SIERRA CLUB, PETITIONER v. FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT EMPIRE PIPELINE, INC. AND NATIONAL FUEL GAS SUPPLY CORPORATION, INTERVENORS; SIERRA CLUB AND PUBLIC CITIZEN, PETITIONERS v. FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT CHENIERE CORPUS CHRISTI PIPELINE, L.P. AND CORPUS CHRISTI LIQUEFACTION, LLC, INTERVENORS
No. 22-1233, No. 22-1235, Consolidated with 22-1267
Unitеd States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT
Argued September 18, 2023 Decided March 29, 2024
On Petition for Review of an Order of the Federal Energy Regulatory Commission
Nathan Matthews argued the cause for petitioner. With him on the briefs was Ankit Jain, at the time the brief was filed. Thomas Gosselin entered an appearance.
Susanna Y. Chu, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.
Eamon P. Joyce argued the cause for respondent-intervenors. With him on the brief was Brooke E. Boyd. Emily P. Mallen entered an appearance.
Michael Diamond and Michael R. Pincus were on the brief for amicus curiae Interstate Natural Gas Associаtion of America in support of respondent.
Nathan Matthews argued the cause for petitioners. With him on the briefs was Thomas Gosselin.
Matthew J. Glover, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor. Susanna Y. Chu, Attorney, entered an appearance.
Catherine E. Stetson argued the cause for respondent-intervenors. With her on the brief were Sean Marotta and Michael West.
Before: HENDERSON and PAN, Circuit Judges, and ROGERS, Senior Circuit Judge.
Opinion for the Court filed by Circuit Judge PAN.
PAN, Circuit Judge: When the Federal Energy Regulatory Commission (“FERC” or the “Commission“) approves the construction of natural-gas infrastructure, such as a pipeline, it sets a deadline for the completion of the construction project. If the project developer requests an extension of that deadline, FERC generally will grant the request if the developer (i) shows “good cause” for needing the extension, in a motion made before the deadline expires,
extensions. Because FERC acted well within its discretion in both cases, we deny the petitions for review.
I.
A.
Under the Natural Gas Act (“NGA“),
Any person may file comments about whether a natural-gas infrastructure project should be approved.
in the public interest.“);
The NGA does not require FERC to set deadlines for the completion of construction projects. But FERC has authority to “perform any and all acts” to “prescribe, issue, make, amend, [or] rescind” a certificate order, “as [the agency] may find necessary or appropriate to carry out the [NGA].”
Under a FERC regulation, “[a]ny authorized construction [or] extension . . . shall be completed and made available for service . . . within [a] period of time to be specified by the Commission in each order.”
developers from holding on to certificates for so long thаt they “inhibit a potential competitor from pursuing its own project to serve the same market.” Id. at P 9.
When a developer applies for an extension, FERC publishes the application so that any person can provide comments about whether the extension should be granted. See Algonquin Gas, 170 FERC ¶ 61,144, at P 39.1 If FERC issues an extension order, persons that opposed the extension can submit a request for rehearing. See
after the issuance of such order“). FERC can deny rehearing either by operation of law, when it declines to act on the rehearing request within thirty days, or by issuing an order explaining its rationale for the denial.
B.
National Fuel Gas Supply Corporation (“National Fuel“) seeks to build the 99-mile Northern Access Pipeline across Pennsylvania and New York. The proposed pipeline will connect gas producers to markets in Canаda and throughout the northeastern United States. FERC first approved the pipeline project in a 2017 Certificate Order, requiring it to be completed by February 3, 2019. Nat‘l Fuel Gas Supply Corp., 158 FERC ¶ 61,145 (2017), on reh‘g, 164 FERC ¶ 61,084 (2018). But National Fuel ran into a major hurdle: The New York State Department of Environmental Conservation (“NYSDEC“) denied its application for a water-quality certification under section 401 of the Clean Water Act (“CWA“). National Fuel challenged that decision, spawning years of litigation in the Second Circuit. As a result of the ongoing litigation, FERC granted National Fuel an extension of time in 2019, pushing the deadline for project completion back to February 3, 2022. The 2019 extension is not at issue in this case.
