systemically important BHC equals or exceeds 1130 basis points, the method 2 surcharge equals the sum of: