URS CORPORATION, еt al. v. FORT MYER CONSTRUCTION CORPORATION
No. 31, Sept. Term, 2016
Court of Appeals of Maryland.
March 24, 2017
156 A.3d 753
Gerard J. Emig (Erin Schiesel, Gleason, Flynn, Emig & Fogleman, Chartered, Rockville, MD), on brief, for respondent.
Barbera, C.J., Greene, Adkins, McDonald, Watts, Hotten, Lynne A. Battaglia (Senior Judge, Specially Assigned), JJ.
McDonald, J.
This appeal concerns the application of two rules. One rule is critical to the determination of appellate jurisdiction. The other sets the standard for imposing monetary sanctions when a litigant prosecutes a case in bad faith or without substantial justification.
Petitioner Maryland-National Capital Park and Planning Commission (“the Commission“) contracted with Respondent Fort Myer Construction Corporation (“Fort Myer“) to build a pedestrian bridge in accordance with design documents provided by the Commission. After running into several issues that delayed construction of the bridge, Fort Myer sued the Commission claiming that the design documents were at fault. The Commission impleaded Petitioner URS Corporation (“URS“), the engineering firm that crеated the design documents, on the theory that URS was contractually obligated to defend the Commission against Fort Myer‘s claims and would be liable for any damages. URS, in turn, countersued the Commission for contract payments that the Commission had withheld from URS.
Fort Myer‘s original complaint was eventually dismissed by the Circuit Court without prejudice, but the claims between the Commission and URS went to trial. URS and the Commission each prevailed on their claims against each other. Both the Commission and URS asked the court to award monetary sanctions against their common adversary—Fort Myer—under
All three parties appealed those rulings. The timing of the appeals of URS and the Commission, and its effect on appellate jurisdiction, became the dispositive issue for those appeals. The Court of Special
URS and the Commission ask us to reverse the decision of the Court of Special Appeals on the sanctions awards, proposing both procedural and substantive grounds for doing so.
The procedural issue turns on the requirement of
The substantive issue turns on the merits of the Circuit Court‘s conclusion that Fort Myer had prosecuted its complaint “without substantial justification.” The Court of Special Appeals found that conclusion to be unsupported by the factors cited by the Circuit Court and therefore clearly erroneous—which rendered the Circuit Court‘s award of sanctions an abuse of discretion. URS and the Commission argue that, even if there was appellate jurisdiction of Fort Myer‘s appeal, the Court of Special Appeals should be reversed because the Circuit Court acted within its discretion in awarding sanctions.
We hold that the Court of Special Appeals properly exercised jurisdiction to decide the appeal of Fort Myer (and in fact had jurisdiction to decide those of URS and the Commission). Because the separate document requirement is intended to clarify the deadline for filing an appeal—not to create delay for its own sake—the separate document requirement may be waived when waiver does not prejudice appeal rights. Such is the case in this appeal. As for the sanctions awards against Fort Myer, we agree with the Court of Special Appeals that the Circuit Court‘s explanation of its reasoning did not support a finding that Fort Myer‘s pursuit of its claim was “without substantial justification.”
I
Background
A. Proceedings in the Circuit Court
A Bridge Contract Beset by Delays
In 2008, Fort Myer contracted with the Commission to build a pedestrian bridge over Veirs Mill Road in Montgomery County. The contract required Fort Myer to construct the bridge according to design documents that had been prepared for the Commission by URS under a separate, earlier contract between the Commission and URS. Several problems arose during construction, and completion of the bridge was delayed by more than four months.
Fort Myer Sues the Commission
Alleging that the construction issues and delay resulted from problems with the design documents, Fort Myer sued the Commission on October 12, 2012, in the Circuit Court for Montgomery County. In Count I of the complaint, Fort Myer asserted breach of contract and sought $876,822.03 in damages related to Fort Myer‘s increased costs and lost profits. In Count II,
The Commission Impleads URS; URS Counterclaims
Some months later, on March 27, 2013, the Commission filed a third-party complaint against URS pursuant to
URS answered the third-party complaint, asserting various defenses to the claims of both the Commission and Fort Myer.1 URS also asserted a counterclaim against the Commission, alleging that the Commission owed URS $103,420, which was due for services URS had provided to the Commission, but which the Commission had withheld in light of the impending claim by Fort Myer.
