SUPERIOR COMMUNICATIONS, dba Smile FM, Plaintiff-Appellant, v. CITY OF RIVERVIEW, MICHIGAN, Defendant-Appellee.
No. 17-1234
United States Court of Appeals, Sixth Circuit.
Argued: December 7, 2017. Decided and Filed: February 1, 2018
881 F.3d 432
Accordingly, we DENY Black‘s motion for authorization to proceed with a second or successive motion to vacate and his motion for a certificate of appealability.
OPINION
JULIA SMITH GIBBONS, Circuit Judge.
This appeal concerns a dispute over whether Superior Communications can significantly expand and upgrade its radio broadcast equipment located on a telecommunications tower owned by the City of Riverview, Michigan. Though Superior alleges violations of the Telecommunications Act and of its constitutional rights, this case in fact turns on the interpretation of a straightforward licensing agreement between the parties. Because this agreement prohibits Superior from expanding its equipment without apprоval from the City, we affirm the district court.
I.
Superior Communications (“Superior“), doing business as Smile FM, is a nonprofit corporation that operates 21 radio broadcast stations throughout the State of Michigan. The City of Riverview (the “City“) owns and operates a 320-foot telecommunications broadcast tower on City-owned property in Riverview, Michigan. Having received its permit from the FCC to operate a low-powered FM radio broadcast station, Superior entered into a “Telecommunication Site Access License Agreement” (the “License Agreement“) with the City on October 20, 2010, to locate and operate certain radio broadcasting equipment on the City-owned telecommunications tower. Thereafter, and pursuant to the License Agreement, Superior installed one FMEC/1 single-bay antenna on the tower at a height of 300 feet and one 1,000-watt transmitter in the City‘s equipment shelter. The antenna and transmitter broadcasted a 700-watt station in accordance with Superior‘s original FCC permit and the License Agreement. The License Agreement placed strict limitations on future modifications to Superior‘s broadcast equipment and made future upgrades subject to the City‘s prior approval.
In April 2011, without the City‘s knowledge, Superior applied to the FCC for a modification to its FCC permit to allow for a significant increase in its broadcast power. In August 2012, the FCC issued Superior a permit to operate at 50,000 watts. In September 2012, Superior first approached the City regarding upgrading its equipment to allow it to broadcаst at this increased power when Superior‘s President Ed Czelada e-mailed the City‘s Land Preserve Sales Manager John Menna that Superior “received permission from the FCC to replace [Superior‘s] antenna.” DE 21-11, E-mails, Page ID 762. At the City‘s request, Superior then provided details of its proposed new equipment.
To aid in assessing Superior‘s request, the City hired Russell Harbaugh, an electrical engineer, to conduct an engineering evaluation of the proposed upgrade. He produced two reports (the “Harbaugh Reports“), which identified several issues to consider in determining whether to grant Superior‘s proposed equipment upgrade. The reports made clear that Superior‘s request to replace its single-bay antenna with a four-bay antenna would cause Superior‘s equipment to occupy thirty feet of space on the tower instead of its current three feet of space. They also expressed concern that the equipment upgrade would expose individuals around the tower to unsafe levels of radiofrequency electromagnetic radiation and that Superior‘s transmissions might create radio interference with other tower tenants.
Subsequently, on November 12, 2013, the City denied Superior‘s request to expand its broadcasting equipment located
The City moved for summary judgment on all grounds, which the district court granted. The district court concluded that the License Agreement was unambiguous and that it granted the City a contractual right to refuse Superior‘s requested upgrade, which the City had properly exercised. It also concluded that the City had not violated the Telecommunications Act, as the City had not enacted a “regulation” within the meaning of the Act but had instead acted in its proprietary capacity in dеnying Superior‘s request under the terms of the License Agreement. Finally, the court held that the City had a rational basis for its actions and, therefore, that Superior‘s constitutional claims were without merit.
We agree that Superior‘s claims are without merit and hold that the district court correctly granted summary judgment for the City.
