Thе MINESEN COMPANY, Appellant, v. John McHUGH, Secretary of the Army, Appellee.
No. 2010-1453.
United States Court of Appeals, Federal Circuit.
March 2, 2012.
671 F.3d 1332
IV
For the above stated reasons, the judgment of the Board stands
AFFIRMED
COSTS
No costs.
Sandra B. Wick Mulvany, McKenna Long & Aldridge LLP, of Denver, Colorado, argued for appellant. With her on the brief were Thomas A. Lemmer and Joseph G. Martinez, III.
Before BRYSON, O‘MALLEY, and REYNA, Circuit Judges.
Opinion for the court filed by Circuit Judge REYNA.
Dissenting opinion filed by Circuit Judge BRYSON.
REYNA, Circuit Judge.
The Minesen Company (“Minesen“) appeals the final decision of the Armed Services Board of Contract Appeals (“ASBCA” or “Board“) which granted the motion to dismiss of the United States Army‘s Morale, Welfare, and Recreation Fund (“the Fund“). Minesеn has been under contract with the Fund since 1993 to build and operate a hotel facility at a military base on Oahu Island, Hawaii. With eighteen years remaining on the agreement, the ASBCA determined that the Fund breached the core of the contract and the parties entered the quantum phase of the dispute. While in the quantum phase, Minesen filed a separate complaint alleging that the Fund had done nothing to cure its ongoing breach. The ASBCA dismissed Minesen‘s second complaint as duplicative of the first breach of contract action. Minesen appeals the ASBCA dismissal of its second complaint. Because we find that Minesen voluntarily waived its right to appeal to this court under its negotiated contract with the Fund, we dismiss.
I. BACKGROUND
Minesen, a small business from Denver, Colorado, was created for the purpose of acquiring and fulfilling government contracts. In January of 1993, after several years of negotiation, Minesen and the Fund entered into Contract No. NAFBA3-93-C-0001 (“the Contract“) to create accommodations for travelling military personnel. The Contract provided that Minesen would construct and operate, for a term of thirty-two years, a “transient lodging facility” at Schofield Barracks in central Oahu. Joint Appendix (“J.A.“) 272. Schofield Barracks is an 18,000 acre site twenty-three miles northwest of Honolulu, and is the largest Army installation in Hawaii. The Minesen lodging facility, to be built on four acres leased from the government, became known as the Inn at Schofield Barracks (“the Inn“). The Inn was to feature 184 rooms with kitchenettes, as well as other hotel amenities such as a vending area, guest laundry, playground, convenience store, and deli. Id. On a secure installation, the Inn would offer lodging only to eligible active and temporary military personnel, their families, and qualifying veterans. Under the Contract, Minesen‘s lease and operation of the Inn terminates in 2026. Id.
In addition to revenue generated operating the facility, Minesen‘s consideration for the bargain was that the Inn was officially deemed “government quarters” under the Joint Federal Travel Regulation (“JFTR“). Id. at 274. This designation was significant because it required travelling military personnel to patronize the Inn or else forfeit reimbursement for lodging costs. The Contract stated:
The completed [Inn] will fall within the current Joint Federal Travel Regulation
definition of government quarters.... Travelers receiving government per diem payment, in order not to forfeit their per diem entitlement, will be required to patronize the [Inn] on a mandatory basis as long as confirmed reservation priorities are in accordance with those provided at Section III, Operation Requirements.
Id. The Contract did not require the Fund to deliver any specific level of occupancy to the Inn.
The Contract indicated on its face that “NO FUNDS OF THE UNITED STATES GOVERNMENT WILL BE PAID OR BE DUE TO THE CONTRACTOR BY VIRTUE OF THIS CONTRACT.” Id. at 271 (emphasis original). In the definition section, the Contract further specified that: “The Fund is ... a nonappropriated fund instrumentality (NAFI) of the United States.... The Government is not a party to this contract, and no funds appropriated by Congress are in any way obligated or can be obligated by virtue of any provision of this contract.” Id. at 273.