Thereafter, the parties engaged in pretrial discovery. Various discovery disputes arose, which resulted in requests for sanctions. The Circuit Court referred some of those disputes to a special master, and ultimately adopted the recommendations of the master, which did not include sanctions.
Dismissal of Fort Myer‘s Complaint without Prejudice
On February 26, 2014, after more than a year of litigation, URS moved to dismiss Fort Myer‘s complaint, or, in the alternative, for summary judgment. URS argued that Fort
Myer‘s complaint was deficient under a State statute because Fort Myer had not filed a certificate of a qualified expert (“CQE“) in conjunction with its complaint. See
Fort Myer initially opposed the URS motion. In its response, it noted that, given the statutory definition of “claim,” the CQE requirement applies only when a claim is “filed ... against a licensed professional [engineer] or the employer, partnership, or other entity through which the licensed professional [engineer] performed professional services ... [and] based on the licensed professional‘s alleged negligent act or omission in rendering professional services....”
On March 11, 2014, a few days after the summary judgment motions were filed and shortly before the scheduled trial, Fort Myer withdrew its opposition to URS‘s motion to dismiss, implicitly agreed that the CQE requirement applied to its comрlaint, and consented to dismissal of its complaint without prejudice. In a subsequent filing and at two pretrial hearings, counsel for Fort Myer explicitly agreed that the CQE statute applied and stated that the court was required to dismiss its complaint without prejudice. Unsurprisingly, URS and the Commission agreed that the complaint should be dismissed, but argued that the dismissal should be with prejudice. (The Commission took the position that the CQE statute did not apply to Fort Myer‘s claim, but that its complaint should be dismissed with prejudice for other reasons set out in its summary judgment motion).
At a motions hearing on March 31, 2014, the Circuit Court decided to dismiss Fort Myer‘s complaint without prejudice. The third-party claim of the Commission against URS and URS‘s counterclaim against the Commission survived the dismissal of Fort Myer‘s complaint and remained pending, however.
Sanctions Awards against Fort Myer
URS and the Commission pursued an award of sanctions against Fort Myer with respect to the ill-fated complaint that had been dismissed without prejudice. Their respective motions were brought under
The Commission argued that it was entitled to judgment as a matter of law on Count II of the complaint because, among other things, Fort Myer had failed to identify in discovery an expert who could testify that the bridge design was defective. The Commission also filed a motion for summary judgment with respect to both counts of complaint, based on an argument that Fort Myer had previously released or waived its claims. court finds that a party acted “in bad faith or without substantial justification” in maintaining or defending a proceeding.4
In its motion, the Commission alleged, among other things, that Fort Myer had failed to retain expert witnesses despite representing that it had done so; that Fort Myer‘s witnesses failed to appear for properly-noticed depositions; and that Fort Myer proceeded with depositions of Commission witnesses despite “full knowledge that its complaint was fatally flawed” because of the failure to file a CQE. The Commission sought recovery of the costs and attorney‘s fees incurred in defending against Fort Myer‘s complaint, which it computed to be $376,597.68. URS joined in the Commission‘s motion and sought recovery of its attorney‘s fees and costs incurred in the amount of $248,638.31. Fort Myer opposed the motions, arguing that its claims were made neither in bad faith nor without substantial justification.
