MEMORANDUM OPINION
The United States of America, for the use and benefit of Tusco, Inc., and Tusco, Inc. in its own capacity (collectively “Tus-co”) have sued Clark Construction Group, LLC (“Clark”) and Travelers Casualty and Surety Company of America (“Travelers”) (collectively “Defendants”) based on a dispute over work Tusco performed on a federal construction project. Tusco, a subcontractor on the project, alleges that Clark, the prime contractor, failed to timely pay it for certain change order work performed by Tusco at Clark’s request. Tus-co’s claims include breach of contract against Clark (Count I); quantum meruit against Clark (Count II); and breach of payment bond in violation of the Miller Act, 40 U.S.C. § 3133, against Travelers. Clark has moved to dismiss Counts I and II, and Travelers has moved to stay Count III.
I. FACTS AND PROCEDURAL HISTORY
On or about September 27, 2011, Clark contracted with the United States (the “Prime Contract”) to provide construction services with respect to a federal project located in Bethesda, Maryland, known as the Intelligence Community Campus-B (ICC-B) North Campus (the “Project”). Compl. ¶ 7, ECF No. 1. On September 28, 2011, Clark secured a payment bond (the “Bond”) from Travelers Casualty and Surety Company with a penal sum of $39,912,000.00. Id. ¶ 8. Under the terms of the Bond, Travelers agreed to be bound jointly and severally with Clark to make payment to all persons having a direct contractual relationship with Clark or to any of Clark’s subcontractors who furnished labor, material, or both in performing the work for the Prime Contract in the event Clark failed to make prompt payment. Id.) Compl, Ex. A, ECF No. 1-1.
A. The Subcontract
On or about January 16, 2012, Clark entered into a subcontract with Tusco
Subcontractor agrees that payment by the Owner to Clark for work performed by the Subcontractor... is a condition precedent to any payment obligation of Clark to Subcontractor. Subcontractor agrees that the liability of Clark’s sureties on any bond for payment to Subcontractor is subject to the same conditions precedent as are applicable to Clark’s liability to Subcontractor.
Compl., Ex. B, Art. 4(j).
In addition to setting forth these payment procedures, the Subcontract contained several clauses governing “changes” in the scope of Tusco’s work under the Project. In general, the Subcontract permitted Clark to order such changes unilaterally and without notice, provided that it notified Tusco of the changes in writing.
Clark’s receipt of payment from the Owner on account of pending changes made by the Owner shall be a condition precedent to Clark’s obligation to make payment for changed work to Subcontractor.
Id., Art. 9(c). For changes made by Clark autonomously, Article 9(d) directed:
For changes ordered by Clark independent of the Owner of the Contract Documents, Subcontractor shall be entitled to equitable adjustment in the Subcontract price.
Id., Art. 9(d).
Finally, in the event Clark and the Subcontractor disputed payment, the Subcontract contained several provisions governing settlement of these disputes. For disputes involving the Government, Article 11(b) of the Subcontract stated:
In any case of any dispute between Clark and the Subcontractor, in any way relating to or arising from any act or mission of the Owner or involving the Contract Documents, Subcontractor agrees to be bound to Clark to the same extent that Clark is bound to the Owner, by the terms of the Contract Documents, and by any and all preliminary and final decisions or determinations made thereunder by the party... whether or not Subcontractor is a party to such proceedings. In case of such dispute, Subcontractor will comply with all provisions of the Contract Documents allowing a reasonable time for Clark to analyze and forward to the Owner any required communications or documentation. Clark will, at its option, (1) present to the Owner, in Clark’s name, or (2) authorize Subcontractor to present to the Owner, in Clark’s name, all of Subcontractor’s claims and answer the Owner’s claims involving Subcontractor’s work, whenever Clark is permitted to do so by the terms of the Contract Documents .... The Subcontractor price shall be adjusted by Subcontractor’s allocable share determined in accordance with Article 9, hereof.
Id., Art. 11(b).
B. Tusco’s Work on the Project
Tusco alleges that it performed all the work it agreed to perform under the original scope of the Project, which it says was
Tusco’s last day of work on the Project was on or about August 18, 2014. Id. ¶ 12. Although Clark has paid Tusco for the work performed under the original scope of the Project,
Soon thereafter, Tusco submitted a claim to Travelers for payment. Id. ¶ 15. Although Travelers did not deny the claim, it has failed to provide Tusco with a substantive response or pay it the $100,852.69 Tusco says it is owed. Id: ¶ 16.
