IN RE PETER J. GOGUEN, Dеbtor. DAVID M. SHARFARZ, Appellant, v. PETER J. GOGUEN, Appellee.
No. 11-9004
United States Court of Appeals For the First Circuit
August 15, 2012
ON APPEAL FROM THE BANKRUPTCY APPELLATE PANEL FOR THE FIRST CIRCUIT. Before Boudin, Circuit Judge, Souter, Associate Justice, and Thompson, Circuit Judge.
Paul R. Chomko, with whom Alford & Bertrand, LLC was on brief, for appellee.
August 15, 2012
* The Hon. David H. Souter, Associate Justice (Ret.) of the Supreme Court of the United States, sitting by designation.
LAYING THE GROUNDWORK
What happened in this bankruptcy case is probably every homeowner‘s worst nightmare. We start, naturally, with the facts, which are either undisputed or based on the bankruptcy judge‘s not-clearly-erroneous findings.
Having just moved with his 14-year-old son from Anchorage, Alaska to Acton, Massachusetts, David Sharfarz started talking to contractors in the summer of 2006 about building an addition to his new home. Sharfarz ended up hiring Peter Goguen, who drafted up a contract. Stripped to its essentials, the contract specified different construction phases, requiring Goguen to pour the foundation by October 15, 2006, for example. It required Goguen to obtain the necessary town permits too. It also required Sharfarz to make progress payments to Goguen totaling roughly $171,000. And it set a completion date of March 15, 2007.
Sharfarz made no secret of the fact that he needed Goguen to start the project right away, for these reasons: first, he wanted his son to settle into his new life as quickly as possible, and second, he wanted the foundation poured before winter because he feared that a cold-weather concrete pouring could cause the foundation to crack. Sitting in Sharfarz‘s living room, the two signed the contract and Sharfarz handed Goguen a $25,693 check as
A week or so later Goguen emailed Sharfarz that he had “filed” a building-permit application with the town and was “in wait mode.” But that was not true, and Goguen did his best to keep Sharfarz from finding that out. Over the next couple of months, for example, every time a worried Sharfarz asked him for a permit update, Goguen blamed the delay on foot-dragging town bureaucrats. And when Sharfarz offered to talk to the town manager or a member of the board of selectmen, a nervous Goguen called it “the worst thing we could do.” No need to “aggravate” the building inspector by going over the inspector‘s head, Goguen said. We just have sit tight until the town acts, he added.
That did little to calm Sharfarz, who had a gnawing belief that project delays would expose him to the risk of concrete damage due to the onset of winter. One of Sharfarz‘s November 2006 emails to Goguen made this perfectly plain: “I would . . . like a better understanding as to how we will keep the foundation warm” to help the concrete strengthen and harden after a cold-weather pouring, he wrote. “I know there are ways to do it, but I assume that they all cost money.” “This,” he wrote, “is pretty much the only aspect of a wintertime start-up that is concerning me.” Goguen replied that “weather protection [won‘t be] an issue until night time temperatures” dip below freezing.
Goguen finally applied for the building permit on November 29, 2006 - two months after he said he had - and he asked the town to “expedite[]” things so that he could “move forward on the foundation before the cold of winter sets in.” He knew that it
In any event, Sharfarz continued making progress payments, even though Goguen made little progress: Goguen would start a new phase of the project, ask for and receive money without finishing the work, and then do the same thing over and over again - all the while trying to keep Sharfarz in the dark. At one pоint Goguen asked Sharfarz for more money so that he could hire another worker to get the project back on track. Sharfarz ponied up the extra money, but Goguen never hired extra help. Goguen also recommended that Sharfarz upgrade the home‘s electrical service. Sharfarz came up with the additional cash for the upgrade, but Goguen never did the work.
Things went from bad to worse for Sharfarz. By November 2007 he had paid Goguen the full contract price, and then some.
Sharfarz sued Goguen in Massachusetts state court, relying on certain consumer-protection laws. See
As part of his findings of fact and conclusions of law (a document admitted as an exhibit at the bankruptcy trial), the state judge wrote that Goguen was “both deceptive and unfair, almost from the beginning and tо the end,” and that his “violations” had been “willful and knowing.” Turning to the concrete issue, the state judge found that
[t]he concrete foundation walls for the basement and the garage . . . were poured Christmas week, in very cold weather, and subsequently cracked. They admitted a substantial amount of water, which - because Goguen had not poured the concrete floors - drained into the gravel subfloors.
