Ariz. Admin. Code § R19-3-552
B. If a contractor fails to submit data to support a contract modification in the form required and within the time-frames required, the procurement officer may:
1. Reject the contract modification; or
2 Set the amount of the contract modification subject to the contractor’s rights under A.R.S. Title 41, Chapter 6, Article 10.
Section R19-3-552 renumbered from R19-3-545 and amended effective December 16, 1997 (Supp. 97-4). Section repealed; new Section made by final rulemaking at 12 A.A.R. 4495, effective January 6, 2007 (Supp. 06-4). Section R19-3-552 renumbered to R19-3-555; new Section R19-3-552 renumbered from R19-3-549 by final rulemaking at 19 A.A.R. 1641, effective August 4, 2013 (Supp. 13-2).