DEPARTMENT OF TRANSPORTATION, Appellant v. EAGLE PEAK ROCK & PAVING, INC., Appellee
2021-1837
United States Court of Appeals for the Federal Circuit
Decided: June 6, 2023
Appeal from the Civilian Board of Contract Appeals in No. 5692, Administrative Judge Beverly M. Russell, Administrative Judge Marian Elizabeth Sullivan, Administrative Judge Harold C. Kullberg.
DAVID WONDERLICK, Varela, Lee, Metz & Guarino, LLP, Tysons Corner, VA, argued for appellee. Also represented by BENNETT J. LEE, STEPHEN LOUIS PESSAGNO, JR., San Francisco, CA.
Opinion for the court filed by Circuit Judge TARANTO.
Dissenting opinion filed by Circuit Judge NEWMAN.
TARANTO, Circuit Judge.
In May 2016, the Department of Transportation‘s Federal Highway Administration (FHWA) entered into a contract with Eagle Peak Rock & Paving, Inc., under which Eagle Peak would do specified construction work in Yellowstone National Park, with the work to be completed by October 5, 2018. The contract required Eagle Peak to submit to FHWA a schedule detailing how it would complete the project on time. But by late January 2017, FHWA (acting through either its contracting officer or project engineer) had rejected all eight formal schedule submissions by Eagle Peak as not complying with the contract‘s requirements, and in early February 2017, the contracting officer terminated the contract for default, concluding that Eagle Peak was insufficiently likely to complete the project on time.
Eagle Peak challenged the termination for default under the Contract Disputes Act of 1978 (CDA),
I
A
FHWA awarded a contract—valued at roughly $35 million—to Eagle Peak in May 2016, the work to consist of improving roads, parking areas, trails, and overlooks in Yellowstone National Park. Eagle Peak, CBCA 5692, at 1-2 (page numbers taken from version of opinion at J.A. 1-17); J.A. 768-69. Eagle Peak was to complete the project by October 5, 2018, with construction work to occur during three construction seasons. Eagle Peak, CBCA 5692, at 2; J.A. 771-72. The contract included one of the standard termination-for-default provisions of the Federal Acquisition Regulations (FAR), namely,
On May 24, 2016, FHWA issued a notice to Eagle Peak that it could proceed with performance the next day. J.A. 772. Within 20 days of receiving the notice to proceed, Eagle Peak was to provide an initial construction schedule that would set a “baseline” for the project and would incorporate various restrictions imposed by the contract, e.g., halting construction during the winter and not engaging in certain activities during bird-migration season. J.A. 71-83; J.A. 744; J.A. 757; J.A. 771-72. But Eagle Peak did not submit a schedule by the deadline. J.A. 86.
On October 3, 2016, the contracting officer issued a “cure” notice to Eagle Peak. Eagle Peak, CBCA 5692, at 4; J.A. 464. In it, she noted that she was contemplating terminating the contract for default due to Eagle Peak‘s failure to submit a contract-compliant schedule, and—echoing the language of the contract-incorporated
Between October 13, 2016, and January 25, 2017, Eagle Peak submitted five more schedules, each of which the contracting officer rejected. Eagle Peak, CBCA 5692, at 4-9; J.A. 772. The officer ultimately terminated the contract for default on February 1, 2017, citing her lack of
B
Eagle Peak appealed the termination for default to the Board under
In its analysis after setting forth those findings, the Board first explained that, even though Eagle Peak initiated the appeal, “[a] termination for default is a government claim, and the Government bears the burden of proof that its action was justified,” id. at 11 (internal quotation marks omitted), citing authorities back to Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 764-65 (Fed. Cir. 1987) (same). The Board then stated what it believed the government had to justify—based on the
The Board proceeded to apply that standard in a discussion that focused heavily, though not entirely, on what the contracting officer said and considered in determining that timely completion was in sufficient doubt, rather than on what the record developed before the Board showed about whether timely completion was in sufficient doubt. Notably, the Board found neither that the contracting officer failed to make a determination about Eagle Peak‘s performance (to date and to be expected) nor that the officer‘s statements about performance were a pretext for a decision actually made on non-performance grounds. See Darwin Construction Co. v. United States, 811 F.2d 593, 596 (Fed. Cir. 1987) (holding that the Board was required to set aside a termination for default, on facts similar to precedent in which “the contractor‘s status of technical default served only ‘as a useful pretext for taking the action found necessary on other grounds unrelated to the plaintiff‘s performance or to the propriety of the extension of time,‘” i.e., where the government “‘used the termination article as a “device” and never made a “judgment as to the merits of the case“‘” (quoting Schlesinger v. United States, 390 F.2d 702, 709 (Ct. Cl. 1968))). The Board thus accepted that the contracting officer‘s decision was performance-based and not pretextual, though it did not make express findings to that effect. Despite that acceptance, the Board devoted much of its discussion to finding faults in the contracting officer‘s reasoning.