“There is a particularly aggravated character to several of Goguen‘s violations,” the state judge said, pointing to (among other things) Goguen‘s “[d]elaying the building permit application for nearly three months and lying about it, thereby delaying the
At some point Goguen filed for bankruptcy under Chapter 7 of the Bankruptcy Code. Quite predictably, Sharfarz reacted by petitioning to have his judgment against Goguen declared nondischargeable, relying on a Bankruptcy Code provision that bars discharge of “any debt . . . for money . . . to the extent obtained by . . . false pretenses, a false representation, or actual fraud . . . .”
Having heard from them and examined the exhibits, the bankruptcy judge sided with Sharfarz. His reasoning ran this way. Accurately stating the law, the bankruptcy judge stressed that a creditor must establish six things to exclude a debt from discharge under this provision:
1) the debtor made a knowingly false representation or one made in reckless disregard of the truth, 2) the debtor intended to deceive, 3) the debtor intended to induce the creditor to rely upon the false statement, 4) the creditor actually relied upon the false statement, 5) the creditor‘s reliance was justifiable, and 6) the reliance upon the false statement caused damage.
In re Spigel, 260 F.3d 27, 32 (1st Cir. 2001) (footnote omitted) (explaining that the first two components of this “test describe conduct and scienter required to show fraudulent conduct generally” while “the last four embody the requirement that the claim of the creditor arguing nondischargeability in an adversary proceeding must arise as a direct result of the debtor‘s fraud“). Moving on, the bankruptcy judge found that Sharfarz had made it crystal clear
The bankruptcy judge did not differentiate between cause in fact and legal cause, the BAP noted. Noting that a comment to the Restatement says that “[i]f the misrepresentation has not in fact been relied upon by the recipient in entering into a transaction in which he suffers pecuniary loss, the misrepresentation is not in fact a cause of the loss under the rule stated,” id. § 546 cmt. a., the BAP held that the cause-in-fact
Sharfarz now appeals to us.
HIGHLIGHTING SOME LEGAL PRINCIPLES
In cases like this one we zero in on the bankruptcy judge‘s ruling, affording clear-error review to any fact-bound
The parties’ dispute here centers on causation, and we review a bankruptcy judge‘s causation finding for clear error - unless he applied the wrong legal standard, in which case our review is de novo. See Clement v. United States, 980 F.2d 48, 53 (1st Cir. 1992); see also In re Am. Bridge Prod., Inc., 599 F.3d 1, 8 (1st Cir. 2010). Also, because one of the Bankruptcy Code‘s chief aims is to give the deserving debtor a “fresh start,” we read exceptions to dischargeability “narrowly.” See, e.g., In re Spigel, 260 F.3d at 32 (internal quotation marks omitted). That means that a person in Sharfarz‘s shoes must show that his claim fits “squarely” within a specific exception set out in the Bankruptcy Code. See, e.g., id. (internal quotation marks omitted). And as the party seeking an exception to discharge, Sharfarz had the burden of proving nondischargeability by a preponderance of the evidence. See, e.g., Grogan v. Garner, 498 U.S. 279, 281, 287-88 (1991).
WORKING THROUGH THE ISSUES
An admittedly confusing concept, see United States v. Hatfield, 591 F.3d 945, 947 (7th Cir. 2010) (Posner, J.), causation is composed of cause in fact and legal cause, as we said earlier. In the typical case, the causal relation between the defendant‘s conduct and the plaintiff‘s injury need only be probable. See, e.g., Samos Imex Corp. v. Nextel Commc‘ns, Inc., 194 F.3d 301, 303 (1st Cir. 1999) (explaining that tort causation requires that the “plaintiff . . . show that it is more probable than not that the injury was caused by the action or event (or a combination of them) for which the defendant is responsible“). Of course, a “superseding cause” (something that intervenes between the defendant‘s wrongful act and the plaintiff‘s injury, “snap[ping] the causal chain” that links the act to the injury) can “wip[e] out the defendant‘s liability” - but the burden of proving this “is on the defendant.” BCS Servs., Inc. v. Heartwood 88, LLC, 637 F.3d 750, 757 (7th Cir. 2011) (Posner, J.) (citation and internal quotation marks omitted); accord Wojciechowicz v. United States, 582 F.3d 57, 67 (1st Cir. 2009) (declaring that “[p]roximate cause is not proven if the defendant can show the occurrence of an intervening cause that was foreseeable“); Parker v. Gerrish, 547 F.3d 1, 14 (1st Cir. 2008) (noting that the defendant has the “burden of showing an independent intervening event“).