Significant for purposes of this appeal are the Contract‘s express provisions regarding dispute resolution. In the “Disputes Clause” at § II(6), the Contract stated:
a. This contract is not subject to the Contract Disputes Act of 1978 (
41 U.S.C. 601-613 ).* * *
c. All disputes arising under or relating to this contract shall be resolved under this clause.
* * *
g. The Contracting Officer‘s decision shall be final unless the Contractor appeals as provided in paragraph h. of this clause.
h. The Contracting Officer‘s final decision may be appealed by submitting a written appeal to the Armed Services Board of Contract Appeals within 90 days of receipt of the Contracting Officer‘s final decision. Decisions of the Armed Services Board of Contract Appeals are final and are not subject to further appeal.
J.A. 276-78 (emphasis original). On February 1, 1993, the parties executed Lease No. DACA84-1-91-14, which became an attachment to the Contract. After the parties finalized the Contract in early 1993, the Inn was constructed and opened for business by June 1994.
In 1997 and 1998, the JFTR, the travel regulation incentivizing military personnel to patronize the Inn, was amended. As a result of the amendments, the Department of Defense began reimbursing for any lodging costs up to the amount charged at government quarters, whether or not the travеler actually stayed at government quarters such as the Inn.
On June 7, 1999, Minesen filed a certified claim with the Contracting Officer (“CO“) in which it alleged that the JFTR amendments eliminating the mandatory per diem forfeiture breached the Contract and negatively impacted occupancy rates. Minesen sought (1) $2,541,670.14 in lost revenues through May of 1999, and (2) future performance, or alternatively, immediate termination of the Contract with a payment of $25,506,325.00.
The CO denied the claim. On February 18, 2000, Minesen submitted further claims to the CO, seeking, inter alia, anticipatory profits for breach of contract. These claims were also denied by the CO. Minesen timely appealed both claims to the ASBCA, a right guaranteed in the Contract.
On November 20, 2006, after a five-week merits hearing, the ASBCA issued its deci-
The ASBCA remanded the case to the CO for a determination of damages. Minesen claimed entitlement to past lost profits; interest; and future lost profits. Minesen‘s statement of costs calculated “anticipatory profits from January 1, 2008 through the end of Minesen‘s contract equal [to] $34,024,454.” J.A. 314. The Fund identified various documents it claimed were necessary to verify damages, particularly those showing what Minesen would have earned from soldiers who declined to stay at the Inn but who did not forfeit the lodging reimbursement. Minesen did not promptly provide, among other things, its audited financial statements for FY 1994 through FY 1996, preventing the Fund from comparing the Inn‘s profitability before and after breach.
In early 2008, barely a year into the quantum phase, Minesen filed a new complaint (the “2008 Claim“) alleging that, subsequent to the 2006 Decision, the Fund had failed to cure its ongoing breach. Minesen asserted that failure to cure over the intervening fifteen months constituted an independent ground of material breach as of December 31, 2007, given that eighteen years were left on the Contract.
The CO denied the 2008 Claim, stating: “[T]here is no new dispute. This claim duplicates claims which you previously filed ... and to which the Board, as described above, has already rendered a decision on the merits.” Id. at 150. The CO noted that the earlier action “is now in the quantum phase in which the parties are working to effect settlement of the dispute.” Id. Minesen again appealed to the ASBCA.
On July 7, 2008, Minesen moved for partial summary judgment, alleging that the Fund had done nothing to cure its continuing breach despite having been found liable in 2006. The Fund countered with a motion to dismiss, arguing that the 2006 Decision did not require anything more than what it was presently doing—cooperating in the quantum phase on remand. According to the Fund, no new claim was warranted because it “has regularly kept Minesen informed of the status of its efforts to calculate damages, and thus, has provided adequate assurances of a remedy.” Minesen Co., ASBCA No. 56346, Slip Op. at 5 (July 16, 2010).