The Board stated that the contracting officer “failed to consider” (or did “not give[] due consideration” to) a number
The Board issued its decision on December 7, 2020, and the government filed a notice of appeal on April 6, 2021, within the 120 days permitted by
II
Under the Contract Disputes Act, “we review legal conclusions of the [Board] without deference” and “accept the [Board‘s] findings of fact unless they are: (1) fraudulent; (2)
A
Whenever a contracting officer makes a decision subject to the Contract Disputes Act, “[s]pecific findings of fact are not required,” and “[i]f made, specific findings of fact are not binding in any subsequent proceeding.”
When a contracting officer terminates a contract for default, and the contractor appeals that termination decision, “the government . . . bear[s] the burden of proof with respect to the issue of whether termination for default was justified.” Lisbon, 828 F.2d at 765. In failure-to-make-progress cases, the government must establish that “the contracting officer‘s decision to terminate . . . was reasonable given the events that occurred before the termination decision was made.” Empire Energy Management Systems, Inc. v. Roche, 362 F.3d 1343, 1357-58 (Fed. Cir. 2004); see id. at 1358 (affirming the Board‘s finding that the contracting officer “had a reasonable basis for default termination” (citation omitted)); Danzig v. AEC Corp., 224 F.3d 1333, 1336 (Fed. Cir. 2000) (noting that “the government [must] show that it was reasonable for the [governmental decisionmaker] to conclude that [the contractor] would be unable to complete the project by what the Board found to be the proper completion date“). If the government makes this showing, the contractor then bears the “burden of proving that its nonperformance was excusable.” DCX, Inc. v. Perry, 79 F.3d 132, 134 (Fed. Cir. 1996); see also McDonnell Douglas Corp. v. United States, 567 F.3d 1340, 1353 (Fed. Cir. 2009) (noting that burden shifts to contractor to rebut government‘s untimeliness showing or to establish “that there was excusable delay“), vacated and remanded on other grounds by General Dynamics Corp. v. United States, 563 U.S. 478 (2011).
Importantly, the “reasonable basis” language of the substantive standard does not put the focus on the contracting officer‘s own reasoning. The CDA‘s de novo standard—rooted partly in the statute‘s command that “[s]pecific findings of fact are not required” to be made by the
On the often-central issue of whether it was reasonable to view timely completion as not reasonably likely, see Empire Energy, 362 F.3d at 1357-58; Lisbon, 828 F.2d at 765, the tribunal must focus on “tangible, direct evidence reflecting the impairment of timely completion,” McDonnell Douglas XII, 323 F.3d at 1016. In particular, the Board must “decide the actual performance that the contract requires and the amount of time remaining for performance” and “may also consider” factors such as “the contracting officer‘s testimony and contemporaneous documents[,] . . . a comparison of the percentage of work completed and the amount of time remaining under the contract, the contractor‘s failure to meet progress milestones, problems with subcontractors and suppliers, the contractor‘s financial situation, . . . a contractor‘s performance history, and other pertinent circumstances.” Id. at 1016-17 (citations omitted). This is a de novo adjudication: If the adjudicatory tribunal finds, based on all the evidence before it, that the standard for termination under the contract‘s default clause is met, it is to uphold that decision whether or not the contracting officer stated the basis for that finding. As we explained in Empire Energy, clarifying some language in McDonnell Douglas XII, 323 F.3d at 1017:
Our decisions have consistently approved default terminations where the contracting officer‘s ground for termination was not sustainable if there was another existing ground for a default termination, regardless of whether that ground was known to the contracting officer at the time of the termination. Thus, the subjective knowledge of the contracting officer herself is irrelevant, and the government is not required to establish that the contracting officer conducted the analysis necessary to sustain a default under the alternative theory.
