Plaintiff-appellant NextG Networks of NY, Inc. (“NextG”) appeals from a judgment of the United States District Court for the Southern District of New York (Berman, J.), granting summary judgment in favor of the defendants-appellees (collectively, “the City”).
Broadly speaking, this case concerns whether the City has impeded NextG’s access to the New York City telecommunications market by unlawfully denying NextG the use of City-owned poles. NextG, a wholesale provider of telecommunications services, offers other wireless carriers a method for extending wireless coverage to “dead spots.” It does this, among other ways, by constructing a continuous grid of low-level antennas (“nodes”) mounted at heights of no more than approximately 30 feet from the ground. To construct such a network in New York City, NextG proposes to install nodes and node equipment on City-owned utility poles and streetlight poles in the public rights-of-way. 1 Under the New York City Charter, before any entity can use the “inalienable property” of the City, including City poles, it must first obtain a franchise. Such a franchise is available only if the City’s Department of Information Technology and Telecommunications (“DoITT”) makes an initial determination of the need for franchises of a particular type, and the New York City Council then adopts a resolution authorizing the granting of such franchises. Once this is done, DoITT issues a Request for Proposals (“RFP”) pursuant to which an individual entity may apply for such a franchise. If DoITT approves the application, the franchise is subject to a public hearing, approval by the Mayor, and review and approval by the Franchise and Concession Review Committee, before it can finally be granted.
In connection with the provision of mobile telecommunications services, the City Council, beginning in 1994, passed three successive resolutions authorizing DoITT to issue franchises for the installation of telecommunications equipment and facilities on, over, and under the “inalienable property” of the City. The resolution that was in place when NextG first brought this action was Resolution No. 957, which took
After the action was filed, DoITT, on February 9, 2004, finally issued an RFP (the “2004 RFP”) entitled a “Request For Proposals For Franchises For The Installation And Use, On City-Owned Street Light Poles, Traffic Light Poles And Highway Sign Support Poles, Of Telecommunications Equipment And Facilities, Including Base Station And Access Point Facilities, In Connection With The Provision Of Mobile Telecommunications Services.” The deadline for submitting franchise applications pursuant to the 2004 RFP was April 16, 2004. NextG and eight other companies duly submitted applications. Two applicants then withdrew their proposals. On April 30, 2004, DoITT sent letters to the remaining applicants, stating, in effect, that no franchise would be granted to any applicant who did not commit to various requirements. NextG declined to commit to a number of the requirements, including a commitment to pay a minimum annual “zone” compensation fee of $100,000 and a minimum bid of $250 per pole per month for the zone encompassing Manhattan; an agreement to accept a “priority rating” for a particular zone based on an entity’s per pole bid; and an agreement to a system whereby if there were competing requests for use of the same pole, the requesting company with the highest priority rating in that zone would have first option to utilize the pole for a certain period of time. Accordingly, the City refused to grant NextG a franchise. It did, however, grant franchises to the other six applicants, who agreed to these conditions.
Meanwhile, on March 2, 2004, NextG amended its complaint to seek a declaration that the City’s rules, regulations and requirements embodied in the City Charter, in Resolution No. 957, and in the 2004 RFP violated Section 253 of the Telecommunications Act of 1996, 47 U.S.C. § 253. It also requested an order enjoining the City from enforcing these rules and regulations. Finally, it sought damages under 42 U.S.C. § 1983 for the City’s alleged violations of Section 253.
On August 11, 2004, Resolution No. 957 expired, by its own terms. Although a new, similar resolution, Resolution No. 519, was enacted on March 23, 2005, no RFP was issued pursuant to Resolution No. 519 until July 19, 2007.
In the interim, on March 6, 2006, the District Court granted the City’s motion for summary judgment. In its Decision and Order, the District Court concluded that it would be “inappropriate to issue a declaratory judgment with respect to the [City] Charter, Resolution No. 957, and 2004 RFP because (i) Resolution No. 957 and the 2004 RFP have expired and (ii) NextG has an available claim for money damages under Section 1983.” In a footnote, the District Court noted that “NextG does not appear to have requested that the Court declare that the City’s new franchise scheme under Resolution No. 519 is preempted by Section 253. In any event, on this record, there does not appear to be
The District Court also found that in-junctive relief was not warranted because, given its prior ruling that an action for damages was available, NextG had not established “that it suffered or is likely to suffer irreparable injury.”
