Melissa SHELL, an individual, Petitioner on Review, v. THE SCHOLLANDER COMPANIES, INC., dba Schollander Development Company, Respondent on Review. THE SCHOLLANDER COMPANIES, INC., dba Schollander Development Company, an Oregon corporation, Third-Party Plaintiff, v. KUSTOM BUILT CONSTRUCTION, LLC, an Oregon limited liability company; HL Stucco Systems, Inc., an Oregon corporation; Newside, Inc., an Oregon corporation; Western Cedar, Inc., an Oregon corporation; and J & R Gutter Services, Inc., an Oregon corporation, Third-Party Defendants.
CC 106480CV; CA A150509; SC S062791
IN THE SUPREME COURT OF THE STATE OF OREGON
February 19, 2016
358 Or 552
KISTLER, J.
Argued and submitted May 8, 2015. On review from the Court of Appeals. On appeal from Washington County Circuit Court, Donald R. Letourneau, Judge. 265 Or App 624, 336 P3d 569 (2014).
Paul E. Sheely, Smith Freed & Eberhard P.C., Portland, argued the cause and filed the brief for respondent on review. With him on the brief was Jakob Lutkavage-Dvorscak.
Adele J. Ridenour, Ball Janik LLP, Portland, filed the brief for amicus curiae Gerald and Melissa McKee. With her on the brief were Philip E. Joseph and James C. Pritchard.
Christine Moore, Landye Bennett Blumstein LLP, Portland, filed the brief for amicus curiae Oregon Trial Lawyers Association.
Before Balmer, Chief Justice, and Kistler, Walters, Landau, Baldwin, Brewer, and Nakamoto, Justices.**
KISTLER, J.
The decision of the Court of Appeals and the judgment of the circuit court are affirmed.
Case Summary:
The question in this construction defect case is which of two statutes of repose applies when a buyer enters into a purchase and sale agreement to buy an existing home. Although each statute provides for a 10-year period of repose, the two periods of repose run from different dates. One runs from “the date of the act or omission complained of.”
The judgment of the circuit court and the decision of the Court of Appeals are affirmed.
KISTLER, J.
The primary question in this construction defect case is which of two statutes of repose applies when a buyer enters into a purchase and sale agreement to buy an existing home. Although each statute provides for a 10-year period of repose, the two periods of repose run from different dates. One runs from “the date of the act or omission complained of.”
Defendant is a general contractor that builds “spec” houses—houses built without preexisting construction contracts in anticipation of eventual sale to the public.1 Defendant‘s president explained that his company ordinarily does not sell homes to the public until the homes have been completed. In particularly strong markets, however, defendant has sold homes that are approximately 95 percent complete. On May 30, 2000, defendant and plaintiff entered into a purchase and sale agreement for a house. Although most of the construction had been completed, the agreement specified that defendant would make changes to the interior of the house. Specifically, defendant agreed to upgrade some of the flooring, install an air conditioning unit, and install a gas dryer in the laundry room. After defendant made those changes and the parties conducted a walk-through inspection, the sale closed on July 12, 2000.
More than 10 years after plaintiff entered into the purchase and sale agreement but less than 10 years after the sale closed, plaintiff filed a complaint against defendant in which she alleged that, as a result of defendant‘s negligence, some of the exterior elements of her house—the windows, siding, water resistant barrier, and flashing—were defective. In its answer, defendant alleged, as an affirmative defense, that the statute of repose set out in
Plaintiff responded that defendant was relying on the wrong statute of repose. In her view,
After considering the parties’ argument, the trial court ruled that
action), defendant was entitled to summary judgment. The trial court entered judgment accordingly.4
The Court of Appeals affirmed. It reasoned that the 10-year period of repose set out in
We allowed plaintiff‘s petition for review to consider which of the two statutes of repose applies. On that issue, plaintiff does not argue that
As we understand plaintiff‘s argument, it rests on the proposition that
Defendant does not argue otherwise, and we assume that that proposition is correct. The issue, as the parties frame it, is whether plaintiff‘s claims come within the subset of claims to which
At first blush, the text of
As the Court of Appeals observed, however, we cannot look solely at subsection (1) of
“‘Substantial completion’ means the date when the contractee accepts in writing the construction, alteration or repair of the improvement to real property or any designated portion thereof as having reached that state of completion when it may be used or occupied for its intended purpose or, if there is no such written acceptance, the date of acceptance of the completed construction, alteration or repair of such improvement by the contractee.”
The 10-year statute of repose in
We conclude from the text of
The parties do not identify any relevant context, and we turn to the statute‘s legislative history. See State v. Gaines, 346 Or 160, 171-72, 206 P3d 1042 (2009) (describing statutory construction methodology).
The impetus for House Bill (HB) 1259 (1971), which is codified as
To meet that concern, AGCA proposed that the limitations period would run from a fixed date. See Tape Recording, House State and Federal Affairs Committee, Subcommittee on Financial Affairs, HB 1259, May 10, 1971, Tape 16, Side 2 (testimony of J.R. Kalinoski) (explaining that the bill provides “a given period of time after completion of construction, rather than * * * a time period commencing with an injury or damage that might occur“). As initially drafted, subsection 2(1) of the bill provided that claims “against a person, arising from such person‘s work, as a contractor for the construction, alteration or repair of any improvement to real property shall be commenced within six years after the substantial completion of the improvement to real property or within six years after the acceptance of the completed improvement by the contractee, whichever is earlier.” Bill File, HB 1259 § 2(1), Jan 26, 1971 (initial draft). Subsection 2(2) of the initial draft defined “substantial completion” as “the date when the contractee accepts the improvement * * * as having reached the state of completion when it may be used or occupied for its intended purpose.” Id. § 2(2).