362 F.3d at 1357 (citations omitted); see also Kelso v. Kirk Brothers Mechanical Contractors, Inc., 16 F.3d 1173, 1175 (Fed. Cir. 1994) (“This court sustains a default termination if justified by circumstances at the time of termination, regardless of whether the Government originally removed the contractor for another reason.” (citation omitted)).
In addition to the issues of failure to meet contractual obligations and endangerment of timely completion (in the sense explained in Lisbon), the standard termination-for-default clause at issue here presents what can be considered a threshold issue—whether the contracting officer actually terminated the contract for default on the basis of a perceived performance problem. Specifically, the termination-for-default decision must be performance-based and not pretextual, under the Schlesinger and Darwin Construction decisions quoted above. See supra p. 6; see also McDonnell Douglas Corp. v. United States, 182 F.3d 1319, 1329 (Fed. Cir. 1999) (McDonnell Douglas X) (“[T]he government may not use default as a pretext for terminating a contract for reasons unrelated to performance; instead, there must be a nexus between the government‘s decision to terminate for default and the contractor‘s performance.“). That limited nexus requirement is implicit in the standard termination-for-default contract clause.
Accordingly, as long as “the termination for default was predicated on contract-related issues,” i.e., “the government‘s default termination was not pretextual or unrelated
B
The Board, in its opinion on review here, did not clearly separate its de novo analysis of the record evidence, see, e.g., Eagle Peak, CBCA 5692, at 2 (discussing required performance and project completion date); id. at 10-16 (evaluating Eagle Peak‘s expert‘s testimony, Eagle Peak‘s narrative reports accompanying its schedule submissions, and the percentage of work completed relative to the percentage of time used up), from its more extensive threshold analysis of the officer‘s reasoning, see, e.g., id. at 12 (“abuse of discretion” (citation omitted)); id. at 12-13 (discussing “failure to consider . . . critical information“); id. at 14 (noting that “substantial information . . . was not given due consideration“); id. (noting “inaccurate assessment of work completed by Eagle Peak prior to termination” (capitalization removed)); id. at 16 (“[D]iscretion must be exercised in a reasonable and fair manner . . . .“); id. at 17 (“The Boards of Contract Appeals have authority to set aside terminations for default where they find that the contracting officer has not acted fairly and reasonably, i.e., where the contracting officer‘s action was arbitrary and cap[r]icious.” (cleaned up) (citation omitted)). Given the Board‘s mixing
The Board‘s threshold analysis, moreover, was erroneous in going beyond the issues of pretext and a performance basis. See, e.g., id. at 12-14 (discussing “failure to consider one or more of the factors” found in
In sum, the Board‘s evaluation of the contracting officer‘s reasoning exceeded the limited scope of the threshold inquiry recognized by this court. The Board also failed to separate that threshold analysis from its de novo evaluation of the record evidence bearing on whether termination for default was justified. Because of these errors, we vacate and remand for re-adjudication on the existing record.
III
For the foregoing reasons, we vacate the Board‘s decision and remand the case for proceedings consistent with this opinion.
The parties shall bear their own costs.
VACATED AND REMANDED
DEPARTMENT OF TRANSPORTATION, Appellant v. EAGLE PEAK ROCK & PAVING, INC., Appellee
2021-1837
United States Court of Appeals for the Federal Circuit
NEWMAN, Circuit Judge, dissenting.
The Civilian Board of Contract Appeals (CBCA or “Board“) determined that the United States Department of Transportation, Federal Highway Administration (FHWA or “agency“) improperly terminated a contract with Eagle Peak Rock & Paving, Inc. on the ground of default. The asserted default was based on the contracting officer‘s finding that Eagle Peak made inadequate progress during the first year of this three-year contract. The Board converted
The Board‘s decision was reached after an evidentiary hearing with witnesses for both sides and briefing, argument, and explanation. The Board‘s decision is supported by substantial evidence and is in accordance with law. Nonetheless, the panel majority declines to complete our appellate review, and returns the case to the Board for redetermination of the same issue on the same record — to the delay, burden, and cost of both sides. I respectfully dissent.
DISCUSSION
The issue on appeal is whether the Board appropriately held that this contract should be subject to termination for convenience, or whether the contracting officer‘s termination for default should be reinstated.
The contract relates to various structural and highway construction projects in Yellowstone National Park and was to be performed over three years. After one year the FHWA contracting officer terminated the contract for default, holding that Eagle Peak had not made sufficient progress. On Eagle Peak‘s appeal to the Board, the Board converted the termination into a termination for convenience, citing the many errors in the FHWA‘s project specifications, the ensuing delays, the steps taken in correction, and the failure of the contracting officer to consider these aspects.