Finally, with regard to NextG’s claim for money damages, the District Court held that, because NextG had offered no evidence as to the actual economic effect on NextG of the City’s requirements that NextG was challenging, NextG’s claim for damages must be dismissed.
We review a district court’s grant of summary judgment
de novo. Physicians Comm. for Responsible Med. v. Johnson,
Only
“rights,
not the broader or vaguer benefits or interests” may be enforced through § 1983.
Gonzaga Univ. v. Doe,
The District Court believed that such rights were conferred on telecommunications providers by Section 253, primarily because, in the District Court’s view, Section 253 “is phrased in terms of persons (entities) benefitted, i.e. telecommunications providers.” But the statutory language to which the District Court referred in support of this analysis simply states, in relevant part, that “No State or local statute or regulation, or other State or local legal requirement, may prohibit or have the effect of prohibiting the ability of any entity to provide any interstate or intrastate telecommunications service.” 47 U.S.C. § 253(a). We read this language as intended to place limits on state and local governments, rather than as intended to benefit an identified class of putative plaintiffs.
This reading is further confirmed by the additional statutory language that “Nothing in this section affects the authority of a State or local government to manage the public rights-of-way or to require fair and
The two other Circuits that have addressed this issue directly have similarly held that there is no private damages action under Section 1983 for a violation of Section 253.
See Sprint Telephony PCS, L.P. v. County of San Diego,
From our conclusion that § 253 does not create a private right of action for damages, it follows that we do not agree either with the portion of the District Court’s decision that denied injunctive relief on the ground that NextG had an
A dispute usually becomes moot if the defendant can demonstrate that “(1) there is no reasonable expectation that the alleged violation will recur and (2) interim relief or events have completely and irrevocably eradicated the effects of the alleged violation.”
Granite State Outdoor Adver. v. Town of Orange,
Here, the expiration of Resolution No. 957 and the 2004 RFP did not obviate appellant’s claims or completely eradicate the effects of the City’s regulatory scheme. For one thing, NextG’s Amended Complaint challenged not only Resolution No. 957 and the 2004 RFP, but also the provisions of the City Charter on which the Resolution and RFP were predicated. Therefore, at a minimum, NextG’s claim that these provisions of the City Charter are preempted by the Telecommunications Act of 1996 is not moot.
See Lamar Adver. of Penn, LLC v. Town of Orchard Park, New York,
Furthermore, the gravamen of NextG’s complaint was that the City’s regulatory scheme as a whole violated Section 253 of the Telecommunications Act of 1996 because the “City assumes that it has the unfettered discretion and power to determine who may or may not provide telecommunications services.” This claim was not mooted by the expiration of Resolution No. 957 or the 2004 RFP. On the contrary, it applied with even greater force after the Resolution and the RFP expired because the expirations worked to prevent, perhaps indefinitely, any entity from using City poles to provide telecommunications services. Further still, even NextG’s more specific claims regarding Resolution No. 957 and the 2004 RFP were not mooted when the Resolution and the RFP expired because there was a reasonable basis on which to anticipate that the ordinances would be reenacted in a form that would raise the same questions,
see Catanzano,
Accordingly, while we affirm the dismissal of NextG’s claim for damages, we reverse the dismissal of its claims for declarative and injunctive relief and remand to the District Court for consideration, inter alia, of NextG’s claims that the City’s regulatory scheme is in material respects prohibited or preempted by the Telecommunications Act of 1996.
Notes
. While NextG claims, and the City disputes, that NextG has no reasonable alternative to such use of Ci1y-owned property, we do not reach that issue here.
. On March 17, 2006, NextG moved for leave to amend its complaint to challenge the legality of Resolution No. 519. The district court denied plaintiff's motion to amend its complaint, finding that Resolution No. 519 had not been previously litigated in the case and that allowing plaintiff to amend would be prejudicial at this stage.
. A Court of Appeals “may, of course, affirm the district court’s judgment on any ground appearing in the record, even if the ground is different from the one relied on by the district court.”
ACEquip Ltd. v. Am. Eng’g Corp.,
. In
TCG Detroit,
the Sixth Circuit declined to hold that it had jurisdiction to adjudicate a claim for preemption under the Supremacy Clause and instead analyzed whether § 253(c) created a private right of action in federal courts.
. Without disturbing the District Court’s December 2006 Order denying NextG’s motion to amend the complaint, we conclude that it would be appropriate on remand for the District Court to permit NextG to amend its complaint to challenge Resolution No. 519 and the 2007 RFP.