C. The Complaint
On March 24, 2015, Tusco, Clark, Travelers, Fidelity and Deposit Company of Maryland, and Federal Insurance Company entered into a tolling agreement under which the statute of limitations on all claims “arising from; or in any way connected with the construction .of the ICC-B North Campus Project” would be tolled from March 15, 2015, until- September 24, 2015. Id ¶,17.
On September 23, 2015, Tusco filed its Complaint in this Court, alleging on the basis of the above facts: breach of contract against Clark (Count I), quantum meruit against Clark (Count II), and breach of payment bond and violation of the Miller Act against Travelers (Count III). See id. Clark has -moved to dismiss Counts I and II for failure to state a claim upon which relief may be granted. Defs.’ Mot. Dismiss and Stay,ECF No. 7. Travelers has answered the Complaint, but has moved to stay litigation of Count III. Id.\ Answer, ECF No. 8. Clark joins in Travelers’ Motion to Stay, to the extent its claims are not dismissed for failure to state a claim. Defs.’ Mot. Dismiss and Stay.
II. MOTION TO DISMISS COUNTS I AND II
A, Legal Standards
Federal Rule of Civil Procedure 8(a) prescribes “liberal pleading standards,” requiring only that a plaintiff submit a “short and plain statement of the claim showing that [he or she] is entitled to relief.” Erickson v. Pardus,
B. Count I: Breach of Contract Claim
Tusco claims in Count I that Clark breached its obligations under the Subcontract when it “failed and refused to pay Tusco in full for labor, services and materials provided by Tusco in performing its scope of work under the Subcontract and pursuant to Clark’s direction.” Co'mpl. ¶ 20.
In moving to dismiss this claim, Clark points to Article 9(c) of the Subcontract, in which Tusco expressly agreed that receipt of payment by the Government to Clark for change-order work would be a “condition precedent” to Clark’s obligation to pay Tusco. Defs.’ Mot. Dismiss and Stay, Mem. Supp. 6-7, ECF No. 7-1.
The Court agrees with Tusco.
Clark relies principally on Article 9(c) of the Subcontract which makes payment by the Government to Clark a condition precedent to payment by Clark to Tusco for work per change orders:
Clark’s receipt of payment from the Owner on account of pending changes made by the Owner shall be a condition precedent to Clark’s obligation to make payment for changed work to Subcontractor.
Compl.,.Ex. B, Art. 9(c) (emphasis added). This type of conditional payment clause in a subcontract agreement is commonly referred to by courts as a “pay-if-paid” or “pay-when-paid” clause. See, e.g., Universal Concrete Products v. Turner Const. Co.,
In Maryland,
First, at this stage of the litigation, sufficient facts have not been developed to determine whether Article 9(c)’s condition precedent has or has not been satisfied. In a contract dispute, plaintiffs are not required to expressly plead satisfaction of a condition precedent to allege a breach of contract claim—an allegation is sufficient if it alleges that the claimant “has at all times performed all its proper and legitimate duties and obligations under its contract.” Howard Robson, Inc. v. Town of Rising Sun, CIV.A. ELH-14-2003,
With respect to the change-order work at issue, Tusco'pleads that it was Clark that “requested additional work be performed” and that Clark did not pay Tusco for that additional work. Compl. ¶¶ 11, 14. Tusco states that it has performed all of its obligations under the Subcontract. Id. ¶ 19. Although Tusco does not allege that Clark has been paid by the Government for the change order work, Tusco does not have an obligation to do so: Tusco’s claim is sufficient if the subcontractor alleges that it “has at all times performed 'all its proper and legitimate duties and obligations under its contract,” Howard Robson,
In response, Clark contends that the Government ordered the additional work and therefore Article 9(c), not Article 9(d), applies. Clark states that it has “submitted a Request for Equitable Adjustment (“REA”), seeking an adjustment of the contract time and contract sum and included costs incurred by Tusco,” but that, “[t]o date, the owner has not accepted or rejected the REA.” Defs.’ Mot. Dismiss and Stay, Mem. Supp. 1-2. As an Exhibit to its Motion, Clark attaches a June 2015 letter from Clark to Travelers apparently discussing the change orders at issue. Defs.’ Mot. Dismiss and Stay, Ex. 1,'ECF No. 7-2. This letter purports to “prove” that the Government was the source of the change orders, and that Clark has not yet been paid by the Government for these change orders. See id, , .