At the Board‘s hearing, witnesses for both sides agreed that the Contract Documents contained errors of major impact on performance of the contract. FHWA Project Engineer, Kyle Stone, stated that he had “never seen this many
The contracting officer testified that she terminated the contract for default without consideration of Eagle Peak‘s proposed schedule to correct FHWA‘s errors or of Eagle Peak‘s proposed activities to meet the original completion date. See Eagle Peak Br. 5 (“Eagle Peak‘s January 25, 2017 Recovery Schedule reflected Eagle Peak‘s plan to accelerate the remaining two seasons of work to overcome excusable delays for which the FHWA was responsible and complete the Project work (including the Mainline [mechanically stabilized earth] wall) by October 5, 2018.“).
Throughout the Board hearing, the contracting officer testified that she did not consider the effect of the FHWA‘s specification errors on performance of the contract, did not respond to Eagle Peak‘s request for corrected Contract Documents, and did not consider Eagle Peak‘s proposed schedules for meeting the three-year completion date. With full explanation of its reasoning, the Board determined the contract issue. That determination is now before us on the government‘s request for appellate review. On an unchallenged record and undisputed facts, it behooves this court to conduct that review, not to require the Board to do it again.
I
The contract is for a construction project for portions of the Grand Loop Road within Yellowstone National Park, including parking areas, trails, and overlooks, for four primary sites. Details are presented in Contract Documents provided by the FHWA, and performance is scheduled over three seasons.
During the first season it became apparent that the Contract Documents contained major errors, which were
1. The Mainline mechanically stabilized earth wall
This portion of the Mainline wall extends approximately 1,400 feet along Grand Loop Road. The Eagle Peak work on this segment was scheduled for completion in the first construction season. However, an error in the Contract Documents affected the schedule.
The Contract Documents state that the ground where the Mainline earth wall would be built did not contain soft soils or underground water. Appx0973-76 (the Boring Log from the Contract Documents); Appx1545-48 (Testimony of Tony Cruse, Eagle Peak president and engineer). However, when Eagle Peak began digging at the site, it found an unstable subgrade of soft soils, and underground water with a high water table up to subgrade level.
FHWA witnesses testified that these conditions required additional work and made construction more complex and more time-consuming than the Contract Documents contemplated. See Appx1022-23 (FHWA Project Engineer Kyle Stone describing problems with the project design, acknowledging they have created a lot of extra work, and requesting verifications of several elements of the design).
2. Inspiration Point elevation error
Eagle Peak started work at Inspiration Point during the first year and discovered that the existing ground was 2-3 feet lower than the elevations in the FHWA Contract Documents. This admitted error “prevented Eagle Peak from implementing its planned work sequence and impacted the work at virtually every portion of Inspiration Point.” Eagle Peak Br. 6.
3. Brink of the Upper Falls instability
The record recites “[a]t least three sources of FHWA-caused delays” at the Upper Falls site at the east edge of the Yellowstone River. Eagle Peak Br. 7. The Contract Documents provided for work at the Brink of the Upper Falls Historic Wall, but instability of the site prevented use of the heavy equipment, including the placement of a 90-ton crane on the wall.
“The FHWA acknowledged both the need for a redesign to address the wall‘s instability, and that the ‘[p]ending [c]ontract [m]odification’ for this changed work ‘[m]ay impact [the] critical path.‘” Eagle Peak Br. 7 (citations to record omitted). Eagle Peak states, and the FHWA agrees, that “the FHWA never issued a redesign before termination.” Eagle Peak Br. 7; see Appx1590-92 (contracting officer‘s testimony agreeing that “the ball was in the [FHWA‘s] court” and stating the unanswered questions “left things up in the air“).
In addition, the FHWA delayed commencement of work on the Upper Falls Historic Wall for at least 26 days, such that this work could not be included in the first construction season. None of this evidence was disputed.
4. Uncle Tom‘s Point micropiles
The Uncle Tom‘s Point site is at the west edge of the Yellowstone River. The FHWA design specified insufficient linear feet of micropile materials to allow them to
5. Additional design errors and omissions
The record refers to additional errors and omissions that were not corrected by the FHWA before the contracting officer terminated the contract for default. FHWA‘s Senior Engineer, Jason Hahn, testified “that there is [sic] likely numerous errors in elevations in many of the overlook designs.” Appx1310. The FHWA stated at the Board hearing that there were at least nine pending contract modifications, none of which had issued. Appx1206-07, Appx1211, Appx1226 (various emails from FHWA Project Engineer Kyle Stone to Contracting Officer Elizabeth Firestone).