Read together, subsections 2(1) and 2(2) of the initial draft applied to claims against “contractors” for the “construction, alteration or repair of any improvement to real property” and required that those claims be brought within six years of either “substantial completion” of the improvement or “acceptance of the completed improvement by the contractee, whichever is earlier.” The bill, as initially drafted, assumed the existence of a contract to construct, alter, or repair an improvement to real property. Moreover, because the events that triggered the period of repose turned on the either the contractor‘s substantial completion of its work or the contractee‘s acceptance of that work as complete, the period of repose necessarily applied only in the context of contracts to construct, alter, or repair improvements to real property.
During the first subcommittee hearing in March 1971, a committee member pointed out what AGCA viewed as a drafting error in the bill,6 and AGCA asked the committee to table the bill so that the error could be
Subcommittee on Financial Affairs, HB 1259, Apr 7, 1971. Over the next two months, the subcommittee made several changes to the bill but did not change the bill‘s essential structure or purpose.
The subcommittee expanded the bill to apply not only to claims against contractors but also to claims against persons who “furnished the design, planning, surveying, architectural or engineering services for such improvement.” Bill File, HB 1259, May 17, 1971, § 2 (House Amendments to Engrossed House Bill). It fixed the drafting error in the initial version of the bill, and it made the period of repose 10 rather than six years. Id. Finally, the subcommittee provided that the period of repose would run from “substantial completion of such construction, alteration, or repair” of the improvement, and it defined “substantial completion” as including essentially the same two events that the original bill had identified as triggering the period of repose.7 Id. §§ 2, 3. That is, it defined “substantial completion” as either the date “when the contractee accepts in writing the construction, alteration or repair of the improvement to real property” or, in the absence of a written acceptance, “the date of acceptance of the completed construction, alteration or repair of such improvement by the contractee.” Id.; see PIH Beaverton, LLC v. Super One, Inc., 355 Or 267, 275-84, 323 P3d 961 (2014) (explaining differences between those two events).
In discussing HB 1259, the proponents of the bill described “acceptance of the completed construction * * * by the contractee” entirely in terms of contract specifications:
“Certain specifications are put out * * * and you complete it in accordance with th[ose specifications]. The owner‘s acceptance is conditioned upon his acknowledgement that you‘ve completed your work and you‘ve completed in accordance with his desires and his specifications. Certainly,
there should be an obligation on the owner at that time to assure himself in his own mind that it has been completed [in] the way he wants it.”
Tape Recording, House Committee on State and Federal Affairs, Subcommittee on Financial Affairs, May 10, 1971, Tape 16, Side 2 (testimony of Preston Hiefield); see PIH Beaverton, LLC, 355 Or at 283 (concluding from the quoted comment that the legislature intended that the contractee‘s “acceptance of completion” under the bill meant acceptance of the work as “fully complete in accordance with contractual specifications“).
The proponents took the same course in discussing the alternate event that would trigger the period of repose—the “contractee[‘s] accept[ance of] the improvement * * * as having reached the state of completion when it may be used or occupied for its intended purpose.” For example, in explaining how that method of acceptance would work, they focused on a contract to build a large construction project:
“It‘s not uncommon at all, especially in school construction, for a school district to occupy * * * part of a building before the contractor is completely finished and in such cases * * * we feel that it‘s necessary for substantial completion to be determined in limiting the cause of action. The intent of this is to say that when * * * the contractor agrees with the owner that the owner may occupy part of the building that he is constructing, that the contractor should be responsible to secure something from the owner saying that he is occupying the building and that be the beginning of the [period of repose].”
Other parts of the legislative history similarly indicate that HB 1259 applied to contracts to construct, alter, or repair improvements to real property. For example, one legislator asked whether there was some “certificate of completion” that could serve as definitive evidence of substantial completion, and an AGCA representative explained that there is “an instrument of some kind that says that the project is completed and accepted subject to a provision in the contract,” but that such an instrument is “not given in every instance.” Tape Recording, House Committee on State and Federal Affairs, Subcommittee on Financial Affairs, HB 1259, Apr 9, 1971, Tape 14, Side 2 (conversation between Representative George F. Cole and J. R. Kalinoski). In PIH Beaverton LLC, 355 Or at 278-79, this court looked to a model contract drafted by the American Institute of Architects to define when a contractee will accept construction “as having reached that stage of completion when it may be used or occupied for its intended purpose.” That is, the court took from the legislative history that, in referring to the contractee‘s acceptance of the construction as complete, the legislature was referring to acceptance by a party to a contract to construct, repair, or alter an improvement to real property. The legislative history thus confirms what the text of
Plaintiff advances primarily one contrary argument in this court. She agrees that the purpose of
We reach a different conclusion for two reasons. First, as discussed above, the text and legislative history of
Second, the legislature reasonably could have concluded that, for purposes of statutes of repose, “spec” houses present different issues from houses built pursuant to construction contracts. Among other things, “spec” houses may go unsold for years. If plaintiff were correct and if the buyers in an agreement to buy an existing home were “contractees” for the purposes of
The decision of the Court of Appeals and the judgment of the circuit court are affirmed.