The Circuit Court held a hearing on the motions for sanctions on April 28, 2014. Ruling from the bench at the hearing, the
In explaining its reasoning, the court stated that it was “not a question of whether [Fort Myer] had a right to pursue [its] case,” but rather whether it had “a legal obligation to do it without fatal flaws.” The court reiterated that it believed that the failure to file a CQE by itself would not merit sanctions, but that the failure to do so, when coupled with the discovery violations, the dismissal of the complaint on the eve of trial, and Fort Myer‘s subsequent motion seeking sanctions against
the Commission, had led the court to conclude that a sanctions award against Fort Myer was appropriate. The court summarized that “there has been a [Rule] 1-341 violation taking place in its entirety, discovery violations, conduct of counsel, lacking substantial justification.” While the court stated that there was “lack of substantial justification,” it conceded that Fort Myer‘s underlying claim “may be a cause of action in some other court, some other day, for some other judge to decide.” The court explicitly declined to find that Fort Myer had acted in bad faith.
At the hearing the court awarded $376,597.68 to the Commission and $248,638.31 to URS—the total amounts requested by each. The court incorporated its oral ruling in a written order dated May 29, 2014, which included a finding that the “conduct of Fort Myer in maintaining [its] case was without substantial justification.” The court clerk entered two separate written documents, each entitled Notice of Judgment, on June 2, 2014—one memorializing the award in favor of URS and the other the award in favor of the Commission.
Trial of Claims Between the Commission and URS
In the meantime, the Commission and URS had continued to litigate their claims against one another. The Circuit Court held a bench trial on those claims on April 7 and 8, 2014. In an Order and Opinion issued on May 5, 2014, the Circuit Court decided in URS‘s favor on its counterclaim against the Commission and found that the Commission owed URS $103,420 with respect to the contract payments that the Commission had withheld from URS. The clerk entered a separate document in the record entitled Notice of Judgment in that amount.
In the same opinion, the Circuit Court also decided in the Commission‘s favor on its third-party claim against URS concerning the URS‘s contractual duty to defend the Commission against Fort Myer‘s claims. The court did not compute the amount of damages at that time or enter a separate document incorporating its judgment.5
Some months later, on December 18, 2014, the Circuit Court held a hearing on the amount of damages owed by URS to the Commission on the duty-to-defend claim.6 At that hearing, the Circuit Court
Motion for Reconsideration of Sanctions Awards
On November 10, 2014,7 Fort Myer asked the Circuit Court to reconsider the awards of sanctions, arguing that its alleged bad acts during the litigation were not relevant to the question of whether its claim was filed or maintained “without substantial justification.” Opposing this motion, the Commission and URS again pointed to the alleged discovery violations and the lack of expert witnesses and a CQE.
The Circuit Court took up the motion at the hearing on December 18, 2014—the same hearing at which it determined the damages on the Commission‘s third-party claim against
URS. In a subsequent order entered February 19, 2015, the court denied the motion for reconsideration, noting that “[n]o new facts or legal argument [were] presented in the motion” and “[n]o good reason [wa]s presented” to reconsider the previous decision.
B. Proceedings in the Court of Special Appeals
Appeals Noted
In March 2015, each party filed a notice of appeal. In their respective notices of appeal, Fort Myer indicated that it was challenging the award of sanctions and URS stated that it was challenging the Circuit Court‘s ruling that it owed the Commission a duty to defend.8 The Commission also filed a notice of appeal but ultimately did not pursue its appeal—i.e., it did not file an appеllant‘s brief, although it did file appellee briefs in response to briefs filed by Fort Myer and URS.
The appeals were consolidated in the Court of Special Appeals. Although no party had addressed the issue of timeliness of the appeals in their briefs, the issue was raised by the court at oral argument.
April 1 Opinion
On April 1, 2016, in an unreported opinion (“April 1 opinion“), the Court of Special
untimely. (The Commission‘s appeal was also dismissed as untimely, although the court acknowledged that the Commission had not pursued its appeal). However, the intermediate appellate court regarded Fort Myer‘s appeal as timely and reached the merits of that appeal, reversing the sanctions awards.