We also agree with the Fund that Minesen‘s “new” claim in ASBCA No. 56346 is duplicative. The factual premise of this claim is in dispute, as is its legal conclusion that it has identified “a new, independent claim for material breach.” As the Fund states in its brief, “the only ‘new’ facts the Appellant cites are those related to the amount of time the parties are taking to resolve the controversy in ASBCA Nos. 55996 and 55997.” ASBCA No. 56346, thus, is not a new cause of action, is duplicative, and must be dismissed.
Id. at 7. Pursuant to the ASBCA final determination dismissing the 2008 Claim, Minesen appealed to this court.
II. DISCUSSION
Minesen argues on appeal that the ASBCA dismissal of the 2008 Claim was improper because it constitutes a new and distinct claim over that decided in the 2006 Decision. The Fund responds that this court should not even reach the merits of whether the new claim is duplicative because at least two threshold defects estop Minesen‘s appeal before this court.
First, according to the Fund, the decision of the ASBCA was not rendered under the Contract Disputes Act (“CDA“),
A. Statutory Jurisdiction
Under
Minesen counters that our recent holding in Slattery v. United States, 635 F.3d 1298 (Fed.Cir.2011) (en banc), changes this rule. The court in Slattery indeed concluded that the Tucker Act provides jurisdictiоn over claims against NAFIs. Id. at 1301 (“Tucker Act jurisdiction does not depend on and is not limited by whether
We decline to decide this issue here. While we are generally obligated to resolve jurisdictional challenges first, Supreme Court precedent only requires federal courts to answer questions concerning their Article III jurisdiction—not necessarily their statutory jurisdiction—before reaching other dispositive issues. See Steel Co. v. Citizens for a Better Env‘t, 523 U.S. 83, 95-97, 101, 118 S.Ct. 1003, 140 L.Ed.2d 210 (1998); Restoration Pres. Masonry, Inc. v. Grove Eur. Ltd., 325 F.3d 54, 59 (1st Cir.2003) (“[W]hile Article III jurisdictional disputes are subject to Steel Co., statutory jurisdictional disputes are not.“). Here, the jurisdictional issues are strictly statutory, and not constitutional. Even without this exception for statutory jurisdictional disputes, Justice Breyer, concurring in Steel Co., noted with approval that “[t]his Court has previously made clear that courts may ‘reserve difficult questions of ... jurisdiction when the case alternatively could be resolved on the merits in the favor of the same party.‘” 523 U.S. at 111, 118 S.Ct. 1003 (citing Norton v. Mathews, 427 U.S. 524, 532, 96 S.Ct. 2771, 49 L.Ed.2d 672 (1976)); see also Bowers v. Nat‘l Collegiate Athletic Ass‘n, 346 F.3d 402, 415-16 (3d Cir.2003); cf. United States v. Caruthers, 458 F.3d 459, 472 n. 6 (6th Cir.2006).
Because the question of whether claims against NAFIs can be made pursuant to the CDA is complex post-Slattery, and because the question has a statutory provenance, we will assume jurisdiction for present purposes and proceed directly to the substance of the appellate waiver argument.
B. Appellate Waiver
The parties agreed in the Contract‘s “Dispute Clause” at § II(6)(h) that the ASBCA was the exclusive and final appellate review forum: “The Contracting Officer‘s final decision may be appealed by submitting a written appeal to the Armed Services Board of Contract Appeals within 90 days of receipt of the Contracting Officer‘s final decision. Decisions of the Armed Services Board of Contract Appeals are final and are not subject to further appeal.” J.A. 278. Minesen does not dispute the plain language interpretation of this contract provision, nor does it dispute that it voluntarily and knowingly agreed to the finality of ASBCA decisions. Minesen instеad contends that it could not legally consent to waive its statutory right under
i. Waiving Federal Circuit Appeal Is Not Contrary to the CDA
According to Minesen, its right to appear before the Federal Circuit is guaranteed by Congress, despite any contrary contract language to which it may have agreed. Minesen argues—without reference to any specific provision of the CDA—that Congress did not intend that the right to appeal to this forum be waivable.
In order to conclude that Congress intended for the CDA to include protection against waiving appeals from the ASBCA to this court, that intention must be dis-
We find no such intention here. The plain words and meaning of the relevant provision,
Judicial review of agency board decisions
(a)Review.