II
On a contractor‘s appeal from termination for default, “the government . . . bear[s] the burden of proof with respect to the issue of whether termination for default was justified.” Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 765 (Fed. Cir. 1987). When the asserted termination ground is the contractor‘s failure to make adequate or scheduled progress, the government bears the burden of establishing that “the contracting officer‘s decision to terminate . . . was reasonable given the events that occurred before the termination decision was made.” Empire Energy Mgmt. Sys., Inc. v. Roche, 362 F.3d 1343, 1357-58 (Fed. Cir. 2004). And even if this standard is met, the contractor may prevail if it meets the “burden of proving that its nonperformance was excusable.” DCX, Inc. v. Perry, 79 F.3d 132, 134 (Fed. Cir. 1996) (stating the burden shifts to the
A
Contract Disputes Act Appeals
As stated in Wilner v. United States, 24 F.3d 1397 (Fed. Cir. 1994) (en banc), when an action is brought under the Contract Disputes Act following a contracting officer‘s decision, the parties start in the Board with a clean slate. Id. at 1402; see Assurance Co. v. United States, 813 F.2d 1202, 1206 (Fed. Cir. 1987).
Instead of correcting the design errors and processing appropriate contract modifications, the contracting officer terminated the contract for default, asserting lack of progress during the first year. However, the Board recognized the error in this theory, for it was undisputed that the design errors and absence of correction of those errors affected progress during the first year. And it was not disputed that the FHWA was the sole source of those errors. The reduction in scheduled progress during the first contract year was not the fault of Eagle Peak, but of the agency.
The panel majority states that on review of “whether a contracting officer has abused his discretion in terminating a contract for default,” the “threshold inquiry is properly limited to whether the [contracting officer‘s] termination decision was pretextual and unrelated to performance.” Maj. Op. at 14 n.1 (quotation marks and citation omitted). On the general standard of administrative review, the
Although the panel majority spots the flaws in the government‘s arguments in support of termination for default, the panel majority declines to resolve the merits, instead asking the Board to repeat its prior evaluation. There are no disputed facts, and the case warrants finality.
1. The FAR factors
The Board held that the FHWA had not met its burden of showing that termination for default was reasonable. The Board considered the regulatory factors of
With two full seasons remaining on the contract, the contracting officer here failed to consider “the urgency of the need for the . . . services [described in the contract] and the period of time” that another contractor would have required to complete the remaining work on the contract compared with the date by which Eagle Peak could have completed performance under the contract.
Board Op. at 8 (quoting
The Board cited
2. The work completed assessment
The contracting officer estimated 9-10% of the work was completed in 2016. Id. The FHWA‘s expert Steven Weathers assessed 17.1% work completed. Id. at 9. Eagle Peak‘s expert Jason Nolting estimated 26.5% work completed when weather and design impacts were considered. Id.
The Board concluded that Eagle Peak‘s progress was not “so deficient as to support a termination for default based on a calculation of work completed.” Id. The Board discussed Eagle Peak‘s critical path schedules and narratives, and found that Eagle Peak “was ready, willing, and capable of performing the project work in the two remaining seasons of the contract.” Id. at 10. The Board concluded:
Unlike the cases cited by FHWA which demonstrated that default was clearly warranted, we cannot find the facts in this appeal reflect “impairment of timely completion” of the Yellowstone project, particularly with two full construction seasons remaining under the contract, justifying the drastic sanction of default termination.
Id.
Eagle Peak argues that even if it were reasonable for the contracting officer to believe there was no expectation of timely completion, any delay in Eagle Peak‘s first year of progress was excusable because of the myriad flaws and errors in the FHWA‘s Contract Documents, and failure of
B
Review of the Board‘s findings
The panel majority observes that the Board‘s factual findings must be accepted “unless they are: (1) fraudulent; (2) arbitrary or capricious; (3) so grossly erroneous as to necessarily imply bad faith; or (4) not supported by substantial evidence.” Maj. Op. at 7-8 (quoting Ryste & Ricas, Inc. v. Harvey, 477 F.3d 1337, 1340 (Fed. Cir. 2007) (citations omitted)); see also Rockies Express Pipeline, LLC v. Salazar, 730 F.3d 1330, 1335 (Fed. Cir. 2013) (stating factual findings of the Board are only overturned “if they are arbitrary, capricious, or unsupported by substantial evidence“); Tip Top Constr., Inc. v. Donahoe, 695 F.3d 1276, 1281 (Fed. Cir. 2012) (factual findings of the Postal Service Board of Contract Appeals are final unless they are “fraudulent, arbitrary, or capricious,” “so grossly erroneous as to imply bad faith,” or “not supported by substantial evidence“).