The Court is not disposed to grant Clark’s Motion based on these contentions and this single exhibit. The veracity vel non of Clark’s assertions 'is not properly before the Court at this juncture. At the motion to dismiss stage, a court must accept all factual allegations in the complaint (and exhibits attached to the complaint, if any, see Fed. R. Civ. P. 10(c)) as true; a court does not ordinarily accept as true, much less as dispositive, the factual contentions a defendant makes in response. See Twombly,
For these reasons, Clark’s Motion to Dismiss Count I is denied without prejudice.
C. Count II: Quantum Meruit Claim
In Count II, Tusco seeks to recover against Clark based on quantum meruit, stating that it “provided valuable labor, services, and materials that were necessary for Clark to perform and complete its obligations under the Prime Contract,” that Clark “acknowledged” and “accepted]” the work, but that Clark' “failed and refused to pay Tusco” and “has been unjustly enriched.” Compl, ¶¶ 23-27. Clark moves to dismiss this Count, arguing that quantum meruit is hot a legally permissible claim when a contract governs the dispute at issue. Defs.’ Mot. Dismiss and Stay, Mem. Supp. 7-8. Tusco responds that quantum meruit is merely an alternative theory of recovery, and it argues that it should not be barred from pleading this theory at this point in the litigation. Plfs.’ Resp. Opp’n 6-7. ■
On the other hand, “[p]arties may plead alternative theories of liability, indeed as many theories as the facts will fit.” Swedish Civil Aviation Admin. v. Project Mgmt. Enterprises, Inc.,
Ill: MOTION TO STAY
A. Legal Standards
“Whether .to stay a case is a decision made in the exercise of discretion by the district court as part of its inherent power to control its own docket.” Elite Const. Team, Inc. v. Wal-Mart Stores, Inc., No., CIV. JKB-14-2358,
When considering a motion to stay, the court takes into consideration “[e]conomy of time and effort for the court, counsel, and litigants” and weighs “competing interests” to “maintain an even balance.” Id. (citing Landis,
Travelers’ asks the Court to stay Count III, Tusco’s Miller Act claim. The Court declines to do so.
B. The Miller Act
The Miller Act (or “the Act”) requires a general contractor on a federal construction project to furnish a payment bond “for the protection of all persons supplying labor and material in the prosecution of work provided for in [the] contract.” 40 U.S.C. § 3131(b)(2). The Act is designed to achieve certain policy objectives. As the Supreme Court has stated:
The Miller Act represents a congressional effort to protect persons supplying labor and material for the construction of federal public buildings in lieu of the protection they might receive under state statutes with respect to the construction of nonfederal buildings. The essence of its policy is to provide a surety who, by force of the Act, must make good the obligations of a defaulting contractor to his suppliers of labor and material. Thus the Act provides a broad but not unlimited protection.
U.S. for Benefit & on Behalf of Sherman v. Carter, 353 U.S. 210, 216-17,
To achieve its purpose, the Act creates a cause of action in favor of “[e]very person who has furnished labor or material in carrying out work provided for in [the] contract.” 40 U.S.C. § 3133(b). Persons “who [have] not been paid in full within 90 days after the day on which the person did or performed the last of the labor or furnished ... the material... may bring a civil action on the payment bond for the amount unpaid at the time the civil action is brought.” Id. As the Ninth Circuit has explained, “by the express terms of the Miller Act a subcontractor’s right of recovery on a Miller Act payment boncj is conditioned on the passage of time from completion of work or provision of materials.” U.S. for Use and Benefit of Walton Tech., Inc. v. Weststar Engineering, Inc.,
As a result of this unambiguous language, federal courts have enforced the right of subcontractors to collect on payment bonds after they have completed their work on a federal project, especially in the face of attempts by sureties to delay litigation. A principal context in which this has arisen is in connection with conditional payment clauses (or “pay-if-paid” and “pay-when-paid” clauses) in subcontracts.
When a surety attempts to enforce its principal’s (the prime contractor’s) conditional payment clause, federal courts that have addressed the issue have unanimously held that a surety is not entitled to the benefits of its principal’s pay-when-paid or pay-if-paid clause. See e.g., Walton Tech.,
Courts that have held conditional payment clauses unenforceable have emphasized the Miller Act’s unambiguous right to sue after completion of a project and the passage of time. As the Ninth Circuit explained in Walton Tech.:
A subcontractor’s right of recovery on a Miller Act payment bond accrues ninety days after the subcontractor has completed its work, not “when and if’ the prime contractor is paid by the government. Permitting a Miller Act surety to avoid liability on the payment bond based on an unsatisfied “pay when and if paid” clause in the subcontract would, for all practical purposes, prohibit a subcontractor from exercising its Miller Act rights until the prime contractor has been paid by the government. In cases where the government does not pay the prime contractor within the one year statute of limitations period, the subcontractor would be barred from asserting its Miller Act rights.
