History
  • No items yet
midpage
235 F. Supp. 3d 745
D. Maryland
2016
Read the full case

Background

  • Clark was prime contractor on a federal project (ICC‑B North Campus); Clark obtained a Travelers payment bond. Tusco was subcontractor under a written subcontract.
  • Subcontract fixed an original price ($615,000 paid) and contained change‑order provisions: Article 9(c) makes Clark’s receipt of owner payment a condition precedent for owner‑directed changes; Article 9(d) provides equitable adjustment for changes ordered by Clark.
  • Tusco performed additional change‑order work at Clark’s request, claims Clark accepted the work but failed to pay $100,852.69 for those extras. Tusco alleged breach of contract (Count I), quantum meruit (Count II), and Miller Act/payment bond claim against Travelers (Count III).
  • Clark moved to dismiss Counts I and II arguing Tusco failed to plead satisfaction of the subcontract’s “condition precedent” (pay‑if‑paid). Travelers moved to stay the Miller Act claim pending exhaustion of subcontract dispute procedures.
  • The court denied Clark’s motion to dismiss Counts I and II (without prejudice) and denied Travelers’ motion to stay Count III, allowing the Miller Act bond suit to proceed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether breach‑of‑contract claim must be dismissed for failure to allege satisfaction of subcontract condition precedent (Article 9(c) pay‑if‑paid) Tusco: pleading that it performed all contractual duties is sufficient; satisfaction of condition precedent is an affirmative defense not required in the complaint Clark: Article 9(c) makes owner payment a condition precedent, and Tusco does not allege owner paid Clark Court: Denied dismissal—plaintiff need not allege satisfaction of condition precedent at pleading stage; facts unresolved whether work was owner‑directed (9(c)) or Clark‑directed (9(d)) so claim plausible.
Whether quantum meruit claim must be dismissed because an express contract exists Tusco: may plead alternative theories; if change work falls outside subcontract scope quantum meruit could apply Clark: expressed contract governs, barring quasi‑contract remedy Court: Denied dismissal—quantum meruit permitted as alternative pleading pending factual development.
Whether court should stay Miller Act/payment bond claim pending subcontract dispute resolution Tusco: subcontract dispute procedures cannot delay statutorily created Miller Act rights; indefinite delay would prejudice subcontractor Travelers/Clark: Article 11(b) binds subcontractor to subcontract dispute processes; stay avoids duplication and inconsistent results Court: Denied stay—Miller Act entitlement accrues by statute after work completion; subcontract clauses cannot effectively delay or defeat Miller Act rights absent a clear, explicit waiver.
Whether surety may enforce subcontract pay‑when/if‑paid or dispute‑resolution clauses to defeat Miller Act claim Tusco: Miller Act rights are federal and preempt subcontract terms that would delay recovery Travelers: surety’s liability is derivative of Clark’s and should reflect subcontract terms Court: Rejected attempt—surety may not invoke subcontract delay provisions to frustrate Miller Act claims absent explicit waiver; allowing stay would undermine Miller Act protections.

Key Cases Cited

  • U.S. v. Sherman, 353 U.S. 210 (Sup. Ct.) (describing Miller Act purpose to protect suppliers on federal projects)
  • U.S. for Use & Benefit of Walton Tech., Inc. v. Weststar Eng’g, Inc., 290 F.3d 1199 (9th Cir.) (subcontractor’s Miller Act right accrues by statute and cannot be conditioned on owner payment)
  • Universal Concrete Prods. v. Turner Constr. Co., 595 F.3d 527 (4th Cir.) (discussing enforceability and effect of pay‑when‑paid/pay‑if‑paid clauses under state law)
  • MidAmerica Constr. Mgmt., Inc. v. MasTec N. Am., Inc., 436 F.3d 1257 (10th Cir.) (distinguishing pay‑when‑paid and pay‑if‑paid clauses and their effect)
  • F.D. Rich Co. v. United States ex rel. Indus. Lumber Co., Inc., 417 U.S. 116 (Sup. Ct.) (Miller Act gives a federal cause of action; scope of remedy is federal)
  • United States v. Zurich Am. Ins. Co., 99 F. Supp. 3d 543 (E.D. Pa.) (declining to stay Miller Act suit pending prime contractor’s administrative dispute; subcontract terms that conflict with Miller Act are ineffective)
Read the full case

Case Details

Case Name: United States ex rel. Tusco, Inc. v. Clark Construction Group, LLC
Court Name: District Court, D. Maryland
Date Published: Aug 15, 2016
Citations: 235 F. Supp. 3d 745; 2016 U.S. Dist. LEXIS 107571; 2016 WL 4269078; Civil No. PJM 15-2885
Docket Number: Civil No. PJM 15-2885
Court Abbreviation: D. Maryland
Log In