UNITED PARCEL SERVICE, INC., Appellant, v. PENNSYLVANIA PUBLIC UTILITY COMMISSION, Appellee.
Supreme Court of Pennsylvania.
Decided July 23, 2003.
September 16, 2003
830 A.2d 941
Submitted April 21, 2003.
Lawrence F. Barth, Harrisburg, Elizabeth A. Lion Januzzi, for Pennsylvania Public Utility Commission.
Before CAPPY, C.J., and CASTILLE, NIGRO, NEWMAN, SAYLOR, EAKIN and LAMB, JJ.
OPINION
Justice SAYLOR.
In the proceeding under review, United Parcel Service, Inc. (“UPS“) sought enforcement by the Commonwealth Court of the court‘s previous decision sustaining the carrier‘s challenge to one aspect of the methodology utilized by the Public Utility Commission (the “PUC” or the “Commission“) in allocating the agency‘s regulatory expenses among utilities for assessment purposes as provided by statute. For the reasons that follow, we vacate the Commonwealth Court‘s order pertaining to the enforcement phase of the proceedings.
As a national motor carrier of property, certain of UPS‘s operations in Pennsylvania are conducted pursuant to Commission authority and subject to its jurisdiction. With the substantial deregulation of the motor carrier industry beginning in 1995, however, the PUC‘s regulatory role in relation to such carriers was reduced, see generally Application of S. Penn Gas Co., A-122900F0003, slip op., 1994 WL 932389 (Pa.P.U.C. Jul.26, 1994) (referencing “the considerable relax
Pursuant to Section 510(b) of the Public Utility Code,
UPS took the position that Section 510(b)(2) required the PUC to allocate “the balance of its expenditures,”
On these grounds (and others that are not relevant here), UPS filed objections to the assessments pursuant to Section 510(d) of the Public Utility Code,
On consideration of the ALJ‘s recommendation in these regards, the PUC rejected it, concluding that the Commission‘s methodology conformed with Section 510(b) in all material respects, since the statutory language was sufficiently broad to accommodate use of the Indirect Expense Subcategories. See Opinion and Order of the Pennsylvania Public Utility Commission, M-00981098, et al., slip op. at 18 (Mar. 9, 2001) (“Subsection (b)(2) ... does not so delimit the group referenced there to those utilities furnishing the same type of service.“). The Commission, however, also rejected its Fiscal Office‘s alternative proposal for realignment of the members of the Utility Groups, based on UPS‘s argument that the matter was not properly presented for decision since it had not been raised in the responses to UPS‘s objections or before the ALJ. See id. at 17 n. 9.
UPS then initiated proceedings in the Commonwealth Court via a petition for review seeking an order compelling a refund, and the court treated the matter as filed within its original jurisdiction. See United Parcel Serv., Inc. v. Pennsylvania Pub. Util. Comm‘n, 789 A.2d 353, 357 (Pa.Cmwlth.2001) (citing to
[UPS] contends that the PUC erred in its interpretation of Section 510(b) of the Code when calculating the allocation of its indirect expenses by dividing the total indirect expenses for the Common Carrier of Property group into four subcategories.
Id. at 357-58 (emphasis added). As further discussed below, unfortunately the Commonwealth Court‘s use of the “Common Carrier of Property group” terminology, and later use of the shorthand “Common Carrier,” did not align with the nomenclature utilized by the Commission, thus generating uncertainty.9 This problem was compounded, because, contrary to the Commonwealth Court‘s assertion, UPS had not argued that the Commission improperly subdivided any discrete grouping of utilities; rather, as explained above, UPS complained that the Commission had inappropriately subdivided its overall indirect expenses (i.e., those attributable to all utilities) into the four Indirect Expense Subcategories.
Nevertheless, the analysis offered by the Commonwealth Court tracked UPS‘s position fairly closely:
Section 510(b)(1) is clear that the PUC shall determine the amount of its expenditures directly attributable to the regulation of each group of utilities furnishing the same kind of service and debit the amount determined to such group. In the paragraph immediately following, Section 510(b)(2) provides that the PUC shall also determine the balance of its expenditures and allocate that balance to each group. This can only mean that the PUC must allocate its balance to each group of utilities furnishing the same kind of service because no other types of groups are mentioned, and there is no support or rationalization for the PUC‘s allegation that subsection (b)(2) means it can allocate balances to subcategories of the individual group of utilities furnishing the same kind of service.... [F]or the PUC to interpret that “group” [a]s defined differently in subsection (b)(2) from all of the other subsections is incongruous.