Consistent with this view, federal courts have also held that a surety may only enforce a conditional payment clause in the subcontract if there is a clear and explicit waiver of Miller Act rights in the subcontract. Walton Tech.,
C. Travelers ’ Arguments
Pursuant to the Miller Act, Tusco has sued Travelers for payment on the Bond, alleging in Count III that “Travelers is obligated, pursuant to the Bond, to pay Tusco for labor, materials, and services it provided in performing its scope of work under the Subcontract” and that “Travelers has failed to fulfill its obligation under the Bond.” Compl. ¶¶ 29-30. Travelers argues for a stay of the Miller Act claim, pointing to Article 11(b) of the Subcontract, which sets forth certain dispute resolution procedures as between Clark and Tusco “relating to or arising from any act or omission of the Owner or involving the Contract Documents.” Defs.’ Mot. Dismiss and Stay, Mem. Supp. 8-9 (quoting Compl., Ex, B., Art. 11(b)). Travelers asserts that Tusco is obligated to exhaust these same dispute resolution procedures, and submits that Tusco expressly agreed to a stay of any litigation pending exhaustion of these procedures. Defs.’ Mot. Dismiss and Stay, Mem. Supp. 8-9. Travelers also claims that allowing Tusco to proceed would lead to inefficiency, duplication of effort, and possibly “anomalous results.” Id. 10 (internal citations and quotations
In response, Tusco contends that, to the extent that Article 11(b) (or - any other provisions of the Subcontract) requires Tusco to wait for an indefinite period prior to suing on the Bond, such provisions are unenforceable because they contravene the purpose of the Miller Act. Plfs.’ Resp. Opp’n 8-9. Obligating Tusco to wait until a final determination has been made under the Subcontract’s dispute resolution procedure harms Tusco, not only because it trifles .with Miller-Act. rights, see id.; it also fails to acknowledge that.Tusco has already been waiting almost two years to be paid for the change order work.
Tusco is right.
In arguing for a stay, Travelers suggests that, because its liability for payment of the bond is derivative of Clark’s, and because- Tusco agreed in Article 11(b) to “be bound to Clark to the same extent that Clark is bound to the Owner,” the dispute resolution procedures set forth in Article 11(b) must or should be followed prior to the initiation of any claims against Travelers.
Travelers’ argument ignores established case law to the effect that “the principal’s and the surety’s liability are only coextensive to the extent permitted by the terms of the Miller Act.” United States, et al. v. Zurich Am. Ins. Co.,
United States, et al. v. Zurich Am Ins. Co. involved a payment dispute between a government contractor, Nason Construction, Inc. (“Nason”), its surety, Zurich American Insurance Company (“Zurich”), and a subcontractor, Marenalley Construction, LLC (“Marenally”), with respect to a construction project for the Veterans' Administration (“VA”).
The Miller Act entitles Marenalley to bring suit ninety days after the completion of its work on the Project... not when and if Nason recovers from the VA. Conditioning Marenalley’s right to recover from the Payment Bond on the completion of Nason’s [administrative dispute resolution process] would be inconsistent with the terms of the Miller Act.
Id. (internal citations omitted).
Nason and Zurich protested that they would be prejudiced in the absence of a stay due to the costs of dual litigation and
The Court agrees with the reasoning of Zurich Am.
The Miller Act gives a subcontractor the right to sue a payment bond’s surety based “on the passage of time,” not on the payment from the federal government to a prime contractor. Walton,
The .Court is not “overly troubled” by Travelers’ arguments that allowing, the litigation to proceed could lead to inconsistent decisions and duplicative, costly litigation. See id. There is no reason why a dispute resolution process between Clark and the
Far more troubling to the Court, quite frankly, is the potential effect of a lengthy dispute resolution process on Tusco’s right to reimbursement for the change order work.