(1) In general. The decision of an agency board is final, except that—
(A) a contractor may appeal the decision to the United States Court of Appeals for the Federal Circuit within 120 days from the date the contractor receives a copy of the decision; or
(B) if an agency head determines that an appeal should be taken, the agency head, with the prior approval of the Attorney General, may transmit the decision to the United States Court of Appeals for the Federal Circuit for judicial review under section 1295 of title 28, within 120 days from the date the agency receives a copy of the decision.
Id. If Congress did not want this right altered by agreement, it would have said so; but this provision contains no express prohibition on appellate waivers beyond the ASBCA.
Nor does anything in the CDA‘s legislative history demonstrate that Congress did not intend for parties to be able to agree to the finality of ASBCA decisions. On the contrary, Congress recognized first among the express purposes of the CDA “induc[ing] resolution of more contract disputes by negotiation prior to litigation,” S.Rep. No. 95-1118, at 1 (1978), 1978 U.S.C.C.A.N. 5235, 5235 and “encourag[ing] the informal, quick resolution of disputes before they can develop into expensive and time-consuming administrative tangles or litigation,” 124 Cong. Rec. 31,645 (1978).
Recognizing these legislative goals, we do not find that Congress wanted to prevent parties from properly contracting to simplify dispute resolution. Agreeing to the finality of ASBCA decisions accomplishes precisely what Congress intended, at least in part, in passing the CDA. See Pathman Constr. Co. v. United States, 817 F.2d 1573, 1578 (Fed.Cir.1987) (“A major purpose of the [Contract] Disputes Act was to induce resolution of сontract disputes with the government by negotiation rather than litigation.“) (internal quotation marks omitted); cf.
ii. Waiving Federal Circuit Appeal Is Not Contrary to the CDA‘s Purpose
Minesen argues as a matter of public policy that allowing a party to waive Federal Circuit appeal skews the balance between the government and contractors during contract negotiations. Minesen argues that its promise to waive appeal rights to the Federal Circuit should be held unenforceable because of the government‘s superior bargaining power.
a. Extensive Case Law Permits Voluntary Waivers
The Supreme Court and this court have long held that the government, if not otherwise prohibited by statute, can enforce a voluntary contractual waiver with the same force as a private party, notwithstanding superior bargaining power. Town of Newton v. Rumery, 480 U.S. 386, 392-94, 107 S.Ct. 1187, 94 L.Ed.2d 405 (1987); see also Lynch v. United States, 292 U.S. 571, 579, 54 S.Ct. 840, 78 L.Ed. 1434 (1934) (“When the United States enters into contract relations, its rights and duties therein are governed generally by the law applicable to contracts between private individuals.“); Do-Well Mach. Shop, Inc. v. United States, 870 F.2d 637, 641 (Fed.Cir.1989) (“Just as the common law limits the government‘s power to contract in the same way it limits a private person, it also protects the government‘s power to contract in the same way it protects a private person.“) (emphasis original).
In Rumery, the Supreme Court addressed an argument analogous to Minesen‘s and held that the mere possibility of intimidation in contracting with the government cannot justify invalidating all such agreements. 480 U.S. at 392-94, 107 S.Ct. 1187. The Court explained that parties are often forced to make difficult choices which effectively forego statutory or constitutional rights. Id. at 393, 107 S.Ct. 1187. Parties can be held to such obligations if contracted knowingly and voluntarily. Id.
In McCall, this court held that a postal employee could enter into an agreement with the government waiving his statutorily confеrred right to appeal an agency disciplinary action. 839 F.2d at 665. The agreement at issue concluded by stating that, “the removal will be ... with no rights of appeal to any forum....” Id. When the removal action was later appealed despite the express agreement, the AJ dismissed, finding McCall‘s waiver of appellate rights valid and enforceable. Id. at 666. This court affirmed, directly addressing McCall‘s contention that such waivers are unenforceable as against public policy due to unequal bargaining power. Id. at 666-67. The court explained:
The waiver agreement in this case, like that in Rumery, reflects a rational judgment on the part of McCall.... Because his choice was knowing and voluntary, the public interest against involuntary waivers of rights does not weigh against the enforcement of this agreement and it is not void as a matter of public policy.
