891 F.3d 553
5th Cir.2018Background
- The Nuclear Waste Policy Act (NWPA) set deadlines for federal action: DOE to begin accepting spent nuclear fuel by Jan 31, 1998, and NRC to decide on a Yucca Mountain construction application within prescribed years (effectively by 2012).
- DOE focused on Yucca Mountain, Congress designated it sole candidate in 1987; DOE delayed, formally recommended Yucca in 2002 and filed an NRC application in 2008.
- NRC licensing review stalled: DOE tried to withdraw the application (2010); NRC/ALJ refused withdrawal but the Licensing Board paused proceedings for lack of funds; D.C. Circuit decisions (Aiken I and II) followed, directing NRC to continue licensing.
- DOE later pursued "consent-based siting" (Blue Ribbon Commission, policy documents, public comment periods in 2013 and 2017); Texas filed suit in this court in March 2017 challenging DOE/NRC actions and failures under 42 U.S.C. § 10139(a)(1).
- NWPA grants courts of appeals "original and exclusive jurisdiction" for certain challenges but contains a separate 180-day filing deadline for bringing such actions (42 U.S.C. § 10139(c)).
- Texas sought equitable and injunctive relief (including mandamus) to stop consent-based activities and to compel completion of Yucca licensing; Nevada moved to dismiss for lack of timeliness and finality.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether NWPA's 180-day filing deadline is jurisdictional | Texas: §10139(c) governs courts of appeals actions and thus gives this court original jurisdiction despite timing | Nevada/Gov: The 180-day provision is a claim-processing rule, not a jurisdictional bar; it is separable from the jurisdictional grant in §10139(a) | Held: The 180-day deadline is not jurisdictional (Congress did not clearly state it was). |
| Whether equitable tolling / continuing violations toll the 180-day deadline | Texas: continuing violations/equitable tolling apply because DOE/NRC conduct is ongoing (consent-based activity, failure to accept waste, stalled licensing) | Defs: Plaintiffs were on notice of discrete acts long ago; doctrine applies sparingly; NWPA itself has a knowledge-based exception | Held: Equitable tolling/continuing-violations tolling does not save Texas's claims—most challenged acts occurred far outside 180 days. |
| Whether the statute contemplates accrual under a continuing-violation (daily accrual) theory | Texas: failures to act are ongoing so each day creates a new claim | Defs: NWPA text treats "failure to act" as discrete events and sets specific statutory dates; allowing continuing accrual would nullify the 180-day limit | Held: Statutory text favors discrete-event accrual; continuing-accrual theory rejected for NWPA failures-to-act claims. |
| Whether DOE's Jan 2017 consent-based siting document and comment period are final actions reviewable within 180 days | Texas: the 2017 documents are recent agency actions subject to review | Defs: The documents were non-binding draft/policy solicitations and not final agency actions under NWPA/APA | Held: The 2017 policy publication and comment solicitation are not final actions with legal consequence; court lacks jurisdiction to review them. |
Key Cases Cited
- In re Aiken County, 645 F.3d 428 (D.C. Cir. 2011) (addressed DOE attempt to withdraw Yucca application; dismissed earlier challenge as unripe)
- In re Aiken County, 725 F.3d 255 (D.C. Cir. 2013) (directed NRC to continue licensing; mandated resumption absent congressional direction or lack of funds)
- United States v. Kwai Fun Wong, 135 S. Ct. 1625 (2015) (distinguishes jurisdictional rules from claim-processing rules)
- Dolan v. United States, 560 U.S. 605 (2010) (jurisdictional deadlines are absolute and non-waivable)
- Bennett v. Spear, 520 U.S. 154 (1997) (finality under the APA requires consummation of agency decisionmaking and legal consequences)