On remand, the Commission recalculated UPS‘s assessments, but it did so by employing an entirely new assessment methodology akin to that which had been previously recommended by the PUC‘s Fiscal Office but which was rejected by the Commission. The PUC reordered the members of the twelve primary Utility Groups utilized for direct expense allocation into eight groupings by combining the transportation-related utility groups (Airplanes, Boats & Ferries, Motor Carriers of Property, Motor Common Carriers, and Railroads) into a single group that it denominated “Common Carriers.” The Commission took the position that it was required to implement this realignment as a consequence of the Commonwealth Court‘s directive to “utiliz[e] the group of Common Carriers once.” Id. The effect was to fundamentally alter base figures used in the Commission‘s subsequent calculations--UPS was grouped with a broader segment of utilities than the former Motor Carriers of Property Utility Group, and several of the former subcategories of indirect expenses were recharacterized as direct expenses attaching the newly combined group. The PUC thus eliminated the Motor Carri
UPS then filed an application to enforce the Commonwealth Court‘s order pursuant to Pennsylvania Rule of Appellate Procedure 2591(b), asserting that the PUC‘s actions in restructuring the foundational Utility Groups contravened the clear terms of the court‘s remand order. UPS emphasized that the Utility Group methodology, particularly with respect to direct expenses, had never been challenged in the case, was never addressed by the Commonwealth Court, and was a matter that should have been treated as settled for the three fiscal years at issue by virtue of various stipulations on the part of the Commission, as well as the Commission‘s own rejection of the Fiscal Office‘s proposal to combine the transportation-related utilities that was made during the administrative proceedings. Moreover, UPS noted that the Commission applied its methodology solely to obviate UPS‘s objections; obviously, the Commission could not and did not reassess the thousands of other utilities to which it had applied its original methodology pertaining to the applicable fiscal years.
In an unpublished decision, the Commonwealth Court (via single-judge memorandum) denied UPS‘s application. United Parcel, Inc. v. PUC, No. 822 C.D.2001, slip op. (Pa.Cmwlth. Apr. 3, 2002) (”UPS II“) Again, the court erroneously articulated UPS‘s claim as positing “the Commission impermissibly
We only disagreed with the Commission‘s previous allocation of its expenses because it had divided the Motor Common Carrier into four sub-groups that not only included the transportation utilities (the Motor Carrier Group and the Transportation Group) but also included a “Fixed Utility Group” consisting of all utility groups not within the transportation group and a fourth sub-group consisting of “All Utility Groups.” Because two of those sub-groups contained utilities that were not related in any way to transportation, we ordered the Commission to recalculate UPS’ allocation without subdividing the Motor Common Carrier group and grouping the utilities that provide the same kind of service together. That is what the Commission has now done.
Since the PUC had never divided the Motor Carriers of Property Utility Group into four subgroups, or otherwise improperly associated it with fixed utilities in any of the Indirect Expense Subcategories eliminated by the PUC on remand, this reasoning is foundationless. Further, the explanation seems to convey that, whatever the Commonwealth Court had intended by its first order, when it used the term “Common Carrier” in that opinion, it was referring to the Motor Carriers of Property Utility Group (which is the grouping that UPS‘s arguments implicated), and not some broader category of “Common Carriers” as the Commission concluded and upon which it based its reassessments. Nevertheless, based on the analysis quoted above, the Commonwealth Court indicated that it could “find no fault” with the Commission‘s regrouping of utilities on remand, since the members of the
In UPS‘s present direct appeal,12 it notes that it filed an action for a refund on the ground that the Commission had assessed it amounts that were calculated in violation of the Public Utility Code; the Commonwealth Court entered judgment in its favor, holding that the Commission had in fact calculated the assessments in violation of the Code; and the matter was remanded for a recalculation in accordance with the court‘s reasoning which mirrored UPS‘s arguments. UPS contends that the Commission lacked the ability to change its method of calculating a judgment-winning utility‘s assessment, to alter aspects of the calculation method that were never at issue in the litigation,13 or to employ a calculation methodology inconsistent with that which was used to assess all other utilities for the same fiscal years. In support of its position, UPS invokes legal theories of waiver, judicial and collateral estoppel, and law of the case, predicated upon the Commission‘s: stipulation to the Utility Group categories; express rejection during the course of the litigation of a reordering of
We tend to agree with many of UPS‘s arguments. Although we are uncertain whether the Commonwealth Court was correct on the merits of the underlying matter, the fact of the matter is that UPS prevailed, and the PUC did not file a direct appeal. The Commission‘s assertion that UPS should have filed an appeal is without merit, since, as the prevailing party, UPS had no standing to appeal. See Pa.R.A.P. 501; Pierro v. Pierro, 434 Pa. 131, 132, 252 A.2d 652, 653 (1969) (explaining that an appealing party must be aggrieved, i.e., adversely affected, by order in order to have standing to appeal). While the Commonwealth Court‘s initial opinion was ambiguous and incorrect in several material respects, it simply did not foreshadow the adverse result that was visited upon UPS by the Commission on remand.