Id. at 667. The McCall court added that the possibility of coercion in a civil context was less serious than what was acceptable in Rumery, where criminal sanctions loomed. Id.
This court has further held that contractors can waive even constitutional rights in litigation with the government. Seaboard Lumber Co. v. United States, 903 F.2d 1560 (Fed.Cir.1990). The Fund argues based on Seaboard that if contractors can
In this case, the record and pleadings indicate that Minesen freely agreed to the finality of ASBCA decisions. While a promise can be unenforceable if the interest in its enforcement is outweighed by public policy, Rumery, 480 U.S. at 392, 107 S.Ct. 1187, public policy is not per se offendеd when a sophisticated contractor knowingly and voluntarily agrees to an appellate waiver provision denying Federal Circuit review.
b. Burnside-Ott Does Not Apply in this Case
This court in Burnside-Ott Aviation Training Center v. Dalton, 107 F.3d 854 (Fed.Cir.1997), analyzed public policy concerns associated with waiving review of contract disputes in a narrow context. Burnside-Ott held that parties may not waive review of CO decisions to the ASBCA, but it did not address waiving appeals from the ASBCA to the Federal Circuit.
The court in Burnside-Ott reminded generally that “parties to a contract may voluntarily waive certain rights, including the right to receive an impartial and independent federal adjudication, otherwise available to the parties under the law.” Id. at 858. However, the court determined that under the CDA at least one impartial review of CO decisions was necessitated by the statute‘s goal of “equaliz[ing] the bargaining power of the parties when a dispute exists,” a requirement satisfied by review in the ASBCA. Id. (citing S.Rep. No. 95-1118, at 1). Whereas the ASBCA is a neutral tribunal and not a representative of the agency,1 the CO is unquestionably biased, permitting the government to “commandeer the final decision on all disputes of fact arising under the сontract” if its decisions remain unreviewable. Id. at 858. The court explained:
In government contract disputes, unlike contract disputes between two private
parties, the initial determination in each dispute is made by one of the parties, i.e., the CO. Congress commanded that the CO‘s decision on any matter cannot be denied Board review.... Permitting parties to contract away Board review entirely would subvert this purpose and return contractors to the position they occupied before the passage of the CDA.
Minesen is not in the same situation described in Burnside-Ott, wherein the contractor was stuck with the determination of the CO, deemed “one of the parties” to the case. Id. at 858. This court confirmed that Congress “provide[d] a fair and balanced system” under the CDA to review claims related to government contracts, id., including unwaivable contractor access to the ASBCA for a de novo review of CO determinations, recourse sufficient to allay policy concerns inherent in the CDA. There is no suggestion in Burnside-Ott law that appeal to this court is additionally required to equalize bargaining power. Id.; see also Seaboard, 903 F.2d at 1565.
An unwaivable right to ASBCA review as distinguished from optional review before the Federal Circuit is supported by the CDA‘s legislative history. Cоngress intended under the CDA that contractors benefit from a “flexible system that provides alternative forums for resolution of particular kinds of disputes,” either in the federal courts or before agency boards. S.Rep. No. 95-1118, at 13. Thus, while Congress ensured immutable access to the United States Court of Federal Claims (“Court of Federal Claims“) under
The aim of any remedial system is to give the parties what is due them as determined by a thorough, impartial, speedy, and economical adjudication.... The claimant should be able to choose a forum according to the needs of his particular case; that is, one where the degree of due process desired can be balanced by the time and expense considered appropriate for the case.
Id. at 13. The CDA thus enlarged the contractor‘s options for dispute resolution: “Congress mandated that the government had to include in its contracts the broader review provisions set out in the CDA, that is, the dual avenues of review either by appeal to a Board of Contract Appeals or by a direct access suit in the Court of Claims.” Seaboard, 903 F.2d at 1565.