II.
This court reviews a district court‘s grant of summary judgment de novo. Kalich v. AT&T Mobility, LLC, 679 F.3d 464, 469 (6th Cir. 2012) (citing Int‘l Union v. Cummins, Inc., 434 F.3d 478, 483 (6th Cir. 2006)). Summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
A.
Superior first challenges the district court‘s grant of summary judgment for the City on Superior‘s claim for breach of the License Agreement. We hold that the district court correctly concluded that the City did not breach the unambiguous terms of the License Agreement.
1.
Superior first argues that the License Agreement was ambiguous and therefore that summary judgment was improper.
Because the License Agreement contains a choice-of-law clause designating it be construed in accordance with the laws of the State of Michigan and Superior‘s breach of license claim arises under state law, this court uses Michigan law to interpret the License Agreement. See Johnson v. Ventra Grp., Inc., 191 F.3d 732, 738-39 (6th Cir. 1999); Super Sulky, Inc. v. U.S. Trotting Ass‘n, 174 F.3d 733, 741 (6th Cir. 1999). Under Michigan law, whether a contract is ambiguous is a question of law,
Superior argues that various provisions of the License Agreement are in conflict, and therefore, the contract is ambiguous. See Klapp, 663 N.W.2d at 453 (“[I]f two provisions of the same contract irreconcilably conflict with each other, the language of the contract is ambiguous.“). Specifically, Superior contends that paragraphs 9(a), 11, and 16(a)(2) of the License Agreement supply conflicting information regarding Superior‘s ability to upgrade its equipment. We find, however, that when read as a whole, with “harmonious effect, if possible,” these provisions do not conflict.
Paragraph 11 states, in relevant part:
[Superior] may update or replace the Antennae Facilities from time to time with the prior written approval of [the City], provided that the replacement facilities are not greater in number or size or power output than the existing facilities and that any change in their location on the Tower is satisfactory to [the City]. [Superior] shall submit to [the City] a detailed proposal for any such replacement facilities and any supplemental materials as may be requested, for [the City‘s] evaluation and approval.
DE 18-2, License Agmt., Page ID 344. Paragraph 9(a) provides that Superior “may erect and operate one FMEC/1 antenna and may expand but only with [the City‘s] consent and only after [obtaining] a certified evaluation indicating that each additional antenna will not interfere with existing antennae....” Id. at 343. And Paragraph 16(a)(2) states that the City “shall have the sole right” to “approve any changes to the size, type and quality of [Superior‘s] Equipment ..., which approval shall not be unreasonably withheld....” Id. at 345. Superior argues that the reservation “provided that the relevant facilities are not greater in number or size or power output” in Paragraph 11 “completely and totally prohibited any expansion” by Superior on the City‘s tower and, therefore, conflicts with paragraphs 9(a) and 16(a)(2), which provide that such upgrades would be allowed subject only to City approval. CA6 R. 28, Reply Br., at 14. We disagree.
Instead, Paragraph 9(a) confirms that Superior is authorized to erect and operate one FMEC/1 antenna and may expand the
Superior also points to extrinsic evidence, such as earlier drafts of the License Agreement and the City‘s course of conduct, to argue that the License Agreement gave it a right to upgrade its equipment. This extrinsic evidence, however, is wholly irrelevant to the question whether ambiguity exists in the License Agreement and could only be considered after finding that the contract is ambiguous. Sheldon-Seatz, Inc., v. Coles, 319 Mich. 401, 29 N.W.2d 832, 834-35 (1947) (“This court does not have the right to ... look to extrinsic testimony to determine [the parties‘] intent when the words used by them are clear and unambiguоus and have a definite meaning.” (quoting Mich. Chandelier Co. v. Morse, 297 Mich. 41, 297 N.W. 64, 67 (1941))); see also UAW-GM Human Res. Ctr. v. KSL Recreation Corp., 228 Mich.App. 486, 579 N.W.2d 411, 414 (1998) (quoting Mich. Chandelier Co. for the same principle). Thus, because the License Agreement is unambiguous, this extrinsic evidence cannot be considered. See Sheldon-Seatz, 29 N.W.2d at 834-35. Further, even were we to find ambiguity in the License Agreement, analysis of this extrinsic evidence would still be inappropriate. The proper remedy upon a finding of ambiguity would be to reverse the grant of summary judgment and remand the case to the district court so that a jury could determine the interpretation the language of this contract “in light of relevant extrinsic evidence“—not for the appellate court to interpret the contract in the first instance. Klapp, 663 N.W.2d at 450; see also Royal Ins. Co. of Am. v. Orient Overseas Container Line Ltd., 525 F.3d 409, 422 (6th Cir. 2008) (“When a contract is ambiguous, it is for the jury to determine the meaning of its terms, subject to propеr instructions....” (quoting Scott v. Anchor Motor Freight, Inc., 496 F.2d 276, 280 (6th Cir. 1974))).