In the April 1 opinion, the court concluded that URS‘S appeal was late because its notice of appeal was filed in March 2015, which was more than 30 days after December 18, 2014—the date that the Circuit Court had ruled from the bench and assessed $352,355.68 in damages in favor of the Commission, a ruling rеflected on the docket that same day.
With respect to Fort Myer‘s appeal of the sanctions awards, the Court of Special Appeals held that the basis of the Circuit Court‘s ruling—that Fort Myer had conducted the litigation without substantial justification—was clearly erroneous. The court observed that the Circuit Court‘s decision turned largely on Fort Myer‘s failure to file a CQE and Fort Myer‘s subsequent decision, shortly before trial, to agree to dismissal of its complaint for that reason. The intermediate appellate court stated that the question whether Fort Myer was required to file a CQE was “fairly debatable” under the case law, as evidenced by the fact that URS had raised the issue relatively late in the proceedings and that the Commission itself had initially taken the position that a CQE was not required.
The Court of Special Appeals found the Circuit Court‘s other “sweeping and nonspecific observations” insufficient to support a finding that Fort Myer had prosecuted its claim without substantial justificаtion. While the Circuit Court had expressed its frustration with the discovery disputes, it had not identified specific violations. Moreover, the Court of Special Appeals observed, the discovery rules provide their own sanctions for such violations, but the Circuit Court had accepted the special master‘s recommendations and declined to impose any such sanctions. Finally, the intermediate appellate court also opined that, if the Circuit Court believed that Fort Myer‘s own motion for sanctions against the Commission was itself without substantial justification, the sanctions award in favor of the Commission should have been limited to the expenses incurred in defending that motion.
In light of its conclusion that the Circuit Court had been clearly erroneous in finding that Fort Myer acted without substantial justification, the Court of Special Appeals held that the trial court had abused its discretion in awarding sanctions under
Motion for Reconsideration
Ten days after the April 1 opinion was issued, URS filed a motion asking the Court of Special Appeals to reconsider its dismissal of URS‘s appeal. URS pointed out that, although the Circuit Court had announced its computation of the damages owed by URS to the Commission from the bench on December 18, 2014, that judgment had never been reduced to written form in a separate document as required by
April 28 Opinion
In resрonse to the motion for reconsideration, the Court of Special Appeals withdrew its April 1 opinion and issued a partially revised unreported opinion on April 28, 2016 (“April 28 opinion“). In the April 28 opinion, the court agreed with URS that the absence of a separate document memorializing the December 18, 2014 judgment meant that final judgment had not yet been entered in accordance with
C. Petitions for Certiorari to Court of Appeals
URS and the Commission each petitioned this Court for a writ of certiorari, which we granted. URS and the Commission challenge the intermediate appellate court‘s reversal of the sanctions awards against Fort Myer on two bases: (1) that the Court of Special Appeals lacked any jurisdiction to сonsider Fort Myer‘s appeal because there was not a final judgment—essentially tracking the reasoning of the intermediate appellate court when it dismissed their own appeals—and (2) that, even if there was a final judgment, the Court of Special Appeals erred in reversing the awards of sanctions against Fort Myer.
II
Discussion
For reasons outlined below, we agree with URS and the Commission that, in this case, the question whether there was an appealable final judgment for Fort Myer merits the same answer as whether there was an appealable final judgment for URS and the Commission. In our view, the answer is that there was appellate jurisdiction over all of these appeals. The only element lacking for purposes of entry of final judgment under
Special Appeals should have regarded the separate documеnt requirement of
As to the second issue, we agree with the Court of Special Appeals that the Circuit Court‘s finding that Fort Myer maintained its action without substantial justification was clearly erroneous, and, correspondingly, that the Circuit Court abused its discretion when it awarded sanctions and denied the Fort Myer‘s motion to reconsider those sanctions.