As Clark has represented, this dispute resolution process currently involves only the Government and Clark, and neither of these parties has an economic interest in how much Tusco is ultimately reimbursed for the change order work. See id. at 551 (noting that the VA has “no interest in how that amount [paid to Nason, the subcontractor] is determined” in declining to stay litigation pending an administrative dispute resolution process). This arrangement is especially troubling given the possibility of a settlement between the two entities. If, for example, the Government agrees to pay Clark less than the total amount claimed by Tusco for the change order work, there is no provision in the Subcontract that obligates Clark to negotiate favorable terms for Tusco, nor does the Government have any particular interest in the amount of Tusco’s ultimate payments. In the event of a settlement which, hypothetically, leaves Tusco with fifty, twenty-five, or even zero percent of what it claims it is owed, Tusco may be able to contest this result against Clark in some forum, but must it wait an indefinite amount of time (until the dispute resolution process is complete) to do so?
It has been nearly two years since Tusco completed work on the project. As a matter of fairness, the Court finds it concerning that the subcontractor might be forced to wait months or even years to get paid for its work. Tusco has not waived its Miller Act rights.
IV. CONCLUSION
For the foregoing reasons, Clark’s Motion to Dismiss and Defendants’ Motion to Stay (EOF No. 7) are DENIED WITHOUT PREJUDICE, as set forth in the accompanying Order.
Notes
.To the extent Counts I and II are not dismissed, Clark has also moved to stay these claims. See Defs.’ Mot. Dismiss and Stay. As will be explained infra, Clark's (Alternative) Motion to Stay these Counts will also be DENIED.
. Unless otherwise noted, the facts are as alleged in the Complaint or the exhibits attached to it, see Fed. R. Civ. P. 10(c).
. Counsel for Tusco indicated that Tusco is a perimeter security and commercial fencing company during the March 29, 2016 Motions Hearing.
. Article 9(a) of the Subcontract stated, in part: “Clark may, at any time, unilaterally or by agreement with Subcontractor, without notice to the sureties, make changes in the work covered by this Subcontract. Any unilateral order.. .shall be in writing. Subcontractor shall perform the work as changed without delay.” Compl., Ex. B, Art. 9(a).
. Tusco does not provide the details of the change order work in the Complaint, nor did parties’ counsel elaborate on this topic during the March 29, 2016 Motions Hearing.
. Although not alleged in the Complaint, counsel for Tusco represented at the March 29, 2016 Motions Hearing that Tusco has been paid approximately $615,000.00 for the work originally contemplated by the Subcontract.
. Notably, Article 4(j) of the Subcontract contains a similar provision conditioning payment to Tusco on payment by the Government, or “Owner.” However, this clause applies to payment of the $615,000,00 Subcontract price. See CompL, Ex. B, Art. 4(j), As counsel for Tusco has represented, Tusco has already been paid this .amount by Clark. Article 4(j) therefore does not appear to have any bearing on this dispute over payment for change-order work, which is governed by Article 9’s provisions.
. Both "pay-when-paid” and "pay-if-paid” clauses condition payment to the subcontractor on receipt of payment by the owner. Notably, however, the two clauses are conceptually distinct. A "pay-when-paid” clause makes
. Count I is alleged as a state law breach of contract claim. The parties appear to agree that Maryland law applies to Tusco’s state law claims. See Defs.’ Mot. Dismiss and Stay, Mem. Supp. 7 (citing Maryland cases in reference to Tusco's quantum meruit claim); Plfs.’ Resp. Opp’n 7 n.l (noting that Maryland law applies to interpretation of the Subcontract). Moreover, Article 22(d) of the Subcontract provides; "Unless otherwise provided in the Contract Documents, the terms and conditions of this Subcontract shall be interpreted in accordance with the laws of the jurisdiction where the Project is located.” Compl., Ex. B, Art. 22(d). The Project at issue in this case was located in Bethesda, Maryland. Compl. ¶ 7. In Maryland, choice of law provisions in contracts are enforceable unless the choice of law jurisdiction has no substantial relationship to the transaction, or there is a fundamental policy difference in the laws of another jurisdiction with a more substantial interest in the parties or the transaction. See Jackson v. Pasadena Receivables, Inc.,
. This case involves a federal construction project and a separate claim for payment against Clark's surety under the Miller Act (Count III). The Miller Act applies to suits on payments bonds and therefore provides a right of action to claims against sureties. See 40 U.S.C. § 3133(b)(1). As will be discussed in Part III, infra, sureties generally cannot enforce conditional payment clauses in a subcontract because such clauses abrogate subcontractors' rights under the Miller Act. At least one court has expressly held that the Miller Act would also preclude enforcement of conditional payment clauses by general contractors, not just sureties. See U.S. for Use of Ackerman v. Holloway Co.,
. As noted by Tusco’s counsel at the Motions Hearing, Clark’s Motion effectively asks Tusco to do the impossible: allege facts about which the subcontractor has no knowledge or awareness. Tusco is not in a position to have alleged satisfaction of Article 9(c)’s condition, precedent, because Tusco has not been privy to any communications between the Government and Clark, let alone given notice of the status of any Government payments to Clark for change order work.
