Verizon New York, Inc. v. Sprint PCSVerizon New York, Inc. v. Sprint PCS
Inasmuch as there is no indication that plaintiff had reason to know, or should have known, that defendants would refuse to pay the contract price, its cause of action for breach of contract
McGuire, J., dissents in a memorandum as follows: Supreme Court correctly determined that plaintiff’s action is time-barred. Accordingly, I respectfully dissent.
On April 6, 1999, the parties entered into a contract pursuant to which plaintiff agreed to diversify cable routes for defendant. Under the contract, plaintiff estimated that the cost of the work would be $100,000, and defendant was to pay that amount within 60 days of the date of the contract. The contract contemplated that the work might be completed either over or under the estimate; plaintiff was to bill defendant for any additional cost over the $100,000 estimate and, if the work cost less than the estimate, refund to defendant any overpayment. While the $100,000 payment was not made by defendant within the 60-day period, the work began in July 1999 and was completed in April 2000. By an invoice dated October 10, 2000, plaintiff billed defendant $109,800 for the work and demanded payment by November 11, 2000. Defendant never paid the invoice.
On June 21, 2006, plaintiff commenced this action to recover the $109,800. In lieu of answering, defendant moved to dismiss the complaint pursuant to
“In contract cases, the cause of action accrues and the Statute of Limitations begins to run from the time of the breach” (John J. Kassner & Co. v City of New York, 46 NY2d 544, 550 [1979]; see Ely-Cruikshank Co. v Bank of Montreal, 81 NY2d 399 [1993]). Where a cause of action is asserted to recover a sum of money owed pursuant to a contract, the cause of action
Here, there was no condition precedent to final payment under the contract. Thus, plaintiff’s cause of action accrued when the work it was retained to perform was completed. According to plaintiff, the work was completed in April 2000. Since the action was not commenced until June 2006, after the six-year statute of limitations had expired (see
The majority’s assertion that the cause of action accrued on November 10, 2000, the date by which plaintiff, in its October 10, 2000 invoice, demanded payment, is erroneous. As discussed above, absent a condition precedent to final payment, a cause of action for breach of contract accrues “on completion of the actual physical work” (Phillips Constr. Co., 61 NY2d at 951). John J. Kassner & Co. (supra) and Matter of Bombardier Transp. (Holdings) USA, Inc. v Telephonics Corp. (14 AD3d 358 [2005]), cited by the majority, both involved contracts that imposed conditions precedent to payment and the plaintiffs’ causes of action for breach of contract did not accrue until those conditions were fulfilled. Moreover, in concluding that plaintiff’s
Accordingly, I would affirm the order.