The dissent contends that exercising the option for flexible, expeditious review provided by the CDA creates an “anomaly.” See Dissent Op. at 1349. Yet neither the CDA nor its legislative history requires that the dual avenues necessarily be coterminous, such that both end by appeals in this court. Agency boards are designed instead for contractors who find that their case does not warrant “the maximum due process available under our system,” and instead opt for “a swift, inexpensive meth-
Minesen could have, as the dissent notes, arrived before this court through the Court of Federal Claims pursuant to
iii. The CDA‘s Standard of Review Provision Is Irrelevant to Contractual Waiver
The dissent raises a novel theory that a standard of review provision found at
The theory that
In any event, the dissent‘s attempt to infer Congress‘s intent by shoehorning
Recognizing the lack of express language in the relevant provision, the dissent relies on the spirit of the repealed Wunderlich Act, Pub.L. No. 83-356, 68 Stat. 81 (1954), to justify a strained interpretation of the CDA. Dissent Op. at 1346-48. The Wunderlich Act of 1954 was passed to legislatively overturn the ruling in United States v. Wunderlich, 342 U.S. 98, 72 S.Ct. 154, 96 L.Ed. 113 (1951). See H.R.Rep. No. 83-1380 (1954). In Wunderlich, a government contract clause provided that factual disputes would be deсided by the CO, with right of appeal only to the Secretary of the Interior. 342 U.S. at 99, 72 S.Ct. 154. The effect of Wunderlich was to keep out of the Court of Claims all cases
In passing the CDA, Congress already renewed the guarantee of direct access from the partial CO to the Court of Federal Claims, “notwithstanding any contract provision ... to the contrary,”
III. CONCLUSION
The disputed contract provision states that, “[d]ecisions of the Armed Services Board of Contract Appeals are final and are not subject to further appeal.” J.A. 278. We find that Minesen knowingly and voluntarily waived its right to appeal to this court, and we respect the clear intent of the parties agreeing to the finality of the ASBCA result. We dismiss.
DISMISSED
COSTS
No costs.
BRYSON, Circuit Judge, dissenting.
I do not agree that the disputes clause of Minesen‘s contract with the Army Morale Welfare and Recreation Fund (“the Fund“) constituted an enforceable waiver of Minesen‘s right to appeal to this court, requiring the dismissal of this appeal. I would therefore hold that this court has jurisdiction over Minesen‘s appeal. On the merits, however, I would affirm the Board‘s dismissal of Minesen‘s claims as duplicative of claims brought in the company‘s ongoing action for breach of contract.
I
The majority dismisses Minesen‘s claim based on a contractual provision that purports to bar any judicial review of a decision of the Armed Services Board of Contract Appeals. I consider that provision to be unenforceable, and I therefore conclude that the Contract Disputes Act (“CDA“) authorizes Minesen to take this appeal. In order to reach that issue, however, it is necessary to dispose of several preliminary arguments made by the government, all of which I find to be legally insupрortable. The majority does not address those issues because it concludes that the waiver argument by itself disposes of this appeal.
A
The government first argues that Minesen‘s claim is not covered by the CDA because the Fund is a nonappropriated fund instrumentality (“NAFI“). We held in Pacrim Pizza Co. v. Pirie, 304 F.3d 1291 (Fed.Cir.2002), that contracts with NAFIs other than those specifically identified in the Tucker Act,
The government‘s argument runs afoul of this court‘s recent en banc decision in Slattery v. United States, 635 F.3d 1298 (Fed.Cir.2011). We held in Slattery that
Although Slattery did not address the NAFI doctrine in the context of the CDA, its holding applies equally to claims brought under that Act, because the reach of the CDA is tied to the waiver of sovereign immunity in the Tucker Act. The CDA is applicable to “any express or implied contract (including those of the nonappropriated fund activities dеscribed in [the Tucker Act]) made by an executive agency....”
B
The government next argues that no appeal can be taken in this case because the Fund is not an “executive agency,” and the CDA applies only to contracts entered into by “executive agencies.” See
C
The government‘s next argument is that Minesen‘s contract is not covered by the CDA because the contract does not concern a “procurement.” That argument is based on the government‘s proposed definition of “procurement,” which is tied to the definition of the term “acquisition” found in the statutes governing the Office of Federal Procurement Policy. Those statutes define “acquisition” as a process that uses appropriated funds.
