State v. United StatesState v. United States
I.
Under the statutory framework of the Waste Act, new repositories were to provide centralized housing for spent nuclear fuel and high-level radioactive waste ("waste") produced by reactors scattered throughout the states. The Waste Act initially envisioned a system in which the Department of Energy would identify a handful of suitable repository sites from which it would recommend three to the president by January 1, 1985.
As directed, the Department of Energy focused on the Yucca Mountain site, conducting a series of preliminary tasks and assessments before in 2002 formally recommending the building of a repository there.
This deadline, too, would go unmet, as just a couple of years later, the Department of Energy hesitated. In 2010, while the tribunal branch of the Nuclear Regulatory Commission, known as the Atomic Safety and Licensing Board (the "Licensing Board"), was reviewing the Yucca Mountain application, the Department of Energy attempted to withdraw the application, professing renewed doubt about the viability of the Yucca Mountain site. Both the Licensing Board and the Nuclear Regulatory Commission denied the request for withdrawal,
Lawsuits followed. Various state and local government entities challenged the Department of Energy's attempt to withdraw the Yucca Mountain application, and in 2011, the D.C. Circuit, in its Aiken I decision, dismissed their complaint for lack of ripeness and finality.
Meanwhile, in 2010, while the Nuclear Regulatory Commission was undertaking the licensing process, then-President Obama established a Blue Ribbon Commission to explore an alternative system of "consent-based siting" for waste storage. The Commission concluded that consent-based siting, not the Yucca Mountain repository, represented the most promising path forward, publishing a strategy document to that effect in 2013 and inviting public comment on the subject in 2015. More recently, in 2017, the Department of Energy published a draft report "lauding the consent-based siting process," and initiated another related public comment period that expired in April 2017. Nothing came of its actions, and the Department of Energy now advises that the Trump Administration "does not intend to take further policy action on the consent-based siting activities in question."
While Texas was not involved, it had its wary eyes on these proceedings, and on March 14, 2017, petitioned this Court for relief, naming various federal entities as defendants, including the Department of Energy, Nuclear Regulatory Commission, Licensing Board, Department of Treasury, and various federal officials associated with these agencies (collectively, the "federal respondents"). Relying on
Seeking several different remedies, Texas characterizes "[t]he thrust" of its petition as a request for "equitable relief prohibiting [the Department of Energy] from conducting any other consent-based siting activity and ordering Respondents to finish the Yucca licensure proceedings," supported by ancillary remedies, such as civil contempt and appointment of a special master. After Texas filed its petition, the Nuclear Energy Institute alongside various nuclear utilities companies (collectively, the "NEI") and the state of Nevada intervened, all of which oppose Texas's petition on jurisdictional and substantive grounds.
II.
As is plain, Texas flies here on creatively fashioned jurisdictional wings. In the ordinary course, civil actions-including petitions for mandamus, one of the remedies Texas seeks-must first be filed in federal district court, our court of first instance.
Texas brings its petition under
(a) Jurisdiction of United States courts of appeals
(1) Except for review in the Supreme Court of the United States, the United States courts of appeals shall have original and exclusive jurisdiction over any civil action-
(A) for review of any final decision or action of the Secretary, the President, or the Commission under this part;
(B) alleging the failure of the Secretary, the President, or the Commission to make any decision, or take any action, required under this part; ....19
Texas asserts that we have this "original and exclusive jurisdiction," a plausible argument if the statute ended there. It does not. It also includes a timeliness requirement: "A civil action for judicial review described under subsection (a)(1) of this section may be brought not later than the 180th day after the date of the decision or action or failure to act involved ...."
And of course, the actions and omissions that Texas challenges came and went years ago.
Sensitive to this hurdle, Texas points us to the continuing violations doctrine. However, before determining whether the continuing violations doctrine should apply to Texas's claims, we must first confront a preliminary question: whether the Waste Act's 180-day deadline imposes a limit on our subject matter jurisdiction. If it does,
III.
