UNITED STATES of America, Plaintiff-Appellee, v. T & W EDMIER CORP., Defendant-Appellant.
No. 06-1237.
United States Court of Appeals, Seventh Circuit.
Argued Sept. 8, 2006. Decided Oct. 10, 2006.
467 F.3d 764
George L. Grumley (argued), Grumley & Rosic, Chicago, IL, for Defendant-Appellant.
Before CUDAHY, EASTERBROOK, and MANION, Circuit Judges.
EASTERBROOK, Circuit Judge.
After T & W Edmier Corp. completed its work on a reservoir in Deerfield, Illinois, it asked the Army Corps of Engineers for $32 million in addition to the agreed price of $11 million. It asserted that the extra $32 million was justified by the expense of removing hazardous materials. When the parties could not reach an agreement, Edmier initiated a formal proceeding under the Contract Disputes Act of 1978,
Edmier‘s initial position in the district court was that the Board had awarded it $1.9 million in addition to the contracting officer‘s award of $3.5 million, so that the United States was the debtor rather than the creditor. Even a quick review of the opinion shows, however, that the Board reckoned from scratch, not from the contract price plus agreed supplements plus the contracting officer‘s addition. So Edmier moved to a fallback: that the suit should be dismissed for lack of subject-matter jurisdiction. The United States had invoked
What Edmier‘s argument has to do with subject-matter jurisdiction is a mystery. The Contract Disputes Act scarcely mentions the jurisdiction of the Article III courts. It permits (and sometimes requires) contractors to file their suits in the Court of Federal Claims, see
Edmier maintains that the United States failed to exhaust administrative remedies created by the Contract Disputes Act. Exhaustion may be a condition to suit (or to success in court) but is rarely a limit on subject-matter jurisdiction. See, e.g., Mathews v. Eldridge, 424 U.S. 319, 328, 96 S.Ct. 893, 47 L.Ed.2d 18 (1976); Weinberger v. Salfi, 422 U.S. 749, 766-67, 95 S.Ct. 2457, 45 L.Ed.2d 522 (1975); Abdelqadar v. Gonzales, 413 F.3d 668, 670-71 (7th Cir.2005). As the Supreme Court has explained frequently, there is a difference between case-processing rules and limits on jurisdiction. See Eberhart v. United States, 546 U.S. 12, 126 S.Ct. 403, 163 L.Ed.2d 14 (2005); Scarborough v. Principi, 541 U.S. 401, 124 S.Ct. 1856, 158 L.Ed.2d 674 (2004); Kontrick v. Ryan, 540 U.S. 443, 124 S.Ct. 906, 157 L.Ed.2d 867 (2004). To say that Congress has authorized the federal courts to decide a class of disputes is to say that subject-matter jurisdiction is present. Congress has authorized the judiciary to entertain debt-recovery suits by the United States. See
Let us consider, then, the right question: Does the Contract Disputes Act
The difference in language is not hard to appreciate. The contractor files a claim, which leads to a “decision“; if that “decision” is in the government‘s favor, no further claim is required. Why would one be? The goal of an exhaustion requirement is to ensure that a dispute receives full administrative consideration. The agency finds essential facts and may facilitate compromise, avoiding the need for litigation. Once the administrative decision has been made, and the parties ask a court for review, it matters not which party initiated the administrative proceeding. It could matter if the statute made the administrative appeal a ratchet: the Board could increase, but never reduce, the contracting officer‘s award. Then the only way to determine whether the contracting officer‘s decision was too high (and, if so, how much too high) would be to initiate a separate proceeding. That would entail wasted motion, however, compared with an approach that allows the administrative appeal to adjust the contracting officer‘s award in either direction. Because the Contract Disputes Act allows the appellate board to make an independent decision and decrease as well as increase the award, there is no reason to rerun the process before the United States may collect any net balance in its favor.
The sort of dispute that these parties are having arose only because the United States paid the contracting officer‘s award without waiting for the outcome of Edmier‘s administrative appeal. If we were to accept Edmier‘s position in this litigation, one logical response by the Executive Branch would be to refuse to pay until the administrative process had run its course—for then there would never be a need to file another administrative proceeding in order to recoup the difference. (A new administrative claim would mean delay in collection, and from the government‘s perspective a year‘s delay in trying to collect from many small and thinly capitalized contractors is the same thing as allowing the money to evaporate. The contractor will be judgment proof.) Inducing the government to defer payment would not assist contractors, however; many a small firm has liquidity problems and cannot wait another year or two to be paid. The approach exemplified here—pay at once whatever the contracting officer awards, and settle up promptly after the Board makes a final decision—is favorable to contractors in the main. The Contract Disputes Act does not compel the United States to act otherwise.
AFFIRMED.