Cause in Fact
The cause-in-fact issue is fairly easy, given the bankruptcy judge‘s factual finding: had Goguen not lied to Sharfarz about the building-permit status, the judge stressed after canvаssing the evidence, Sharfarz “would have canceled the construction contract” and gotten back “all or most” of the initial $25,693 payment. Of course, we must accept this finding unless clearly erroneous - a formidable standard, requiring a “strong, unyielding belief” that the bankruptcy judge made a mistake. See Cumpiano v. Banco Santander P.R., 902 F.2d 148, 152 (1st Cir. 1990). Viewing the record as a whole, as we must, see, e.g., id., we see nothing resembling clear error here. And given this finding, we have no trouble concluding that Goguen‘s deliberately-deceitful conduct played a “substantial” role, and thus was “a substantial factor,” in shaping “the course of conduct that result[ed]” in Sharfarz‘s “loss” - meaning that we can put a check mark next to cause in fact on the causation list. See Restatement (Second) of Torts § 546 & cmt. b.
Wait a minute, says Goguen. Echoing the very the Restatement comment that the BAP had quoted - that if a party “has
Legal Cause
Having dealt with cause in fact, we now turn to legal cause, which is a trickier mattеr. As we explained earlier, legal cause is largely a question of foreseeability - a concept that “shape[s] and delimit[s] a rational remedy: otherwise the chain of causation could be endless.” Sys. Mgmt., Inc. v. Loiselle, 303 F.3d 100, 104 (1st Cir. 2002). Hindsight is always 20/20. And when events have run their course, it is easy to label “‘foreseeable‘” everything “that has in fact occurred” - but this we cannot do. See In re Kinsman Transit Co., 338 F.2d 708, 723 (2d Cir. 1964) (Friendly, J.). Instead, taking our cue from the Restatement, we must see whether Sharfarz showed that Goguen‘s lies led to a “loss” that “might reasonably” have been “expected to result from the reliance.” See Restatement (Second) of Torts § 548A. We conclude that he has.
The net result of this is that Sharfarz made a prima facie case for legal cause: again (and at the risk of trying the reader‘s patience), we stress that Sharfarz foresaw that, without adequate precautions, pouring concrete in cold weather could lead to cracking, and the record, fairly read, shows that Goguen did too; common knowledge and common sense (not contradicted by the evidence) suggest that Sharfarz‘s fear was reasonable; and his fear (according to his testimony, received without objection) ultimately became a reality. So, to put the point in Restatement terms, Sharfarz‘s reliance on Goguen‘s misrepresentations resulted in a “loss” that could “reasonably” have been “expected” to occur “from
Of course, Goguen‘s vague comment below that one could add chemicals to concrete mix to forestall cracking cannot carry the day for him. After all, he has never said that he did that here. Nor has he ever said that he took any other preventative steps. And if he wanted to argue that he had or that the obvious cause was not the actual cause, he had to contribute something more than nothing. See Wojciechowicz, 582 F.3d at 67; Parker, 547 F.3d at 14; see also generally BCS Servs., Inc., 637 F.3d at 757 (stressing that a “plaintiff doesn‘t have to prove a series of negatives,” adding that “he doesn‘t have to offer evidence which positively excludes every other possible cause“) (alterations, citations, and internal quotation marks omitted).
Which brings us full circle. Sharfarz wins because he adequately proved causation and Goguen did not bear his burden of showing an intervening or superseding cause. Consequently, we reverse the BAP‘s decision reversing the bankruptcy judge‘s order. That leaves one loose end, however - and a serious one to boot.
The Nondischargeable Amount
At least some portion of Sharfarz‘s $88,000 in actual damages is attributable to the foundation‘s cracking. But we do not know what that number is, because (the reader will remember)
For starters, Sharfarz claimed that he paid Goguen extra money for an additional worker who was never hired; that he made progress payments to Goguen for work that Goguen said he had done but that was in fact not done; and that he paid Goguen for an electrical upgrade that was never performed. The bankruptcy judge made no findings regarding these allegations. But Sharfarz has not waived them (indeed, he explicitly raises them here), and the bankruptсy judge could well decide on remand that some part of Sharfarz‘s damages is traceable not to the foundation‘s cracking but to other reasonably-foreseeable consequences of Goguen‘s lies.
Also, and importantly, the bankruptcy judge may have erred when he discharged the amount of Goguen‘s debt attributable to the state judge‘s trebling of damages and awarding of attorney fees and costs. See Cohen, 523 U.S. at 215, 223. True, Sharfarz has not appealed on this point. But given that Goguen will be free on remand to show that the nondischargeable amount is really less than $88,000, we see no reason why Shаrfarz should not be allowed to show that the nondischargeable number is really more.
FINISHING UP
Our work complete, we vacate the BAP‘s judgment and remand to that tribunal with directions that it, in turn, remand the case to the bankruptcy court for further proceedings consistent with this opinion.
Vacated and remanded with instructions. No costs.
THOMPSON
CIRCUIT JUDGE