In recent years, the Supreme Court has increasingly turned its attention toward distinguishing statutory requirements implicating the subject matter jurisdiction of federal courts from ones that only function as "claim-processing" rules.
Given the bite of jurisdictional rules, and their elusive and protean character, "Congress must do something special" to mark a procedural requirement as jurisdictional.
Against this backdrop, we ask whether "traditional tools of statutory construction" demonstrate with sufficient clarity that the Waste Act's 180-day deadline is jurisdictional. As Nevada reminds us,
The Waste Act's deadline provision does cross-reference the jurisdictional grant.
It is true that several courts in the past have generically described "section 119" of the Waste Act, or
Because we conclude that the deadline in
IV.
The continuing violations doctrine embodies a "muddled," difficult body of law that has long bedeviled courts and commentators alike.
A.
In its form most commonly deployed in our Circuit, "[t]he continuing violations doctrine is equitable in nature and extends the limitations period on otherwise time[-]barred claims."
This test aligns strikingly well with the sole exception that Congress drafted directly into the Waste Act's deadline provision, which provides that a party may avoid the strictures of the 180-day deadline if it can show that it was subjectively unaware of the complained-of actions and that its lack of knowledge was objectively reasonable in the circumstances.
In any event, Texas points to federal actions that, "in fairness and logic," should have alerted it to act years ago. The fact that the government failed to collect waste by the statutory deadline in 1998 has no doubt been obvious for some time, since
B.
We have occasionally applied a slightly different version of the continuing violations doctrine, which more closely resembles a classic exercise in statutory interpretation.
At least two of our previous cases have applied this approach in an administrative setting. In Interamericas Investments , we considered whether the Bank Holding Company Act allows for a continuing violations theory, such that "a new claim accrues each day the violation [of the statute] is extant" and that the statute of limitations is appropriately calculated from the latest violation.
One clear distinction between those two cases and the one before us now is that we have no administrative interpretation holding that a continuing violations theory of accrual is appropriate under the Waste Act. Thus, our examination must begin and end with the statutory text-and this text suggests that Texas's continuing violations theory of accrual is not available. The Waste Act provides that civil actions "alleging the failure of the [government] to make any decision, or take any action , required under this part" are subject to the 180-day statute of limitations.
But under Texas's continuing violations theory, this language would be rendered practically meaningless. Almost all "failure[s] to act" would be ongoing by definition, and would be immunized from the 180-day deadline that Congress provided. Because the statute expressly sets dates for the government's actions that Texas complains have yet to occur, the more natural reading of the statute is that 180-day timer runs from those dates-1998 for the Department of Energy's receipt of waste from the states, and 2012 for Nuclear Regulatory Commission's completion of the Yucca Mountain licensing procedure.
Texas's proposed application of the continuing violations doctrine would also invite litigants to short-circuit the Waste Act's timeliness requirement by framing claims in "failure to act" terms, just as Texas has done in this case. As the Nuclear Regulatory Commission points out, after the Aiken II decision, it has been mostly devoting what public funds it has left to producing a Safety Evaluation Report, a necessary precursor to eventually resolving the licensing application and thus a part of the overall licensing process. But Texas frames this decision as a continuing failure to act , rather than a decision to act in a particular way that it does not like.
The scale of the statute of limitations also bespeaks a congressional purpose to limit civil actions to the ones occurring in the immediate aftermath of a particular Waste Act-related decision by the government. Congress has pegged the appropriate period as approximately half of a year; yet under Texas's approach, decisions made roughly twenty years ago would be open to challenge today. It is beyond our compass to graft either version of the continuing violations doctrine onto the Waste Act's deadline provision. Texas generally points to actions and omissions that passed far more than 180 days ago; we must conclude that the bulk of its arguments are untimely, an outcome that aligns comfortably with the congressional view that to do otherwise would take the third branch into the middle of a most sensitive and delicate accommodation of the competing interests of the several states, here a quintessential political endeavor laced with strictures of science not subject to decision by votes.
