VERMONT DEPARTMENT OF PUBLIC SERVICE еt al., Petitioner v. UNITED STATES of America and Nuclear Regulatory Commission, Respondents
Nos. 11-1168, 11-1177
United States Court of Appeals, District of Columbia Circuit.
Decided June 26, 2012.
684 F.3d 149
Entergy Nuclear Operations, Inc. and Entergy Nuclear Vermont Yankee, LLC, Intervenors. Argued May 9, 2012.
Nos. 11-1168, 11-1177.
United States Court of Appeals, District of Columbia Circuit.
Argued May 9, 2012.
Decided June 26, 2012.
VERMONT DEPARTMENT OF PUBLIC SERVICE et al., Petitioner
v.
UNITED STATES of America and Nuclear Regulatory Commission, Respondents
Mark D. Davis and Christopher J. Wright were on brief for amici curiae Riverkeeper et al. in support of the petitioners. Timothy J. Simeone entered an appearance.
Eric T. Schneiderman, Attorney General, Office of the Attorney General for the State of New York, and Barbara D. Underwood, Solicitor General, were on brief for amicus curiae State of New York in support of the petitioners. John J. Sipos and Lisa M. Burianek, Assistant Attorneys General, and Monica B. Wagner, Assistant Solicitor General, entered appearances.
Sean D. Croston, Attorney, United States Nuclear Regulatory Commission, argued the cause for the respondents. John E. Arbab, Attorney, United Statеs Department of Justice, Stephen G. Burns, General Counsel, United States Nuclear Regulatory Commission, and John F. Cordes, Jr., Solicitor, were on brief.
Kevin P. Martin argued the cause for intervenors Entergy Nuclear Operations, Inc. et al. David R. Lewis and Elise N. Zoli were on brief.
Adam J. White was on brief for amicus curiae Energy Future Coalition in support of the respondents.
Opinion for the Court filed by Circuit Judge HENDERSON.
KAREN LECRAFT HENDERSON, Circuit Judge:
The Vermont Department of Public Service (DPS) and the New England Coalition (NEC) petition for review of a decision of the Nuclear Regulatory Commission (NRC, Commission), issuing to Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc. (collectively, Entergy) a renewed license to operаte the Vermont Yankee Nuclear Power Station (Vermont Yankee). The petitioners contend the license renewal was unlawful because Entergy failed to furnish a state Water Quality Certification (WQC) which they assert was required under section 401(a)(1) of the Clean Water Act (CWA),
I.
The Atomic Energy Act (AEA) authorizes the NRC to issue an initial license to operate a nuclear power plant for a term of up to 40 years.
Any applicant for a Federal license or permit to conduct any activity including, but not limited to, the construction or operation of facilities, which may result in any discharge into the navigable waters, shall provide the licensing or permitting agency a certification from the State in which the discharge originates or will originate ... that any such discharge will comply with the applicable provisions of [
33 U.S.C. §§ 1311 ,1312 ,1313 ,1316 , and1317 ].... No license or permit shall be granted until the certification required by this section has been
obtained or has been waived as provided in the preceding sentence. No license or permit shall be granted if certification has been denied by the State, interstate agency, or the Administrator, as the case may be.
An operating licensee may also be required to maintain a permit issued under the “National Pollutant Discharge Elimination System” (NPDES) pursuant to CWA section 402. Section 402 authorizes the Environmental Protection Agency (EPA) to “issue a permit for the discharge of any pollutant, or combination of pollutants ... upon condition that such discharge will meet ... all applicable requirements under [
On January 25, 2006, Entergy filed an application with the NRC for a 20-year renewal of Vermont Yankee‘s operating license, which was set to expire on March 21, 2012. Included with the application was an environmental report, as requirеd under
As reported in the [Final Environmental Statement] (1972), the Vermont Water Resources Board provided a water quality certification on October 29, 1970, as amended on November 26, 1971, reflecting its receipt of reasonable assurance that operation of Vermont Yankee will not violate applicable water quality standards. In addition, the current and effective NPDES permit issued by the Vermont Agency of Natural Resources reflects continued compliance with applicable CWA standards. Excerpts of this permit are included in Attachment D.