This court made clear in United States v. General Electric Corp., 727 F.2d 1567 (Fed.Cir.1984), that “[n]othing in the [CDA] limits its application to appropriated funds.” Id. at 1570; see also Furash & Co., 252 F.3d at 1342 (“[T]he CDA contains no express provision limiting it to agencies supported by appropriated
D
The government‘s principal argument on appeal is that the “disputes clause” of the contract between Minesen and the Fund constituted an enforceable waiver of Minesen‘s right to appeal to this court. The majority agrees with the government on that issue, but I do not.
The clause at issue was specifically designed for incorporation into NAFI contracts at a time when the NAFI doctrine was in effect. See Army Regulation 215-4, ch. 2-14(b) (1987); DA Form 4075-R (1987) (clause I-25). The Board‘s charter grants it the authority to hear claims arising under the CDA, 48 C.F.R. ch. 2, app. A, but that route of review was of no use to contractors who entered into agreements with NAFIs, because of the NAFI doctrine. Even absent the disputes clause, Minesen‘s appeal could not have been heard by this court before our decision in Slattery, because the Tucker Act had not been interpreted to waive sovereign immunity for causes of action arising from contracts with non-enumerated NAFIs. Moreover, Minesen could not have proceeded under the CDA because we had tied the scope of that Act to the NAFI doctrine, see Pacrim Pizza, 304 F.3d at 1293, and Board rulings that were not made pursuant to the CDA could not be appealed to this court, Zinger Constr., 753 F.2d at 1054. Thus, at the time the contract was signed, the disputes clause set forth Minesen‘s only right to review of decisions of the contracting officer. And the disputes clause allowed the Board (but not this court) to hear appeals under a provision of its charter that permits it to review claims relating to contracts entered into by any authorized representative of the Army, irrespective of the source of funds used to carry out the contract. 48 C.F.R. ch. 2, app. A; see, e.g., In re Atlantis Constr. Corp., ASBCA No. 44044, 96-1 BCA ¶ 28,045 (assuming jurisdiction over appeal based not on the CDA but on the disputes clause in a contract with a NAFI).
In the aftermath of Slattery, the disputes clause is in tension with
The CDA provides the exclusive remedy for all contract disputes that fall within its scope. Dalton v. Sherwood Van Lines, Inc., 50 F.3d 1014, 1017 (Fed.Cir.1995). It provides a right to judicial review of Board decisions,
While the provision of the CDA that grants the right of appeal to this court,
The Wunderlich Act consisted of two provisions. The first allowed for judicial review of any agеncy decision alleged to be
The Wunderlich Act prevented government contractors from “bargain[ing] away their right to full-scale judicial review of administrative decisions on questions of law,” Lockheed Aircraft Corp. v. United States, 375 F.2d 786, 790 (Ct.Cl.1967), or their right to limited judicial review of agency decisions on questions of fact. Congress intended to “retain for the judiciary their proper functions,” notwithstanding standard government contract clauses purporting to withdraw judicial review. Hoel-Steffen Constr. Co. v. United States, 684 F.2d 843, 851 (Ct.Cl.1982); see also S & E Contractors, 406 U.S. at 14, 92 S.Ct. 1411 (dеscribing the purpose of the Wunderlich Act as “to free citizens from a form of administrative tyranny“); Seaboard Lumber Co. v. United States, 903 F.2d 1560, 1565 (Fed.Cir.1990) (stating that the Wunderlich Act “limit[ed] by statute the contractual options previously available to the government“); Hoel-Steffen Constr., 684 F.2d at 851 (“we have in the history of the Wunderlich Act a strong expression of repugnance by Congress to the creation of decisional finality by contract clause“). Such clauses were recognized by Congress as contrary to the “tradition that everyone should have his day in court.” H.R.Rep. No. 83-1380, at 4 (1954), 1954 U.S.C.C.A.N. 2191, 2194. Because contractors lacked ordinary negotiating power when entering into government contracts, provisions that made an agency‘s decision unappealable were simply voided. Id. at 5. The Wunderlich Act, in short, was designed to invalidate jurisdiction-defeating clauses such as the one at issue in this case.