The Board made explicit findings of fact pertinent to the conclusion that it was unreasonable for the contracting officer to have found no reasonable likelihood of timely project completion. The Board found that “Eagle Peak‘s assurances [to the contracting officer of sufficient resources] were supported by detailed information,” Board Op. at 8,
The panel majority states that “the Board expressly declined to determine whether timely performance was endangered by Eagle Peak‘s inability to submit a compliant schedule.” Maj. Op. at 14. However, the Board explicitly found that Eagle Peak “was ready, willing, and capable of performing the project work in the two remaining seasons of the contract.” Board Op. at 10; see also Discount Co. v. United States, 213 Ct. Cl. 567, 576 (1977) (finding that termination for failure to file a work schedule was wrongfully focused on a “technicality,” unless the underlying “function of the work schedule,” i.e., “to show that the contractor was ready, willing and able to make progress,” was sufficiently in doubt as to make the government “justifiably insecure about the contract‘s timely completion“).
The panel majority‘s ruling that the Board erred “in going beyond the issues of pretext and a performance basis,” Maj. Op. at 14, is contrary to the principles of review under the Contract Disputes Act. And the majority‘s emphasis on “the limited scope of the threshold inquiry recognized by this court,” Maj. Op. at 15, takes the words of precedent beyond the context in which they arose.
The panel majority, while acknowledging this court‘s obligation to conduct de novo review of legal conclusions on appeal, Maj. Op. at 7, nonetheless declines to perform de novo review.
C
De Novo Review
Precedent for government contracts reinforces that “[t]ermination is the most drastic of remedies.” In re Pipe Tech, Inc., ENGBCA No. 5959, 94-2 B.C.A. (CCH) ¶ 26,649 (Dec. 20, 1993). The government bears the burden of proving the propriety of the termination by a preponderance of the evidence. Lisbon Contractors, 828 F.2d at 765. Here, termination was imposed after one year of a three-year contract, despite significant performance during that year, in the face of significant obstacles arising from government errors.
Also, the government cannot “satisfy its burden by merely showing that the contractor was behind schedule.” Id. The contracting officer‘s termination decision must “be based on tangible, direct evidence reflecting the impairment of timely completion.” McDonnell Douglas Corp. v. United States, 323 F.3d 1006, 1016 (Fed. Cir. 2003). The Board correctly held, applying precedent, that the agency must show “that there was no reasonable likelihood of Eagle Peak‘s timely performance by October 5, 2018.” Board Op. at 7.
The government argues that “[b]ecause Eagle Peak made no allegation before the board that the default termination was anything other than performance-related, the board should never have reviewed the termination for abuse of discretion.” Gov‘t Reply Br. 6. The government is correct that the proper application of law cannot be waived. Id. at 7 (citing Aposhian v. Wilkinson, 989 F.3d 890, 897 n.4 (10th Cir. 2021) (en banc) (Tymkovich, C.J., dissenting) (“[P]arties typically cannot waive the proper standard of review.“)); see also Worth v. Tyer, 276 F.3d 249, 262 n.4 (7th Cir. 2001) (“[T]he court, not the parties, must determine the standard of review, and therefore, it cannot be waived.“). “When an issue or claim is properly before the
CONCLUSION
There is no need to repeat this administrative proceeding, for the record is complete, both sides have been fully and fairly heard, and the Board has explained the reasons for its determination. The matter is now before us for appellate review, including de novo review of certain issues. Refusing to adjudge the matter now delays justice, which is contrary to the principles “generally applicable to good judicial administration.” Radio Station WOW v. Johnson, 326 U.S. 120, 124 (1945); see also Cobbledick v. United States, 309 U.S. 323, 325 (1940) (“To be effective, judicial administration must not be leaden-footed.“). From the majority‘s decision to vacate the Board‘s decision and remand for repetition of the Board‘s analysis, I respectfully dissent.
