midpage
Projects
Sign in to see your projects.
255 N.E.3d 596
Mass.
2025
Read the full case

Background

  • Boston University (BU) contracted Clough, Harbour & Associates LLP (CHA) in 2012 to design a synthetic turf athletic field over a parking structure, including a specifically negotiated indemnification provision for negligence.
  • CHA's design was allegedly defective, causing the field to be unusable unless repaired. BU incurred over $25,000 in expenses to remedy the issue.
  • BU demanded indemnification per the contract, CHA refused.
  • More than six years after the field opened (August 2013), BU sued CHA for breach of the indemnification provision.
  • CHA moved for summary judgment, arguing the Massachusetts tort statute of repose (G.L. c. 260, § 2B) barred the claim; the trial court agreed.
  • The Supreme Judicial Court granted direct appellate review and reversed the lower court's decision.

Issues

Issue Plaintiff's Argument (BU) Defendant's Argument (CHA) Held
Does the tort statute of repose bar a contract-based indemnity claim when premised on negligence by the architect? The indemnification claim is contractual, not a tort, and thus not subject to the statute of repose. The claim is based on architect's negligence, thus it is a tort action subject to the statute of repose. Statute of repose does not bar the contract-based indemnification claim.
Is the distinction between breach of an express contractual provision and an implied warranty relevant to repose? Express contracts freely negotiated are not subject to tort repose limits. Only certain contract claims, like express warranties, are excepted; not indemnification. Agreed that express indemnity is distinct and not barred.
Does labeling a claim as contractual avoid repose if it is substantively tort-based? The gist of the claim is contract enforcement, as in prior precedent. The negligence basis converts it into a tort under the statute. Court examines the gist and here finds it is contractual.
Applicability of prior decisions such as Gomes v. Pan Am. Assocs. to claims like this. Prior case supports allowing contract-based indemnity claims post-repose period. Prior case is distinguishable; broader indemnity language required. Precedent supports enforceability of this type of indemnification clause.

Key Cases Cited

  • Klein v. Catalano, 386 Mass. 701 (tort statute of repose does not apply to contract actions)
  • Anthony's Pier Four, Inc. v. Crandall Dry Dock Eng'rs, Inc., 396 Mass. 818 (distinguishes between express and implied warranty for repose analysis)
  • Gomes v. Pan Am. Assocs., 406 Mass. 647 (enforcing a contract-based indemnification clause after statute of repose expired)
  • Bridgwood v. A.J. Wood Constr., Inc., 480 Mass. 349 (repose applies to duties imposed by law, not agreed by contract)
Read the full case

Case Details

Case Name: Trustees of Boston University v. Clough, Harbour & associates llp
Court Name: Massachusetts Supreme Judicial Court
Date Published: Apr 16, 2025
Citations: 255 N.E.3d 596; 495 Mass. 682; SJC-13685
Docket Number: SJC-13685
Court Abbreviation: Mass.
Log In