A. Whether There Was Appellate Jurisdiction
URS and the Commission first contend that the decision of the Court of Special Appeals—expressed in both the April 1 opinion and the April 28 opinion—to overturn the sanctions awards against Fort Myer must be reversed because the intermediate appellate court lacked appellate jurisdiction over Fort Myer‘s appeal. Appellate jurisdiction was lacking, they argue, because the Circuit Court failed to enter a final judgment in accordance with
We agree that the various appeals in this case should be treated the same for purposes of appellate jurisdiction.10 But we reach a different outcome than the Court of Special Appeals. We conclude that the separate document required under
Special Appeals properly had jurisdiction over Fort Myer‘s appeal. Therefore, we uphold that court‘s exercise of jurisdiction over Fort Myer‘s appeal of the
The Final Judgment Rule
As a general rule, under Maryland law, litigants may appeal only from what is known as a “final judgment.”
The Separate Document Requirement
One of the procedural steps for entry of final judgment—the “separate document requirement“—requires the trial court to memorialize the judgment in a separate document that is signed by either the court clerk or the judge and
entered in the docket.
As is the practice in the federal courts, courts in Maryland “mechanically apply” the separate document requirement when determining the timeliness of an appeal. Byrum v. Horning, 360 Md. 23, 32, 756 A.2d 560 (2000) (quoting Bankers Trust Co. v. Mallis, 435 U.S. 381, 386 (1978)).
That is, if the trial court has not complied with the separate document requirement of
Waiver of the Separate Document Requirement
There are certain circumstances, however, when the separate document requirement may be waived in order to preserve an аppeal, rather than eliminate it as untimely. Again, this Court has followed the lead of the United States Supreme Court in developing a concept of waiver of the separate document requirement when it is applied to preserve an appeal.
The leading Supreme Court decision is Bankers Trust Co. v. Mallis, 435 U.S. 381 (1978). In Bankers Trust, the Supreme Court determined that the purpose of the federal separate document requirement—i.e., “[c]ertainty as to timeliness“—would not be advanced by dismissing an appeal where the separate document was “accidentally not ... entered” and where a technical application of the separate document requirement would only result in unnecessary delay. Bankers Trust, 435 U.S. at 385-86. The Supreme Court noted that, otherwise, upon dismissal of the appeal, the case would return to the trial court where that court would simply file the separate document from which a timely appeal would then be taken. The Supreme Court observed “nothing but delay would flow from” this series of actions and that “[w]heеls would spin for no practical purpose.” Id. at 385. This Court applied that
In Suburban Hospital, a jury returned a special verdict which, under
Adopting the reasoning of the Supreme Court, the Court in Suburban Hospital determined that the separate document requirement of
Although in Suburban Hospital this Court did not “undertak[e] to set the outer limits of the availability of waiver of the separate document requirement in order to preserve an appeal in Maryland,” 362 Md. at 156, further clarity was offered in Taha v. Southern Management Corp., 367 Md. 564, 790 A.2d 11 (2002). There, an individual sued a property management corporation and two of its employees. After trial, the jury returned a verdict finding the corporation liable but absolving the two employees of liability. Id. at 566. A judgment order entered after trial reflected the verdict against the corporation, but there was neither a separate document nor any docket entries reflecting the verdicts in favor of the two employees. Id. at 566-67. On appeal, the corporation argued that the separate document requirement was waived bеcause the circuit court, when ruling on another motion, stated on the record that it was “clear [from the] verdict” that the jury did “not find[] the individual employees responsible.” Id. at 570. This Court, however, noting the lack of a separate document and the lack of docket entries reflecting a judgment as to the employees, refused to find such a waiver. Id. at 570-71.
