SOEP PAINTING CORP. vs. GRAYCOR CONSTRUCTION COMPANY, INC., & others.
22-P-1173
COMMONWEALTH OF MASSACHUSETTS APPEALS COURT
September 20, 2023
NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel‘s decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
The defendant appeals from an amended separate and final judgment, entered pursuant to
In Le Fort Enterprises, Inc. v. Lantern 18, LLC, 491 Mass. 144, 151-152 (2023) (Le Fort), the Supreme Judicial Court recently explained the doctrine of impossibility in the context of the COVID-19 pandemic.
“The modern impossibility doctrine provides:
‘[W]here from the nature of the contract it appears that the parties must from the beginning have contemplated the continued existence of some particular specified thing as the foundation of what was to be done, then, in the absence of any warranty that the thing shall exist, the contract is to be construed not as a positive contract, but as subject
to an implied condition that the parties shall be excused in case before breach performance becomes impossible from the accidental perishing of the thing without the fault of either party . . . . The misfortune which has occurred releases both parties from further performance of the contract and gives no right to either to claim damages from the other’ (ellipses in original).”
Id., quoting Boston Plate & Window Glass Co. v. John Bowen Co., 335 Mass. 697, 700 (1957). The question here is whether the summary judgment record could sustain the defendant‘s burden to show that its performance was rendered impossible because of the COVID-19 pandemic. See Le Fort, supra at 154. The defendant failed to meet its burden because, as in Le Fort, the “absence of a causal link is fatal.” Id. at 155. Specifically, the summary judgment record did not raise a triable issue of fact that the owner‘s financial difficulties made it impossible for the defendant, who was the general contractor, to perform its obligations under the contract to the plaintiff, who was the subcontractor.
“The fact that one is unable to perform a contract because of the inability to obtain money . . . will not ordinarily excuse nonperformance in the absence of a contract provision in that regard. . . . [S]imply positing two facts -- that the pandemic has occurred, and that a party finds it very difficult or even impossible to perform its contractual obligations -- is not enough.” (Quotations and citations omitted.)
The amended separate and final judgment entered pursuant to
So ordered.
By the Court (Wolohojian, Shin & Ditkoff, JJ.4),
Clerk
Entered: September 20, 2023.