In 2021, National Fuel prevailed in the Second Circuit litigation. Natiоnal Fuel‘s period of legal uncertainty ended
when NYSDEC‘s time to petition the Supreme Court for a writ of certiorari expired. Five
Sierra Club moved to intervene and submitted a protest opposing the extension. Sierra Club‘s protest noted that National Fuel‘s request for an extension “offers no explanation” as to “[w]hat permits it is referring to” and “[w]hat steps remain to be taken for these permits.” Nat‘l Fuel J.A. 64–65 (emphаsis omitted). FERC responded to the protest by sending National Fuel a request for additional information about the environmental permits that it needed to update. National Fuel promptly submitted a chart that clarified the status of each of its environmental permits under the CWA and the Endangered Species Act. FERC then issued an Extension Order granting National Fuel a 35-month extension of its deadline, until December 31, 2024. FERC determined that there was “[g]ood cause” for the extension because “[t]he Commission has previously found that providing more time for a project applicant to obtain necessary permits can be an appropriate basis for granting an extension of time.” Nat‘l Fuel Extension Order, 179 FERC ¶ 61,226, at P 15.
Sierra Club filed a request for rehearing, contesting FERC‘s finding of good cause for the extension. Sierra Club claimed that National Fuel had not diligently pursued the project because National Fuel did not actively procure necessary permits. Sierra Club also argued that FERC failed to appropriately consider whether the original Certificate Order‘s findings remained valid and failed to supplement its NEPA analysis based on new circumstances. As part of its NEPA
argument, Sierra Club asserted that FERC had failed to address the impact of a new statute, the 2019 New York Climate Leadership and Community Protection Act (“Climate Act“), on project need. FERC issued a notice of denial of rehearing by operation of law. Sierra Club timely petitioned for review of the Commission‘s Extension Order. See
C.
Corpus Christi Liquefaction Stage III, LLC, Corpus Christi Liquefaction, LLC, and Cheniere Corpus Christi Pipeline, LP (collectively, “Cheniere“) sought FERC‘s approval to build a series of improvements to an existing liquefied natural gas (“LNG“) terminal on Texas‘s Corpus Christi Bay and a related pipeline. Corpus Christi Liquefaction Stage III, LLC, 169 FERC ¶ 61,135, at P 1–2 (2019). FERC granted its approval in a 2019 Authorization Order, which included a certificate of public convenience and necessity. The Authorization Order required the project to be completed by November 22, 2024.
In 2021, Cheniere filed a request to extend the deadline for its project by 31 months, until June 30, 2027. Cheniere cited the COVID-19 pandemic as the reason for its delay — sрecifically, it stated that the “onset and duration of the COVID-19 pandemic resulted in adverse economic and logistical conditions that slowed commercial progress and precluded [Cheniere] from making a timely Final Investment Decision (‘FID‘) on the [project].” Cheniere J.A. 26. Sierra Club and Public Citizen filed motions to intervene and filed a protest opposing the extension and contesting good cause.
FERC granted Cheniere‘s extension request. The Extension Order found that Cheniere had established good cause for an extension because “[t]he unforeseeable impacts of the COVID-19 pandemic combined
continued interest in the project satisfy the Commission‘s good cause inquiry.” Order Granting Extension оf Time Request, Corpus Christi Liquefaction Stage III, LLC (Cheniere Extension Order), 179 FERC ¶ 61,087, at P 13 (2022). Sierra Club and Public Citizen submitted a request for rehearing of the Extension Order, which FERC denied by operation of law. See
Thereafter, FERC issued an Order on Rehearing. The Rehearing Order provided further explanation of FERC‘s decision to grant the extension by elaborating on the public-interest findings and addressing certain NEPA arguments. With respect to good cause, the Rehearing Order stated: “[I]n the Extension Order, the Commission adequately addressed the [Petitioners‘] arguments regarding the Commission‘s conclusion that the companies demonstrated good cause for delay.” Order on Rehearing, Corpus Christi Liquefaction Stage III, LLC, 181 FERC ¶ 61,033, at P 9 (2022). Sierra Club and Public Citizen filed a timely petition for review of the Rehearing Order. We consolidated the appeals of Cheniere‘s Extension Order (No. 22-1235) and Rehearing Order (No. 22-1267).2
II.