In sum, the City acted within its unambiguous right to deny Superior‘s request to modify its equipment under the License Agreement. Superior‘s proposed equipment modifications would have expanded the number of antennae (from one to four), would have occupied ten times more space on the City‘s tower (from three feet to thirty feet), and would have significantly increased Superior‘s broadcast power (from 700 watts to 50,000 watts). Thus, the City had a contractual right under Paragraph 11 to deny this request.
2.
Superior next claims that the City waived its right to enforce the conditions of Paragraph 11 of the License Agreement because the City did not cite Paragraph 11 as a basis for denial. This argument is without merit and unsupported by the record.
To establish waiver under Michigan law, a party must show by clear and convincing evidence the mutual intention of the parties to waive or modify the original contract. Quality Prods. & Concepts Co. v. Nagel Precision, Inc., 469 Mich. 362, 666 N.W.2d 251, 258 (2003). And when, as here, the contract includes an anti-waiver clause, the significance of this clause is “heightened where a party relies on a course of conduct to establish modification.” Id.
Superior‘s claim that the City waived the provisions of Paragraph 11 through its course of conduct is unsupported by the record. During discussions related to the upgrade, the City referred to the License Agreement and advised Superior that its proposed modifications would require written amendment to the License Agreement. In their e-mail exchange, Menna and Czelada both referenced to the need for a License Agreement addendum prior to the proрosed upgrades. Moreover, the City‘s failure to cite the specific provision of the License Agreement under which it considered and then denied Superior‘s request does not indicate—much less show by clear and convincing evidence—an intent to waive Paragraph 11. We agree with the district court that failure to specifically reference the specific license provision “shows nothing more than [the City‘s] knowing silence in the face of [Superior‘s] effort to upgrade its broadcast equipment beyond the parameters established in the License Agreement,” and, therefore, no waiver occurred. DE 23, Order, Page ID 917.
3.
Superior also points to a 2012 addendum to the License Agreement addressing the calculation of late payment fees to support its claim for breach of the License Agreement and waiver. Indeed, much of Superior‘s Reply Brief is devoted to this topic. Review of the record, however, reveals that this addendum primarily reconciled provisions of the License Agreement regarding late payment fees1 and is unrelated to the dispute now before the court. Contrary to Superior‘s assertion, the addendum did not “provide[] that appellant could install additional equipment on the Riverview tower.” CA6 R. 20, Appellant Br., at 16, 37. The only reference to additional equipment in the addendum was an addition to Paragraph 5(a) that “[a]dditional equipment is subject to the then effective monthly rent increase and is further subject to the annual escalation as stated in paragraph 5d hereunder. All site equipment shall be negotiated with [the City].” DE 21-10, License Addendum, Page ID 708 (emphasis added). Therefore,
Moreover, this addendum was completed in June 2012—before Superior first approached the City regarding this equipment upgrade request in September 2012 and even before the FCC granted Superior‘s 50,000-watt permit in August 2012. At that time, the City did not even know that Superior had applied for the FCC permit to broadcast at 50,000 watts. Thus, Superior‘s claims of waiver and modification through the License Agreement addendum are without merit.