Even putting these points aside, UPS is due relief, since the Commonwealth Court‘s central reasoning supporting its dispo-
UPS I‘s mandate was for recalculation of assessments to UPS during the relevant time period in accordance with the terms of the opinion. Based on the above, we conclude that the decision‘s core reasoning, read in light of the issues that were properly before the court, required both the elimination of the Indirect Expense Subcategories and reallocation of gross indirect expenses among the stipulated, twelve Utility Groups according to proportionate gross revenues.15 Again,
For these reasons, the Commonwealth Court‘s order pertaining to the enforcement phase of the proceedings is vacated, and the case is remanded for recalculations of the relevant assessments. For purposes of these calculations, the direct expense portions of the relevant assessments are to be restored to their original form, i.e., allocated among the Utility Groups as defined in this opinion (eleven or twelve, depending upon the fiscal year of the assessment). The Commission‘s gross indirect expenses are to be allocated among the same Utility Groups for each assessment year, per Section 510(b)(2), in the proportion that the gross intrastate operating revenue for each Utility Group bears to the gross intrastate operating revenues of all Utility Groups for that year.
Chief Justice CAPPY files a dissenting opinion in which Justice NEWMAN joins.
Chief Justice CAPPY, dissenting.
In my view, the majority decides this appeal on issues that the appellant, United Parcel Service, Inc. (“UPS“), did not raise, and grants UPS relief that UPS did not request. I must, therefore, respectfully dissent.
This appeal arises out of the Application to Enforce Unappealed Final Decision (“Application to Enforce“) that UPS filed in the Commonwealth Court. In the Application to Enforce, UPS asserted that the Pennsylvania Public Utility Commission (“PUC“) failed to comply with the Commonwealth
According to the majority, this case must be remanded to the Commonwealth Court “since the Commonwealth Court‘s central reasoning supporting its disposition in the enforcement phase of the proceedings was invalid. Thus, it committed both errors of law and an abuse of discretion (since discretion cannot be properly invoked in an unreasoned framework).” (Majority Opinion at 305, 830 A.2d at 948). I cannot agree. In its memorandum opinion, the Commonwealth Court explained what it meant in the order it issued in UPS I; explained why it concluded that the PUC complied with that order; and explained how the PUC did not repeat the errors in recalculating UPS’ assessments that had led to that order in the first place. Whether this court agrees with the Commonwealth Court or not, I am at a loss to understand the majority‘s characterization of the Commonwealth Court‘s decision as “invalid” and “unreasoned” or to discern what more the majority is directing the Commonwealth Court to do on remand when it re-evaluates its ruling.
In its opinion, the majority focuses on the ambiguities and references to the Common Carrier grouping that, as the
I can, however, find no authority for the majority‘s willingness to reach back and discuss questions that arise out of the language the Commonwealth Court used in UPS I. Nor can I find any support for the majority‘s apparent decision to have the Commonwealth Court re-visit its opinion and order in UPS I on remand. In its Application to Enforce, UPS did not urge the Commonwealth Court to reconsider or modify the language that appears in either the opinion or order in UPS I. All that UPS asked the Commonwealth Court to do was to enforce that order as written.2
Therefore, in the present appeal, it is the majority, not UPS, that raises these matters. In doing so, the majority ignores Pa.R.A.P. 302 which states that “[i]ssues not raised in the lower court are waived and cannot be raised for the first time on appeal[,]” and violates a cardinal rule of appellate jurisprudence, and one which this court has repeatedly upheld--namely, that an appellate court will refrain from raising issues sua sponte. See Danville Area School District v. Danville Area Educ. Ass‘n, 562 Pa. 238, 754 A.2d 1255, 1259 (2000).
Accordingly, I would affirm the Commonwealth Court‘s order that denied UPS’ Application to Enforce.
Justice NEWMAN joins this dissenting opinion.
Notes
Id. at 359-60 (footnote omitted) (emphasis added).Because the PUC misinterpreted Section 510(b) of the Code and, therefore, miscalculated UPS’ assessments as well as those of all other utilities furnishing the same kind of service, the case is remanded to the PUC for a recalculation of UPS’ assessments. The calculations are to be based on the PUC‘s balance of expenditures only utilizing the group of Common Carriers once and not dividing its total indirect expenses into four subcategories.