In the Contract Disputes Act, Congress chose language that carefully tracked the Wunderlich Act in order to make clear that the CDA was continuing the prohibition on contractual provisions that purport to foreclose judicial review. Subsection 7107(b) of Title 41, formеrly subsection 609(b) of the same title, states:
Notwithstanding any contract provision, regulation, or rule of law to the contrary, in an appeal by a contractor or the Federal Government from the decision of an agency board—
(1) the decision of the agency board on a question of law is not final or conclusive; but
(2) the decision of the agency board on a question of fact is final and conclusive and may not be set aside unless the decision is—
(A) fraudulent, arbitrary, or capricious;
(B) so grossly erroneous as to necessarily imply bad faith; or
(C) not supported by substantial evidence.
The CDA was not designed to diminish the statutory right government contractors previously held under the Wunderlich Act to obtain judicial review of decisions of agency boards. To the contrary, the CDA broadened contractors’ appeal rights. See
Under the CDA, contractors are given the option either to pursue their claims before an agency board or to bring an action directly in the Court of Federal Claims.
We addressed a situation similar to the present case in Burnside-Ott Aviation Training Center v. Dalton, 107 F.3d 854, 858-59 (Fed.Cir.1997). The contractual provision at issue in that case foreclosed review of a contracting officer‘s calculation of an “award fee” due to the contractor. 107 F.3d at 856. This court held the clause unenforceable in light of two provisions in the CDA. One noted that a contracting officer‘s factual determinations “shall not be binding in any subsequent proceeding.”
Although the contractual provision at issue in this case purports to displace the provisions of the CDA altogether, it cannot have the effect of foreclosing a direct appeal to the Court of Federal Claims, because
II
Because I believe that this court has jurisdiction over this appeal, I would reach the merits. On the merits, however, I would affirm the Board‘s decision that Minesen‘s complaint is duplicative of the complaint in its pending quantum action.
The Board has discretion to dismiss a complaint that it deems duplicative of a pending related action. See Finch v. Hughes Aircraft Co., 926 F.2d 1574, 1577 (Fed.Cir.1991); see generally Colo. River Water Conservation Dist. v. United States, 424 U.S. 800, 817, 96 S.Ct. 1236, 47 L.Ed.2d 483 (1976) (“the general principle is to avoid duplicative litigation“). In the first count of its complaint in this action, Minesen asserts that the Fund‘s “knowing failure to cure the breach” of contract identified in the earlier proceeding constituted an independent material breach of contract. The second count of the complaint аlleges that the Fund repudiated the contract by not curing its breach. Minesen requests damages for both counts in accordance with the contract‘s termination-for-convenience provision. In other words, Minesen treats the contract as effectively terminated and seeks to recover damages for total breach.
That theory of damages was rejected by the Board in the original proceeding. Al-
The Board determined that Minesen‘s second complaint did not raise any new cause of action that was not addressed in the previous proceeding, and the Board therefore dismissed the complaint. The Board reasoned that just as Minesen could not recover damages for total breach of contract in the initial proceeding, it could not recover those damages in the subsequent proceeding based only on the passage of time. Instead, it could bring a series of actions for partial breach of contract until the government performed. See Ind. Mich. Power Co. v. United States, 422 F.3d 1369, 1377 (Fed.Cir.2005). The Board noted that the only new facts alleged by Minesen in the second proceeding “relate[] to the amount of time the parties are taking to resolve the controversy in [the prior proceeding].” The Board did not abuse its discretion in determining that delay alone is insufficient to justify the initiation of a separate proceeding on a theory of total contract breach. On the merits, therefore, I would affirm the decision of the Board. Because I would hold that this court has jurisdiction to address the merits of Minesen‘s appeal, I respectfully dissent from the majority‘s decision on that issue.