4.
Superior next claims that its upgrade request should have been deemed granted pursuant to the approval process outlined in Paragraph 16(a)(3) of the License Agreement and that the City breached the License Agreement by not following its dispute resolution provision. Both claims are meritless.
Paragraph 16(a)(3) provides an approval window for relocation of certain interfering “Equipment” and states that if the City has not approved or denied the proposed relocation within ten days, approval is deemed granted. The License Agreement, however, defines “Equipment” as Superior‘s original equipment, as defined in Schedule A. Thus, by its terms, Paragraph 16(a)(3) applies only to disputes between the City and Superior relating to the location of Superior‘s original equipment on the tower, not to the approval of any equipment upgrades or replacements. Therefore, Paragraph 16(a)(3) is irrelevant to the present dispute.
Second, the district court correctly dismissed Superior‘s claim that the City breached the dispute resolution provision of the License Agreement. The License Agreement provides that in any controversy arising out of the License, “[a] meeting will be held promptly between the parties to attempt in good faith to negotiate a resolution of the dispute.” DE 18-2, License Agmt., Page ID 358. Superior claims that the City violated this obligation by failing to meet “promptly” at the request of Superior after its upgrade request was denied. Although Superior claims a meeting was requested as early as February 11, 2015, as Superior acknowledges, the City did not formally deny its upgrade request until April 25, 2015. On June 17, 2015, Superior sent a letter to the City outlining its opposition to the denial and for the first timе requesting a meeting. The parties’ counsel then had a telephone conference sometime prior to July 16, 2015, to discuss the City Attorney letter. And then the parties met in person on August 21, 2015—only slightly over two months from the date a meeting was first requested and within the ambit of “prompt” in the realm of contractual disputes. Thus, the City did not breach the dispute resolution provisions of the License Agreement.2
Ironically, it appears that Superior is the party in breach of the dispute resolution provisions of the License Agreement. Prior to the parties’ August 21 meeting, Superior had already filed this suit in
For these reasons, the district court properly granted summary judgment for the City on Superior‘s claims for breach of the License Agreement.
B.
Superior next asserts that the City violated
We agree with the district court that the City did not take any action properly characterized as a “regulation” within the meaning of the Act. We also hold that the plain text of § 253(d) indicates that there is no private cause of action available for a violation of § 253(a), and, therefore, Superior cannot assert this claim.3
1.
Superior alleges the City violated
(a) In general
No State or local statute or regulation, or оther State or local legal requirement, may prohibit or have the effect of prohibiting the ability of any entity to provide any interstate or intrastate telecommunications service.
Sections 253 (b) and (c) then preserve the rights of state and local governments to impose necessary requirements to protect public safety, manage the public right-of-way, and establish rates on a competitively neutral and nondiscriminatory basis. Importantly, § 253(d) then provides:
(d) Preemption
If, after notice and an opportunity for public comment, the Commission determines that a State or local government has permitted or imposed any statute, regulation, or legal requirement that violates subsection (a) or (b) of this section, the Commission shall preempt the enforcement of such statute, regulation, or legal requirement to the extent necessary to correct such violation or inconsistency.