FERC‘s authority to set and extend construction deadlines is rooted in its broad power to “perform any and all acts” to “prescribe, issue, make, amend, [or] rescind” a construction-
authorization certificate — a power that may be exercised whenever the Commission deems it “necessary or appropriate to carry out the [NGA].”
FERC‘s discretion in granting an extension of time for a natural-gas construction project is limited only by the arbitrary-and-capricious standard of the Administrative Procedure Act (“APA“). See
III.
Both National Fuel and Cheniere filed timely applications for extensions of time to complete their construction projects,
and FERC found “good cause” to grant their requests. See
A.
FERC generally grants a timely application for an extension of a construction deadline if a project sponsor demonstrates “good cause” for its request,
61,226, at P 10 (2022); accord Cheniere Extension Order, 179 FERC ¶ 61,087, at P 8.3
FERC‘s reasoning in each of the instant cases is consistent with the Commission‘s previous dеterminations of how good cause “can be shown.” E.g., Cheniere Extension Order, 179 FERC ¶ 61,087, at P 8; Delfin LNG LLC, 178 FERC ¶ 61,031, at P 10 (2022). For example, the Commission has found that sponsors made good-faith efforts where they advanced their projects by applying for permits, engaging in litigation, acquiring necessary land rights, or negotiating with state agencies. See, e.g., Arlington Storage Co., 155 FERC ¶ 61,165, at PP 11–13 (noting that Arlington had all necessary property rights and was continuing to work with a New York state agency); Algonquin Gas, 170 FERC ¶ 61,144, at PP 26–29 (citing Algonquin‘s filing of lawsuits challenging zoning and wetlands ordinances). Moreover, in examining
caused by lawsuit); Mountain Valley Pipeline, LLC, 173 FERC ¶ 61,026, at P 12 (2020) (delay сaused by legal challenges affecting permits from five different federal agencies); Adelphia Gateway, 178 FERC ¶ 61,030, at PP 19–20 (delay caused by COVID-19‘s disruption of state agencies, construction activities, and material procurement). In sum, in the cases on review, the Commission followed its reasonable practice of evaluating the project sponsor‘s diligence and the reasons for delay in determining whether the extension requests were supported by “good cause.”
Petitioners argue that FERC‘s “good cause” inquiry is too lax, asserting that the agency essentially rubber-stamps all requests for extensions of time. See Oral Argument at 18:15, Sierra Club v. FERC (No. 22-1235) (noting that FERC almost never “says no” to extension requests). Although it is true that FERC has denied very few extension requеsts, that is not surprising.4 Project sponsors invest significant time and resources to secure approval of their pipelines and related facilities, and they generally have economic incentives to promptly complete construction. Accordingly, sponsors typically can meet the “good cause” standard by demonstrating their diligence and citing factors beyond their control that have slowed their progress. See, e.g., Algonquin Gas, 170 FERC ¶ 61,144, at P 34; Mountain Valley Pipeline, 173 FERC ¶ 61,026, at P 12. Project developers who intend to abandon a
project likely would not request any extension. See Wyoming-California Pipeline Co., 70 FERC ¶ 61,041, 61,130 (1995) (rescinding a certificate because a developer still had not applied for an extension with only a month left before the deadline). Thus, the percentage of extensions granted is not necessarily evidence that the Commission‘s decision-making process is faulty. To the contrary, the standard adopted by FERC is reasonable and falls well within the Commission‘s broad discretion to “amend” a certificate order as “necessary or appropriate.”
B.
The foregoing framework for determining “good cause” to extend a construction deadline assumes that the facts and determinations underlying the original certificate approval have not changed. Where there has been no significant shift in the relevant circumstances, FERC generally declines to reevaluate issues that already were addressed when the agency first approved the project. See, e.g., Algonquin Gas, 170 FERC ¶ 61,144, at P 40 (“The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and . . . the Commission‘s environmental analysis.“). This forward-looking policy promotes the interests of FERC and project developers in finality: It allows FERC to avoid duplicating the extensive work that was done when granting the certificate;
extension of time, orders on certificates of public convenience and necessity are final.“).