Texas does complain of two actions that occurred within the Waste Act's 180-day limitation period: it points out that the Department of Energy disseminated a January 2017 policy document and subsequently engaged in a several-months-long formal comment period concerning consent-based siting for waste disposal. But of course, the Waste Act also specifically limits our review to "final decision[s] or action[s]" undertaken by the government."
In Aiken I , the D.C. Circuit specifically rejected the argument that a Department of Energy policy announcement, "which has no legal consequence," could constitute a "final decision or action" subject to challenge, as required by the Waste Act.
Relatedly, Texas v. U.S. Department of Energy explained that we "interpret 'finality,' as that concept is used in the Administrative Procedure Act, in a 'pragmatic way,' and that approach is appropriate here[, in the Waste Act context,] as well."
VI.
We hold that Texas's claims do not satisfy the statutory requirements of timeliness or finality, and we therefore must dismiss them.
Notes
See Nuclear Waste Policy Amendments Act of 1987, Pub. L. No. 100-203,
See In re Aiken County ,
See
See
In re U.S. Department of Energy ,
In re U.S. Department of Energy ,
See Aiken I ,
See In re Aiken County ,
In re U.S. Department of Energy , CLI-13-08,
Id. at *3. The Nuclear Regulatory Commission also focused on uploading licensing support network documents onto a new recordkeeping system, and completing a supplemental environmental impact statement. Id. at *5-6.
See
Indeed, in 1998, the Waste Act's statutory deadline for acceptance of waste passed; in 2010, the Department of Energy attempted to withdraw its Yucca Mountain licensing application from the consideration of the Licensing Board; in 2010, President Obama established his Blue Ribbon Commission on consent-based siting; in 2011, the Nuclear Regulatory Commission suspended the Yucca Mountain licensing proceeding; in 2012, the Waste Act's statutory deadline for completion of the Yucca Mountain licensing proceeding passed; in 2013, the Nuclear Regulatory Commission sought the views of participants on how to proceed with the licensing proceeding and settled on creating a Safety Evaluation Report; in 2013, the Department of Energy released a strategy document relating to consent-based siting; and in 2017, the Department of Energy released an additional consent-based siting document and initiated a public comment period.
See Dolan v. United States ,
See, e.g. , United States v. Kwai Fun Wong , --- U.S. ----,
Herr v. U.S. Forest Serv. ,
Kwai Fun Wong ,
See
Shinseki ,
See Bowles v. Russell ,
Kwai Fun Wong ,
See Pennhurst State Sch. & Hosp. v. Halderman ,
See Cannon v. Univ. of Chi. ,
See, e.g. , Alexander v. Sandoval ,
Kwai Fun Wong ,
Kwai Fun Wong ,
See
See, e.g. , H.R. Rep. No. 97-491(I), at 57 (1982) ("Section 119(c) provides that civil actions for judicial review described under this section may be brought not later than the 180th day after the date of the action or decision or failure to act involved.").
See Nuclear Energy Inst., Inc. v. EPA ,
See Nuclear Energy Inst., Inc. ,
See Neb. Pub. Power Dist. v. United States ,
See Kwai Fun Wong ,
Herr ,
See, e.g. , Earle v. District of Columbia ,
See, e.g. , Doe v. United States ,
See Interamericas Invs., Ltd. v. Bd. of Gov'rs ,
Pegram v. Honeywell, Inc. ,
Compare Heath v. Bd. of Sup'rs ,
See Nat'l R.R. Passenger Corp. v. Morgan ,
Doe ,
See Earle ,
Interamericas Invs., Ltd. ,
See
See
See Newell Recycling Co. v. EPA ,
Compare
See
The D.C. Circuit, examining the Waste Act's timeliness requirement several decades ago, explained that "[a]lmost any objection to an agency action can be dressed up as an agency's failure to act," and that to allow petitioners to simply frame their claims as such and apply a different statute of limitations on that basis would be to "make a nullity of statutory deadlines." See
Bennett v. Spear ,