This court has previously addressed the availability of a private cause of action under § 253 without deciding this precise question. In TCG Detroit v. City of Dearborn, 206 F.3d 618, 621-24 (6th Cir. 2000), a telecommunications provider sued the City of Dearborn for setting unreasonable and discriminatory rates in alleged violation of § 253(a) and (c). The court concluded that § 253(c) allowed for a private cause of action but did not reach a conclusion regarding the availability of a private cause of action under § 253(a). Id. at 624; see also Bristol Tenn. Essential Servs. v. United Tel. S.E., LLC, No. 2:13-CV-267, 2015 WL 10096190, at *5 (E.D. Tenn. Sept. 30, 2015) (citing TCG Detroit and noting “[t]he Sixth Circuit has yet to decide whether § 253(a) confers a private right of action“). In this analysis, however, we made several points indicating that such a private cause of action would not be available under § 253(a). TCG Detroit, 206 F.3d at 623-24. First, we observed that the explicit reference to § 253(a) and (b) in § 253(d) could indicate that FCC preemption serves as the exclusive remedy for violations of those provisions. Id. at 623. Indeed, our conclusion regarding the availability of a § 253(c) private cause of action was solidified by § 253(c)‘s omission from the FCC enforcement provision in § 253(d). Id. at 624. We also noted that another provision of the Telecommunications Act,
The majority of other circuits to address this question have concluded that § 253(a) does not grant a private right of action nor can a § 253(a) violation be brought as a
We conclude the same and hold that there is no private cause of action available under § 253(a).4
2.
Even were Superior able to pursue this action, its § 253(a) claim would nevertheless be without merit. The district court correctly concluded that there was no “regulation” here within the meaning of the Telecommunications Act and therefore
that § 253 is inapplicable to the present dispute.
Section 253 states that no “local statute or regulation” or other “local legal requirement” shall prohibit the ability of any entity to “provide any interstate or intrastate telecommunications service.”
The Second Circuit in Sprint Spectrum L.P. v. Mills, 283 F.3d 404 (2d Cir. 2002), addressed a similar situation and came to the same conclusion. In Sprint Spectrum, a school district entered into a lease agreement with Sprint, permitting Sprint to build an antenna on a school rooftop, but the lease placed limitations on the level of radio emissions allowed. Id. at 407-08. Sprint later sought to modify the installation plan in a way that would have increased the level of radio emissions above the maximum authorized in the lease, though still within federal safety standards. Id. at 410-11. The school district refused to allow the upgrade, and Sprint sued, alleging preemption under the Telecommunications Act. Id. at 411. The Second Circuit concluded that the school district‘s actions did not amount to regulation
Here, the License Agreement between the City and Superior presents the same situation as Sprint Spectrum, and the reasoning from that case is persuasive. Just as private tower owners are not obliged to allow communications companies to operate at the FCC maximum transmissions levels—they may choose, via contract with a tenant, to limit equipment or broadcast power to a lower level—the City, in its capacity as a property owner, had the “right to decline to lease the property except on agreed conditions.” Sprint Spectrum, 283 F.3d at 421. Suрerior sought out the City “only in [its] capacity as a property owner,” and, as well put by the Sprint Spectrum court:
[A] lessee who agreed to the lease conditions requested by the owner of private property could not thereafter compel performance of the lease agreement by the private owner while the lessee refused to perform the agreed conditions. We see no indication that Congress meant the TCA to apply any different set of principles to a telecommunications company‘s negotiated agreement with a public property owner.
Id. As such, the district court correctly granted summary judgment for the City on Superior‘s Telecommunications Act claims.
C.
Superior next alleges two constitutional challenges to the City‘s denial of its upgrade request, neither of which has merit.
1.