FERC has leeway, however, to revisit prior market-need or environmental findings when new circumstances render such findings stale or out of date. See Algonquin Gas, 170 FERC ¶ 61,144, at P 15 (noting that the good cause standard applies only “within a timeframe during which the environmental and other public interest findings underlying the Commission‘s authorization can be expected to remain valid“). In such circumstances, FERC may account for the changed conditions by relying on its discretion to “amend” a certificate order as “necessary or appropriate.”
Sierra Club argues that § 717o requires FERC to re-evaluate the findings underlying the original certificate order any time that it considers an extension request to ensure that its decision is “appropriate.” We disagree. Section 717o is a broad grant of authority to FERC. It empowers FERC to take whatever actions “it may find necessary or appropriate” to amend a certificate of public convenience and necessity.
Nevertheless, FERC must sometimes account for substantial or significant changes that impact a project‘s approval when fulfilling the Commission‘s independent obligation to comply with NEPA.
the proposed action that are relevant to environmental concerns” or “[t]here are significant new circumstances or information relevant to environmental concerns.”
In sum, the NGA, NEPA, and the Commissiоn‘s prior precedents all provide bases for FERC to revisit its prior findings due to a significant change in circumstances. The Commission revisits its prior findings if it believes doing so is “necessary or appropriate” under the NGA or is mandated by NEPA; and it has substantial discretion to amend an approval certificate on those grounds.
C.
Applying the foregoing principles, we conclude that FERC adequately explained its rationale for finding good cause to grant National Fuel‘s request for an extension of its project deadline. FERC cited its long-standing practice of granting extensions to “provid[e] more time for a project applicant to obtain necessary permits.” Nat‘l Fuel Extension Order, 179 FERC ¶ 61,226, at P 15. The Commission recognized that the Second Circuit litigation was “part of [National Fuel‘s] efforts to obtain a state authorization,” which demonstrated National Fuel‘s “continued interest in the project.” Id. FERC also noted that the litigation was a significant obstacle to the project‘s advancement that was beyond National Fuel‘s control. Id. at P 5. FERC‘s application of its “good cause” standard to National Fuel‘s circumstances was well “within the bounds of reasoned decisionmaking.” Balt. Gas & Elec. Co. v. NRDC, 462 U.S. 87, 105 (1983).
Sierra Club errs in arguing that “good faith” invariably requires a project sponsor to actively pursue all needed permits. Because National Fuel did not pursue certain permits between August 2021 and January 2022, Sierra Club asserts that FERC must explain why it nevertheless found good cause to grant the extension. Sierra Club‘s proposed interpretation of “good faith” is unduly exacting. While continuously and actively pursuing permits may suffice to show good faith, such persistence is not always necessary to meet that standard. FERC may decide, in its discretion, that other typеs of reasonable efforts, other than “active pursuit” of all permits, are sufficient. See, e.g., Algonquin Gas, 170 FERC ¶ 61,144, at PP 34, 36 (responding to an allegation of undue delay by stating “[t]he record before us reflects no bad faith or delay on the company‘s part, but rather what appears to be reasonable efforts to move the project forward“). Here, FERC permissibly
relied on National Fuel‘s litigation of the CWA issue in the Second Circuit as evidence of National Fuel‘s good-faith pursuit of the project. That decision was not arbitrary or capricious.
Sierra Club further argues that circumstances have changed, and that FERC should have denied the extension request because the Northern Access Pipeline is no longer needed. According to Sierra Club, under the NGA and NEPA, FERC was required to reconsider its findings of market need because New York passed the 2019 Climate Act, which requires the state to reduce its natural-gas usage. Sierra Club cites analysis predicting that “end-use gas demand [will] decline[] significantly [in New York], with reductions ranging from 83–95% by 2050.” Nat‘l Fuel J.A. 54 n.16. Thus, according to Sierra Club, FERC must reconsider whether the Northern Access Pipeline still serves new demand for gas and whether construction of the pipeline remains in the public interest.
