Trustees of Boston University v. Clough, Harbour & associates llpTrustees of Boston University v. Clough, Harbour & associates llp
SUPREME JUDICIAL COURT
TRUSTEES OF BOSTON UNIVERSITY vs. CLOUGH, HARBOUR & ASSOCIATES LLP
| Docket: | SJC-13685 |
| Dates: | February 5, 2025 - April 16, 2025 |
| Present: | Budd, C.J., Gaziano, Kafker, Wendlandt, Georges, Dewar, & Wolohojian, JJ. |
| County: | Suffolk |
| Keywords: | Repose, Statute of. Contract, Indemnity, Architectural services, Performance and breach. Indemnity. Practice, Civil, Summary judgment |
Civil action commenced in the Superior Court Department on July 2, 2020.
The case was heard by Michael J. Pineault, J., on a motion for summary judgment.
The Supreme Judicial Court granted an application for direct appellate review.
Michael T. Sullivan (William F. Burke also present) for the plaintiff.
Eric A. Howard (Thomas D. Duquette, Jr., & Shaun D. Loughlin also present) for the defendant.
David J. Hatem, Jon C. Cowen, Kelly Martin Malone, & Dillon Aisenberg, for American Council of Engineering Companies of Massachusetts, amicus curiae, submitted a brief.
WENDLANDT, J. The defendant, Clough, Harbour & Associates LLP (CHA or architect), agreed to design a new athletic field for the plaintiff, Trustees of Boston University (university). These sophisticated parties specifically negotiated the terms of an express indemnification provision pursuant to which CHA promised to indemnify the university for "any and all" expenses incurred by the university as a result of the architect's "negligen[t]" design.
Unfortunately, a defect in CHA's design caused the university to incur expenses to fix the field in order to render it usable for its intended purpose. Pursuant to the indemnification provision, the university submitted the bill for its expenses to CHA; CHA declined to pay. More than six years after the field first opened, the university brought the present action against CHA for breach of the indemnification provision.
This case presents the question whether G. L. c. 260, § 2B (tort statute of repose), which bars "[a]ction[s] of tort" for damages arising out of a design defect in an improvement to real property six years after the opening of the improvement to use, bars the university's contract claim. Concluding that it does not, we reverse the decision of the Superior Court judge allowing summary judgment in favor of CHA.[1]
1. Background. a. Facts. The material facts are largely undisputed; we view the facts in the light most favorable to the nonmoving party, here, the university. See Gibney v. Hossack,
On June 25, 2012, the university and CHA entered into a contract pursuant to which, in exchange for approximately $970,000, CHA agreed to design a synthetic turf athletic field for the university; the field was to be located above a parking structure also to be designed by CHA. The contract included an indemnification provision specifically negotiated by the parties.[2] Pertinent to our analysis, it provided: "To the fullest extent permitted by law, [CHA] shall indemnify . . . [the university] . . . from and against any and all . . . expenses, including, but not limited to, reasonable attorney's fees, to the extent caused . . . by the negligence of [CHA]."
The new athletic field hosted its first sporting event on August 31, 2013. From the onset, however, the university experienced numerous problems with the field because of defects in its design. Briefly, CHA's design failed to account for seasonal expansion in the joists of the parking structure; this resulted in depressions in the field that rendered it unsafe for hosting athletic events.
The university incurred more than $25,000 in expenses to render the field usable as an athletic field. Pursuant to the indemnification provision, the university demanded that CHA indemnify it for the expenses. CHA declined. More than six years after the university first started using the field, the university sued CHA for breach of the indemnification provision.[3]
b. Prior proceedings. CHA moved for summary judgment on the basis that the tort statute of repose, which eliminates a cause of action in tort six years after the opening of an improvement to real estate, see note 4, infra, barred the university's indemnification claim. Relying on the Appeals Court's unpublished decision in University of Mass. Bldg. Auth. v. Adams Plumbing & Heating, Inc.,
2. Discussion. a. Standard of review. We review the allowance of a motion for summary judgment, as well as questions of statutory construction, de novo. See Gibney,
b. Tort statute of repose. CHA argues that the tort statute of repose[4] operates to bar the university's indemnification claim, which indisputably was filed more than six years after the opening of the athletic field, because, although the claim ostensibly is based in the parties' contract, the contractual provision requires CHA to indemnify the university for CHA's negligence, and a negligence action is itself an action in tort.
By the statute's plain terms, the tort statute of repose "does not apply to contract actions," and "expressly provides a limitation only for actions of tort." Klein v. Catalano,
"A key difference between an action in tort and an action in contract is that in the latter, 'the standard of performance is set by the defendants' promises, rather than imposed by law.'" Bridgwood v. A.J. Wood Constr., Inc.,
Our decision in Gomes,
Similarly, here, the gist of the university's action is "essentially contractual -– the enforcement of a contract of indemnification." Id. In section 10.10 of the parties' contract, CHA expressly promised to indemnify the university if it suffered any expenses due to CHA's negligence. See Gomes,
Indeed, while the parties chose to incorporate the negligence standard of care into the indemnification provision, the elements of the university's contractual indemnification claim differ from a claim for negligence. See Klein,
3. Conclusion. We reverse the order allowing CHA's motion for summary judgment and remand for further proceedings.
So ordered.
[1] We acknowledge the amicus brief submitted by the American Council of Engineering Companies of Massachusetts.
[2] The indemnification provision does not appear in the American Institute of Architects (AIA) Standard Form of Agreement Between Owner and Architect, AIA Document B101-2007, used by the parties.
[3] The university asserted two additional claims, which were dismissed and are not on appeal.
[4] The tort statute of repose provides:
"Action[s] of tort for damages arising out of any deficiency or neglect in the design, planning, construction or general administration of an improvement to real property . . . shall be commenced only within three years next after the cause of action accrues; provided, however, that in no event shall such actions be commenced more than six years after the earlier of the dates of: (1) the opening of the improvement to use; or (2) substantial completion of the improvement and the taking of possession for occupancy by the owner" (emphases added).
G. L. c. 260, § 2B, first par. "A statute of repose eliminates a cause of action at a specified time, regardless of whether an injury has occurred or a cause of action has accrued as of that date." Bridgwood v. A.J. Wood Constr., Inc.,
[5] See Bridgwood,
[6] CHA incorrectly contends that our decision in Anthony's Pier Four, Inc.,
[7] CHA contends that the parties' indemnification provision in this case is materially different from the provision at issue in Gomes because the Gomes provision required the architect to indemnify the owner for any injury "arising . . . from the work" and "from any actual or alleged act, omission or negligence." Gomes,
[8] We have discussed recently the history and legislative intent in the Legislature's enactment of the tort statute of repose. See Bridgwood,