The Judgment in This Case
In this case, there appears to be no dispute that the Circuit Court did not comply with the separate document requirement, and that this is the only element absent for entry of a final judgment. No party disputes the fact that the Circuit Court intended an “unqualified, final disposition of the matter in controversy” or that all claims against all parties have been adjudicated. Fort Myer‘s claim against the Commission was dismissed and the other two claims—the Commission‘s third-party claim against URS and URS‘s counterclaim
This case thus falls squarely into the framework identified in Suburban Hospital. We hold that the separate document requirement was waived and that the Court of Special Appeals had jurisdiction to consider the appeals of the Circuit Court‘s judgment. No party objected to the absence of a separate document in the Circuit Court or in the Court of Special Appeals. When URS asked that court to reconsider its initial dismissal of its appeal, URS specifically argued that the requirement was waived and no party contradicted that assertion. Unlike the situation in Taha, there is a written opinion explaining the court‘s decision on the third-party claim and the clerk entered judgment against URS on the docket, including the specific amount of damages. See Baltimore County v. Fraternal Order of Police Lodge No. 4, 439 Md. 547, 561-66 & n.13, 96 A.3d 742 (2014) (distinguishing Taha in a case involving written order and docket entry). It is evident that the Circuit Court “clearly intended [that entry] to be a final judgment.” Suburban Hospital, 362 Md. at 156.
Were we to hold that the requirement was not waived, we would remand to the Court of Special Appeals, that court would then remand to the Circuit Court, and the Circuit Court would simply file and enter the separate judgment, from which a timely appeal would then be taken. This would be a classic example of wheels spinning for no practical purpose. We hold that the separate document requirement has been waived, and that the Court of Special Appeals had appellate jurisdiction to decide Fort Myer‘s appeal.14
B. Whether the Awards of Rule 1-341 Sanctions Were Clearly Erroneous
The Circuit Court found that Fort Myer had maintained its case “without substantial justification” and, accordingly, imposed sanctions in favor of the Commission and URS under
Maryland Rule 1-341(a)
(a) Remedial Authority of Court. In any civil action, if the court finds that the conduct of any party in maintaining or defending any proceeding was in bad faith or without substantial justification, the court, on motion by an adverse party, may require the offending party or the attorney advising the conduct or both of them to pay to the adverse party the costs of the proceeding and the reasonable expenses, including reasonable attorneys’ fees, incurred by the adverse party in opposing it.
To impose sanctions under
This case involves review of a trial court‘s finding that a party acted without substantial justification. Under the case
cy.17 That standard is not met if a party has a “reasonable basis for believing that [its] claims [will] generate an issue of fact for the fact finder.”18 Nor is it met when a party advances an arguable interpretation of an ambiguous statute, even if ultimately rejected by a court.19
Application to this Case
In concluding that Fort Myer had prosecuted its action without substantial justification, the Circuit Court recited a host of factors, somewhat vaguely, as the basis for its decision.20 We agree with thе Court of Special Appeals that the factors cited by the Circuit Court do not support a finding that Fort Myer acted without substantial justification and that the Circuit Court‘s finding on that score was clearly erroneous. Given that the requisite finding was clearly erroneous, the Circuit Court abused its discretion when it awarded costs and attorney‘s fees to the Commission and URS and when it denied Fort Myer‘s motion to reconsider those awards.
As the Court of Special Appeals explained—and as the Circuit Court appeared to acknowledge at the April 28, 2014, hearing—the legal issue “at the heart of the sanctions motion” was “fairly debatable.” In its complaint, Fort Myer attributed the delays in construction of the bridge to various factors beyond its control, most notably deficiencies in the design documents provided to it by the Commission. URS and the
Commission both contended, in various ways, that Fort Myer had failed to support that claim with necessary expert opinions and that this failure revealed the absence оf any merit to its claim. In the Commission‘s words, the case was “nothing more than a shake-down seeking to extract a settlement on a claim that Fort Myer knew never had any merit.” However, the Circuit Court explicitly rejected this assessment. It specifically noted during the April 28, 2014, hearing that Fort Myer had a right to pursue its contentions and that, despite the dismissal, Fort Myer‘s claim “may be a cause of action in some other court, some other day, for some other judge to decide.”