On March 27, 2006, the NRC published a notice announcing it had accepted the Vermont Yankee license renewal application and planned to prepare a site-specific environmental impact statement therefor as a supplеment to its Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants (May 1996) (GEIS) pursuant to the National Environmental Policy Act of 1979 (NEPA),
DPS and NEC filed, respectively, three and six contentions challenging Entergy‘s application, only one of which is relevant here. NEC‘s “Contention 1” asserted that “Entergy‘s environmental report (ER) failed to ‘sufficiently assess[ ]’ the environmental impacts of the license renewаl, specifically the impacts of increased thermal discharges into the Connecticut River over the 20-year license renewal period.” Entergy Nuclear Vt. Yankee, LLC, 64 N.R.C. 131, 175 (Sept. 22, 2006) (alteration in original). NEC contended in particular:
Entergy‘s reliance solely on its NPDES permit is not sufficient because the permit is under appeal and, even if issued, will only be valid for 5 years, (2006-2011), and thus will not cover the cumulative impacts of thermal discharges over the 20-year period of the license renewal term (2012–2032).
Id. Entergy answered, inter alia, that once it provided a valid Vermont NPDES per
Entergy moved to strike portions of NEC‘s reply, including “NEC‘s new claims regarding 401 certification” which were not “related to the purported bases for the original contention.” Entergy‘s Mot. to Strike Portions of NEC‘s Reply 10 (July 10, 2006). Entergy explained that “the allegations concerning Contention 1 in NEC‘s Petition related solely to whether the Environmental Report had adequately addressed the impacts of a 1° increase in the thermal effluent limitations recently approved in an amendment to the NPDES permit” and neither Contention 1 nor Entergy‘s response “had anything to do with the need for a section 401 certification,” which was “newly alleged.” Id. In reрly, NEC stated it was “important to note that § [] 401 Water Quality Certification is jurisdictional and imposes an independent obligation on Entergy and the NRC, regardless of whether the need for certification is raised as a contention.” NEC‘s Opp‘n to Entergy‘s Mot. to Strike Portions of NEC‘s Reply 7 (July 20, 2006).
Following oral argument before the Board in August 2006, NEC filed a “Late Contention or, Alternatively, Request for Leave to Amend or File a New Contention” (Late Contention/Req. to Amend) (Aug. 7, 2006), which attempted to add the section 401 objection as a further basis for Contention 1:
Further basis demonstrating the inadequacy of Entergy‘s amended environ
mental report is the absence of a CWA § 401 Water Quality Certifiсation. Entergy is on notice that its requested license extension cannot issue without a § 401 Certification. Yet Entergy‘s amended environmental report makes no mention of any effort to seek and obtain § 401 Certification.
Late Contention/Req. to Amend, at 4-5. After Entergy and NRC staff responded in opposition, NEC filed a reply stating:
Based on NEC‘s prior filings in this matter, Entergy is on notice that its requested license extension cannot issue without a Clean Water Act § 401 certification. Astonishingly, Entergy‘s Amendment 6 to its Environmental Report nonetheless makes no mention of this issue....1
NEC‘s Reply to Entergy & NRC Staff‘s Answers to NEC‘s Late Contention/Req. to Amend, at 5-6 & n. 1 (Aug. 28, 2006).
On September 22, 2006, the Board admitted for hearing several of NEC‘s contentions, including Contention 1, but granted Entergy‘s motion to strike the “portions of NEC‘s Reply that relate[d] to certification under 401,” “agree[ing] with Entergy that NEC‘s attempt to introduce an entirely new argument regarding the alleged need for a section 401 certification is not permissible in a reply.” Entergy Nuclear Vt. Yankee, LLC, 64 N.R.C. 131, 182 (Sept. 22, 2006).6 On October 2, 2006, the Board denied NEC‘s Late Contention/Request
In December 2006, the NRC published a Draft Supplemental Environmental Impact Statement (Draft SEIS). Generic Envtl. Impact Statement for License Renewals of Nuclear Plants, Supp. 30 (Regarding Vt. Yankee Nuclear Power Plant) (Dec.2006) (Draft Report for Comment). An appendix to the Draft SEIS enumerated the required governmental approvals, pursuant to
The Board held an evidentiary hearing in July 2008 and, on November 24, 2008, issued a Partial Initial Decision resolving all but one of the remaining admitted contentions. Entergy Nuclear Vt. Yankee, LLC, 68 N.R.C. 763 (2008). The order stated:
With the exception of [two contentions resolved in favor of NEC and DPS and the one unresolved contention] and the opportunity to seek reconsideration of facts officially and judicially noticed, this Partial Initial Decision shall constitute the final decision of the Commission forty (40) days after the date of its issuance, unless, within fifteen (15) days of its service, a petition for review is filed in accordance with
10 C.F.R. §§ 2.1212 and2.341(b) . Filing a petition for review is mandatory for a party to exhaust its administrative remedies beforе seeking judicial review.10 C.F.R. § 2.341(b)(1) .
