Lead Opinion
Memorandum.
The order of the Appellate Division should be reversed, with costs, plaintiff’s motion to strike the tenth defense (Statute of Limitations), denied, and defendant’s motion to dismiss the action as time barred under the six-year Statute of Limitations (CPLR 213, subd 2), granted.
This action arises оut of the construction of an ice skating rink at Clove Lake Park, Staten Island, New York. The provisions of article 53
In arguing as to the date of accrual of the causes of action alleged in the complaint plaintiff points to certain language lifted out of article 42 of the contract (entitled “Final Pаyment”): “[T]he certification of the Engineer [on the final payment voucher] and the approval of the Commissioner thereof, shall be a condition precedent to the right of the Contractor to receive any money thereunder.” (Emphasis is that of plaintiff contractor.) This provision is explicitly made applicable, hоwever, only to the right to receive payment under the final voucher; it has no relation to the institution of actions for breach of obligations other than the obligation to make payment under that voucher. The present action for damаges for the cost of additional work occasioned by but not included in change orders, for extra
The Statute of Limitations prescribed in CPLR 213 (subd 2) began to run on completion of the actual physical work even though incidental matters relating to the project remained open (State of New York v Lundin,
Notes
. Article 53 provided in pertinent part:
“article 53. claims and actions thereon. No claim against the City for damages for breach of contract or compensation for extra work shall be made or asserted in any action or proceeding at law or in еquity, unless the Contractor shall have strictly complied with all requirements relating to the giving of notice and of information with respect to such claims all as hereinbefore provided.
“Nor shall any such action or proceeding be instituted or maintаined on any such claims unless such action or proceeding be commenced within one year after the date of the filing in the office of the Comptroller of the final payment voucher pursuant to Article 42”.
This section contains no prеscription with reference to the time of accrual of claims arising under the contract.
. In response to the dissent it may be noted that plaintiff’s first cause of action is not for payment of moneys to which the contractor was entitled undеr the terms of change orders executed by the parties, entitlement to which would, of course, be subject to audit by the city. The first cause of action rather seeks to recover damages, over and above the amounts fixed in change orders executed by the parties, allegedly sustained in consequence of additional work occasioned by the change orders. Accordingly, this cause of action, too, accrued on completion of the physical work.
Dissenting Opinion
(dissenting in рart). I cannot agree that plaintiff’s complaint should be dismissed in its entirety. Under one of plaintiff’s causes of action, given the terms of the contract and the parties’ actions insofar as reflected in the record, plaintiff suffered no injury until defendant determined that it would not pay all of the
In April, 1967, plaintiff was awarded a contract to build an ice skating rink at Clove Lake Park in Staten Island. This was not a fixed-sum contract, however. Instead, defendant used a unit-price contract under which the actual cost was to be determined by defendant after construction was completed. For various reasons, plaintiff was not able to present the premises for a final inspeсtion until September 28, 1971. It is undisputed that, to some extent, the delay in completion is attributable to defendant.
Final payment was to proceed by plaintiff’s submitting a requisition for approval. Once defendant, through its engineer, determined the amount to bе paid, a final voucher was to be certified, approved and filed, whereupon plaintiff would be paid. For reasons not apparent from the record or the briefs, the final requisition was not approved until late 1977.
This action was cоmmenced in January, 1978. The complaint pleads four causes of action. The first cause alleges that, by reason of defendant’s change orders, plaintiff was required to provide extra materials subject to the unit-price computations and that it had been underpaid $164,572.38. The second cause of action seeks to recover $132,896.69 for the reasonable value of additional work that was required by defendant’s modifications and other conduct. The third claims losses of $935,352.77 in that defendаnt caused the project’s delay and thereby caused plaintiff to expend additional sums for labor and overhead, as well as restricting its bondability and available working capital. Lastly, plaintiff pleaded that defendant’s conduct constitutеd a total breach so as to vitiate the contract and entitle plaintiff to recover in quantum meruit, with the balance due being $1,134,609.91.
Defendant answered and asserted that the action was barred by the Statute of Limitations. Both courts below denied a motion to dismiss the complaint.
A cause of action in contract accrues and the Statute of Limitations begins to run when a breach occurs (Kassner & Co. v City of New York,
In pleading the Statute of Limitations, a defendant raises an affirmative defense on which it has the burden of proof (see Goncalves v Regent Int. Hotels,
Plaintiff’s third and fourth causes of action should be dismissed as time barred. The rights that plaintiff seeks to enforce in the last two causes of action were violated, if at аll, by September 28, 1971, when plaintiff had substantially performed the contract. The “payments” plaintiff seeks there were not subject to any condition before they became “due”. The injuries claimed were complete, and plaintiff could havе sued that very day.
The second cause of action, to recover for additional work, is problematic. Plaintiff’s right to payment under the unit-cost contract was subject to audit, so that a breach by defendant in making final payment would not ocсur until it informed plaintiff of the results of that audit (see Kassner & Co. v City of New York,
Plaintiff’s first cause of action, however, is a different matter. Essentially, it seeks recovery for the extra work
The majority relies on State of New York v Lundin (
Nor is the majority’s distinction (majority opn, p 951) between a suit on “liability * * * arising out of the contract” and one for “nonperformance of payment” understood. The majority apparently proceeds on the theory that there is a difference in suing for breach of contract and on presenting a claim arising under the contract (p 951, n 2). No matter how one phrases the description, thе gravamen of any contract action is that one party claims that it is owed certain obligations because of the agreement and that the other party has not performed those obligations. No one
Accordingly, the order of the Appellate Division should be modified, without costs, by striking plaintiff’s sеcond, third, and fourth causes of action for the reasons stated above, and as so modified, affirmed. The question certified should be answered in the negative.
Judges Jasen, Jones, Meyer and Kaye concur; Chief Judge Cooke dissents in part and votes to modify by dismissing the plaintiff’s second, third and fourth causes of action in an opinion in which Judge Wachtler concurs; Judge Simons taking no part.
Order reversed, with costs, plaintiff’s motion to strike the tenth defense denied and defendant’s motion to dismiss the action granted in a memorandum. Question certified answered in the negative.