The Circuit Court focused less on the substantive merits—or lack thereof—of Fort Myer‘s claim than on the formal statutory requirement that plaintiffs in certain cases must file a CQE, on Fort Myer‘s alleged failure to designate an expert witness,21 and on the various discovery disputes
As the Court of Special Appeals noted, it was a “fairly debatable legal question” whether or not Fort Myer was required to file a CQE with its complaint. Under the statute, the CQE requirement applies only to a claim filed against “a licensed professional [engineer] or the employer, pаrtnership, or other entity through which the licensed professional [engineer] performed professional services” based on the professional engineer‘s alleged negligent acts or omissions.
tions took the case outside the CQE statute. There was, at the very least, a colorable argument that a CQE was not required. See also Heavenly Days Crematorium, LLC v. Harris, Smariga and Associates, Inc., 433 Md. 558, 72 A.3d 199 (2013) (holding that CQE not required when complaint did not allege negligent acts or omissions by a licensed professional engineer, but dismissal might be required if it became evident that the alleged negligence related to a licensed enginеer).
In addition to the absence of a CQE, the Circuit Court also repeatedly alluded to “discovery violations” committed by Fort Myer. URS and the Commission had earlier sought sanctions against Fort Myer under the discovery rules, in particular,
Finally, while the Circuit Court alluded to the motion for sanctions filed by Fort Myer against the Commission,22 it never explicitly found that this motion was “without substantial justification.” As the Court of Special Appeals noted, even if the court‘s vague reference to that motion sufficed as a finding under
In sum, there is no factual support for the Circuit Court‘s finding that Fort Myer “maintain[ed its] case ... without substantial justification.” To the contrary, the Circuit Court appeared to believe that the underlying breach of contract claim was colorable. Moreover, the applicability of the CQE
requirement was “fairly debatable.” In that context, the Circuit Court‘s apparent finding that Fort Myer was responsible for discovery violations did not support sanctions under
III
Conclusion
For the reasons stated above, we affirm the decision of the Court of Special Appeals.
JUDGMENT OF THE COURT OF SPECIAL APPEALS AFFIRMED. COSTS TO BE EVENLY DIVIDED BETWEEN PETITIONERS AND RESPONDENT.
Notes
On March 19, 2015, the Commission filed a notice of appeal specifically citing various discovery rulings of the Circuit Court, an order of the court denying partial summary judgment in favor of the Commission against URS and the Circuit Court‘s judgment dated December 18, 2014 computing the damages awarded to the Commission against URS. The next day, the Commission also filed a “Notice of Cross-Appeal,” which cited the same issues and which also corrected a typographical error in the caption of the original notice of appeal.
On March 20, 2015, URS filed a notice of appeal specifically citing the Circuit Court‘s Order and Opinion dated May 5, 2014 that ruled against URS on the duty-to-defend issue and the judgment docketed on December 18, 2014 that assessed the amount of damages URS owed with respect to that claim.
Rule 2-601. Entry of judgment.
(a) Prompt entry—Separate document. Each judgment shall be set forth on a separate document. Upon a verdict of a jury or a decision by the court allowing recovery only of costs or a specified amount of money or denying all relief, the clerk shall forthwith prepare, sign, and enter the judgment, unless the court orders otherwise. Upon a verdict of a jury or a decision by the court granting other relief, the court shall promptly review the form of the judgment presented and, if approved, sign it, and the clerk shall forthwith enter the judgment as approved and signed. A judgment is effective only when so set forth and when entered as provided in section (b) of this Rule. Unless the court orders otherwise, entry of the judgment shall not be delayed pending determination of the amount of costs.
(b) Method of entry—Date of judgment. The clerk shall enter a judgment by making a record of it in writing on the file jacket, or on a docket within the file, or in a docket book, according to the practice of each court, and shall record the actual date of entry. That date shall be the date of the judgment.
The rule was subsequently revised, effective July 1, 2015, to take explicit account of the entry of judgment in an electronic case management system.
The Court of Special Appeals did not mention