. See text accompanying note 9, supra.
. Federal law, not state statute or common law principles, controls in Miller Act suits. F.D. Rich Co., Inc. v. United States ex rel. Indus. Lumber Co., Inc.,
. See text accompanying note 8, supra.
. Although not in the context of a Miller Act claim, the Fourth Circuit has held in the context of a private construction contract that allowing a surety to enforce a conditional payment clause “defeats the very purpose of a payment bond.” Moore Bros. Co. v. Brown & Root, Inc.,
.- Although the length of time Tusco has been waiting for payment was not expressly addressed in Tusco’s opposition, Tusco’s counsel emphasized this fact at the Motions Hearing.
. In support of its Motion, Travelers also points to Article 11(c) of the Subcontract, stating that this provision expressly requires a "stay." Article 11(c) provides that, "[t]o the extent not resolved under Article ll.b. above, any dispute between Clark and Subcontractor shall, at Clark’s sole option, be decided by arbitration... .If Clark notifies Subcontractor that Clark contends any arbitration or lawsuit brought under this Article ll.c. involves a controversy within the scope of Article 1 l.b,, the dispute process shall be stayed until the procedures under Article ll.b. are completed.” Compl., Ex. B, Art. l’l(c) (emphasis added). The "stay” referred.'to Article 11(c) is therefore a stay of arbitration or litigation pending any dispute resolution process under Article 11(b). To the extent Article- 11(c) is cited to "stay” this litigation .and thus Tusco’s ability to exercise its Miller Act rights, Article 11(c) is also unenforceable, for the reasons set forth in this, part, infra.' As a separate matter, the arbitration .provision in this clause does not affect the current dispute because (i) Defendants' position is that the change-orders are Owner.-related and therefore should be resolved under 11(b), see Defs.’ Mot, Dismiss and Stay, Mem. Supp. 9 ("[I]t cannot be disputed that Tusco’s claims in this litigation are related to the Owner.”), and (ii) in any event, Clark has not elected to arbitrate.
. At the Motions Hearing, counsel for Defendants suggested that the Subcontract can "overcome” Tusco’s rights under the Miller Act. That is incorrect as a matter of law. As noted, a provision of a subcontract which impedes Miller Act rights can only be enforced if there is an express waiver of Miller Act rights in the agreement. See Zurich Am.,
. The Court asked Defendants' counsel about these hypothetical scenarios at the Motions Hearing. Counsel could not provide the Court with a satisfactory answer about Tus-co’s rights in the event of a settlement between the Government and Clark which significantly decreased the subcontractor’s claim to recovery. Ultimately, Defendants’ counsel conceded that Tusco would be left having to sue Clark in the event that Tusco was paid zero percent of its claimed amount for the change order work.
.Defendants do not argue that Article 11(b) (in setting forth dispute resolution procedures which could delay payment to the subcontractor) effectively waives Tusco’s Miller Act rights to seek payment on the Bond. Even if Defendants had raised this argument, the Court would reject it. Waivers of Miller Act rights must be "clear” and "explicit.” Walton Tech.,
. Without providing additional argument, Clark joins in Travelers’ Motion to Stay. The Court will assume that Clark’s reasons for seeking a stay with respect to Counts I and II are the same as Travelers’ reasons for staying Count III. The Court sees no cause to stay discovery on Tusco’s breach of contract and quantum meruit claims against Clark, given the extensive amount of time Tusco has already been forced to wait to litigate these claims. Furthermore, allowing the case to proceed against the surety on Count III, which involves the same issues of fact present in Counts I and II, will not necessarily decrease costs and increase efficiency—-instead, allowing the case to proceed against both Defendants at the same time could lead to a more efficient administration of the issues in dispute. Finally, any stay of Tusco’s lawsuit could impede its Miller Act rights, as explained at length in this Part. The Court therefore also DENIES Clark’s (Alternative) Motion to Stay.