Superior first alleges a due process violation, claiming its requested equipment upgrade was a “legitimate claim of entitlement protected by due process” because the City had “limited discretion to deny” the request under the License Agreement. CA6 R. 20, Appellant Br., at 49; see Bd. of Regents of State Colls. v. Roth, 408 U.S. 564, 577 (1972) (finding a property interest protected by due process when an individual has a “legitimate claim of entitlement” to a benefit). The district court held that Superior had not made a viable due process claim because the License Agreement squarely gave the City a right to deny approval for replacement facilities “greater in number or size or power output” than the existing facilities, meaning Superior had no protected property interest in the requested upgrade. We agree with the district court that there was no protected property interest here. More fundamentally, however, our precedent holds that that a procedural due process claim cannot be sustained in a situation where, as here, “the only difference be-
In Kaminski v. Coulter, this court, relying on Ramsey v. Bd. of Educ. of Whitley Cty., 844 F.2d 1268 (6th Cir. 1988), concluded that “a claim for a due-process violation does not lie where the thrust of the plaintiffs’ argument is simply breach of contract.” Kaminski, 865 F.3d at 348. The court concluded that “[b]ecause a due-process claim is predicated on the deprivation of a constitutionally protected interest without due process of law, the availability of a state breach-of-contract remedy defeats the due-process claim.” Id. Here, Superior‘s purported property right is derived from the License Agreement and is therefore, at its core, simply a claim for breach of contract. In its complaint Superior asserts that it has “property rights and liberty interests in the License Agreement, its place on the tower, and its right to upgrade its equipment in order to maintain its business.” DE 1, Not. of Removal, Page ID 17. And in its brief on appeal, Superior identifies the License Agreement as the source of its purported right, arguing that “the License Agreement provides that appellant may expand with the City‘s consent, and that such consent ‘shall not be unrеasonably withheld.‘” CA6 R. 20, Appellant Br., at 48. Therefore, Superior has not made out a viable due-process claim. See Ramsey, 844 F.2d at 1273 (“A state breach of contract action is most clearly an adequate remedy for a property deprivation when the only basis for federal jurisdiction is that a state actor is one of the contracting parties.“).
2.
Superior next argues that the City violated the Equal Protection Clause by denying its upgrade request while granting similar requests by other tower tenants, AT&T and T-Mobile.
The Equal Protection Clause prohibits discrimination by the government that “burdens a fundamental right, targets a suspect class, or intentionally treats one differently than others similarly situated without any rational basis for the difference.” TriHealth, Inc. v. Bd. of Comm‘rs, Hamilton Cty., 430 F.3d 783, 788 (6th Cir. 2005) (citing Radvansky v. City of Olmsted Falls, 395 F.3d 291, 312 (6th Cir. 2005)). Superior‘s claim is of the third kind—a “class-of-one” violation—and therefore the government action here is subject to rational basis review only. See Taylor Acquisitions, 313 Fed.Appx. at 836-37.
As an initial matter, to state a class-of-one equal protection claim, a party must show that “the government treated similarly situated persons differently.” See Braun v. Ann Arbor Charter Twp., 519 F.3d 564, 574 (6th Cir. 2008). The party bringing a claim “must allege that it and other individuals who were treated differently were similarly situated in all material respects.” Taylor Acquisitions, 313 Fed. Appx. at 836. Here, Superior has not done so. To support its claim of differing treatment, Superior points to the City permitting AT&T and T-Mobile to expand their equipment in ways that increased their number of antennae and power output; however, as the district court notes, we do not have the terms of AT&T‘s or T-Mobile‘s licensing agreements in evidence and therefore do not know whether their resрective agreements included a provision that replacement facilities not be “greater in number or size or power output” than existing facilities.
Superior asks this court to “infer that the contract provisions that the City has
Moreover, the explicit terms of the License Agreement and the issues raised in the Harbaugh Reports, as outlined in Menna‘s November 2013 letter and the City Attorney‘s letter formally denying Superior‘s request, provide a “conceivable basis” for denial, and thus articulate a rational basis to justify any differential treatment. See TriHealth, 430 F.3d at 788 (“A ‘class of one’ plaintiff may demonstrate that government action lacks a rational basis either by negativing every conceivable basis which might support the government action, or by showing that the challenged action was motivated by animus or ill-will.“). Superior‘s equal protection claim, therefore, is without merit.
III.
For the reasons stated, we affirm the district court‘s grant of summary judgment for the City.
IN RE: OHIO EXECUTION PROTOCOL LITIGATION. Alva E. Campbell, Jr.; Raymond Tibbetts, Plaintiffs-Appellants, v. John Kasich, et al., Defendants-Appellees.
No. 17-4221
United States Court of Appeals, Sixth Circuit.
Argued: January 25, 2018. Decided and Filed: February 1, 2018