As an initial matter, Sierra Club‘s argument about the Climate Act was exhausted before the Commission and is properly
Sierra Club contends that FERC‘s failure to consider the effects of the Climate Act renders the Extension Order arbitrary and capricious. But we defer to FERC‘s determinatiоn that circumstances did not change substantially enough to revisit its underlying findings. See Sacramento Mun. Util. Dist., 616 F.3d at 533 (requiring deference to “technical inquir[ies] properly confided to FERC‘s judgment“). Contrary to Sierra Club‘s contentions, FERC‘s decision not to revisit its market-need finding was reasonable and supported by the record evidence: The record demonstrates that the Climate Act will have little effect on the demand for the natural gas transported by National Fuel‘s pipeline. First, the project remains fully subscribed, pursuant to the same precedent agreement that was evaluated in the 2017 Certificate Order.5 Second, the pipeline does not primarily serve New York — it is focused on channeling gas into Canada and throughout the northeastern United States. While the record reflects that some of the gas could be diverted to upstate New York, that relatively insubstantial amount does not undermine FERC‘s determination that the pipeline‘s overall market-need finding remains valid, especially under our deferential standard of review. See Nat‘l Fuel Gas Supply Corp., 158 FERC ¶ 61,145,
at P 32 (noting that 72% of the gas is intended for delivery into Canada, “with the option for delivery along [the pipeline system] in northern and central New York“).
We similarly reject Sierra Club‘s argument that the effects of the Climate Act necessitated a supplemental NEPA analysis. See
D.
FERC also adequately explained its finding of good сause to grant Cheniere an extension. FERC acknowledged that the “adverse economic and logistical impacts of the COVID-19 pandemic prevented [Cheniere] from making a timely investment decision on the project to meet construction deadlines.” Cheniere Extension Order, 179 FERC ¶ 61,087, at P 10. Petitioners argue, however, that FERC‘s finding of good cause was insufficiently supported by specific facts about the pandemic‘s impact on Cheniere‘s investment decision. At oral argument, Petitioners gave examples of the types of facts that
they believe are required, such as the percentage of investment Cheniere still lacked and how many more contracts it needed to enter. Oral Argument at 6:50, Sierra Club v. FERC (No. 22-1235).
Again, Petitioners аdvocate for an unduly high level of stringency in determining good cause. FERC properly exercised its broad discretion to decide what facts were sufficient to meet the “good cause” standard: It relied on Cheniere‘s representation that the pandemic‘s effects on LNG markets prevented it from making a “final investment decision.” As Cheniere explains, a “final investment decision” is an energy-industry term describing the process by which a sponsor secures financing; it requires the project sponsor to “be confident that it will be able to sell a significant percentage of the project‘s output” at an economically viable price. Brief of Cheniere, Sierra Club v. FERC (No. 22-1235), at 7 (quoting Final Investment Decision (FID) (US), Westlaw Practical Law Glossary Item w-026-2352). Although FERC‘s explanation for granting the extension was concise and used industry-specific terminology, the Commission‘s rationale was discernable and therefore adequate. See Bowman Transp., Inc. v. Arkansas-Best Freight Sys., Inc., 419 U.S. 281, 285–86 (1974) (“While we may not supply a reasoned basis for the agency‘s action that the agency itself has not given, we will uphold a decision of less than ideal clarity if the agency‘s path may reasonably be discerned.” (cleaned up)). We therefore uphold FERC‘s decision to grant Cheniere an extension of time to complete its construction project.
* * *
FERC‘s decisions to extend the construction deadlines for the National Fuel and Cheniеre projects were not arbitrary and capricious. To the contrary, the decisions were reasonable and
adequately supported by the record evidence. FERC enjoys broad discretion in determining whether a project developer has demonstrated “good cause” for an extension and whether circumstances have changed enough to warrant revisiting the Commission‘s findings justifying approval of the project. Petitioners’ assertions that FERC is required to adopt a more stringent approach to assessing extension requests are unsupported by the NGA and the APA. Accordingly, we deny the petitions for review.
So ordered.