Id. at 897. Both of the regulations the Board‘s decision cited—
II.
The court has jurisdiction under the Hobbs Act,
We have recognized two distinct species of exhaustion requirements: (1) “non-jurisdictional exhaustion,” which is “a judicially created doctrine requiring pаrties who seek to challenge agency action to exhaust available administrative remedies before bringing their case to court“; and (2) “jurisdictional exhaustion,” which “arises when Congress requires resort to the administrative process as a predicate to judicial review.” Avocados Plus Inc. v. Veneman, 370 F.3d 1243, 1247 (D.C.Cir. 2004) (internal quotation marks omitted). “We presume exhaustion is non-jurisdictional unless ‘Congress states in clear, unequivocal terms that the judiciary is barred from hearing an action until the administrative agency has come to a decision.‘” Id. at 1248 (quoting I.A.M. Nat‘l Pension Fund Benefit Plan C v. Stockton Tri Indus., 727 F.2d 1204, 1208 (D.C.Cir. 1984)). The language of the Hobbs Act offers no such unequivocal bar. Cf. Daniels v. Union Pac. R.R. Co., 530 F.3d 936, 941 n. 9 (D.C.Cir.2008) (relying in part on exhaustion‘s non-jurisdictionаl presumption in declining to affirm district court‘s dismissal of Hobbs Act action based on
In Sims v. Apfel, 530 U.S. 103, 108, 120 S.Ct. 2080, 147 L.Ed.2d 80 (2000), the United States Supreme Court observed that when “an agency‘s regulations [] require issue exhaustion in administrative appeals[,] courts reviewing agency action regularly ensure against the bypassing of that requirement by refusing to consider unexhausted issues.” In Environmentel, LLC v. FCC, 661 F.3d 80, 84 (D.C.Cir.2011), relying on Sims, we concluded the petitioner had waived two issues it urged on appeal—one it had presented to a Federal Communications Commission (FCC) bureau but not to the FCC itself and one it had not raised at all at the administrative level. We based our conclusion on an FCC regulation which (1) authorizes a “person aggrieved by any action taken pursuant to delegated authority [to] file an application requesting review of that action by the [FCC],” (2) requires a party seeking review by the full Commission of a decision by a delegated bureau to “concisely and plainly state the questions presented for review” and (3) provides that the “filing of an application for review shall be a condition precedent to judicial review of any action taken pursuant to delegated authority.”
They could have petitioned the Commission for interlocutory review of the Board‘s denial of their Late Contention/Request to Amend pursuant to
The petitioners contend it would have been futile to raise the section 401 issue before the Commission, which “has clearly held that the issue of whether an applicant possesses a required CWA authorization is
For the foregoing reasons, we conclude that the petitioners failed to exhaust their administrative remedies before the Commission and thereby waived the right to raise their section 401 objection on judicial review. Accordingly, we deny their petitions for review.
So ordered.
Notes
Parties may file petitions for review of an initial decision under this subpart in accordance with the procedures set out in § 2.341. Unless otherwise аuthorized by law, a party to an NRC proceeding must file a petition for Commission review before seeking judicial review of an agency action.10 C.F.R. § 2.1212 . Regulation 2.341 in turn provides in relevant part: (b)(1) Within fifteen (15) days after service of a full or partial initial decision by a presiding officer, and within fifteen (15) days after service of any other decision or action by a presiding officer with respect to which a petition for review is authorized by this part, a party may file a petition for review with the Commission on the grounds specified in paragraph (b)(4) of this section. Unless otherwise authorized by law, a party to an NRC proceeding must file a petition fоr Commission review before seeking judicial review of an agency action.10 C.F.R. § 2.341(b)(1) .
