Seven County Infrastructure Coalition v. Eagle CountySeven County Infrastructure Coalition v. Eagle County
Syllabus
Under federal law, new railroad construction and operation must first be approved by the U. S. Surface Transportation Board.
Held: The D. C. Circuit failed to afford the Board the substantial judicial deference required in NEPA cases and incorrectly interpreted NEPA to require the Board to consider the environmental effects of upstream and downstream projects that are separate in time оr place from the Uinta Basin Railway. Pp. 6–22.
(a) NEPA ensures that agencies and the public are aware of the environmental consequences of certain proposed infrastructure projects. As a purely procedural statute, NEPA “does not mandate particular results, but simply prescribes the necessary process” for an agency’s environmental review of a project. Robertson v. Methow Valley Citizens Council, 490 U. S. 332, 350. Some federal courts reviewing NEPA cases have assumed an aggressive role in policing agency compliance with NEPA, and have not applied NEPA with the judicial deference demanded by the statutory text and the Court’s cases.
When, as here, a party argues that an agency action was arbitrary and capricious due to a deficiency in an EIS, the “only role for a court” is to confirm that the agency has addressed environmental consequences and feasible alternatives as to the relevant project. Strycker’s Bay Neighborhood Council, Inc. v. Karlen, 444 U. S. 223, 227. Further, the adequacy of an EIS is relevant only to the question of whether an agency’s final decision (here, to approve the railroad project) was reasonably explained.
Judicial deference in NEPA cases extends to an agency’s determination of what details are relevant in an EIS. While NEPA requires an EIS to be “detailed,”
(b) Contrary to the D. C. Circuit’s NEPA analysis, the Board’s determination that its EIS need not evaluate possible environmental effects from upstream and downstream projects separate from the Uinta Basin Railway complied with NEPA’s procedural requirements, particularly NEPA’s textually mandated focus on the “proposed action” under agency review. While indirect environmental effects of the project itself may fall within NEPA’s scope even if they might extend outside the geographical territory of the project or materialize later in time, the fact that the project might foreseeably lead to the construction or increased use of a separate project does not mean the agency must consider that separate project’s environmental effects. See Public Citizen, 541 U. S., at 767. This is particularly true where, as here, those separate projects fall outside the agency’s regulatory authority. Pp. 15–21.
(c) NEPA does not allow courts, “under the guise of judicial review” of agency compliance with NEPA, to delay or block agency projects based on the environmental effects of other projects separate from the project at hand. Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U. S. 519, 558. Pp. 21–22.
82 F. 4th 1152, reversed and remanded.
KAVANAUGH, J., delivered the opinion of the Court, in which ROBERTS, C. J., and THOMAS, ALITO, and BARRETT, JJ., joined. SOTOMAYOR, J., filed an opinion concurring in the judgment, in which KAGAN and JACKSON, JJ., joined. GORSUCH, J., took no part in the consideration or decision of the case.
Opinion of the Court
JUSTICE KAVANAUGH delivered the opinion of the Court.
Some 55 years ago, Congress passed and President Nixon signed the National Environmental Policy Act, known as NEPA. For certain infrastructure projects that are built, funded, or approved by the Federal Government, NEPA requires federal agencies to prepare an environmental impact statement, or EIS. The EIS must address the significant environmental effects of a proposed project and identify feasible alternatives that could mitigate those effects.
NEPA was the first of several landmark environmental laws enacted by Congress in the 1970s. Subsequent statutes included the Clean Air Amendments of 1970, the Clean Water Act of 1972, and the Endangered Species Act of 1973, among others.
Unlike those later-enacted laws, however, NEPA imposes no substantive environmental obligations or restrictions. NEPA is a purely procedural statute that, as relevant here, simply requires an agency to prepare an EIS—in essence, a report. Importantly, NEPA does not require the agency to weigh environmental consequences in any particular way.
In this case, the U. S. Surface Transportation Board considered a proposal by a group of seven Utah counties for the construction and operation of an approximately 88-mile railroad line in northeastern Utah. Under federal law, the Board determines whether to approve construction of new railroad lines. The railroad line here would connect Utah’s oil-rich Uinta Basin—a rural territory roughly the size of the State of Maryland—to the national rail network. By doing so, the new railroad line would facilitate the transportation of crude oil from Utah to refineries in Louisiana, Texas, and elsewhere. And the project would bring significant economic development and jobs to the isolated Uinta Basin by better connecting the Basin to the national economy.
For that proposed 88-mile Utah railroad line, the Board prepared an extraordinarily lengthy EIS, spanning more than 3,600 pages of environmental analysis. The Board’s EIS addressed the environmental effects of the railroad line. But the U. S. Court of Appeals for the D. C. Circuit nonetheless faulted the EIS for not sufficiently considering the environmentаl effects of projects separate from the railroad line itself—primarily, the environmental effects that could ensue from (i) increased oil drilling upstream in the Uinta Basin and (ii) increased oil refining downstream along the Gulf Coast of Louisiana and Texas.
On that basis, the D. C. Circuit vacated the Board’s EIS and the Board’s approval of the 88-mile railroad line. As a result, construction still has not begun even though the Board approved the project back in December 2021.
We reverse. First, the D. C. Circuit did not afford the
I
Under federal law, new railroad construction and operation must first be approved by the U. S. Surface Transportation Board.
In 2020, the Seven County Infrastructure Coalition—a group of seven Utah counties—applied to the Board for approval of an 88-mile railroad line in northeastern Utah. The new railroad line would connect the Uinta Basin with the interstate freight rail network—and via that network, to refineries in Louisiana, Texas, and other destinations.
The Uinta Basin contains significant quantities of crude oil and other fossil fuels. The Uinta Basin Railway would provide oil producers a more efficient option for transporting oil out of the Basin to refineries. As of now, oil from the Basin is carried by trucks that must navigate mountain passes on narrow roads, a difficult and slow journey in any season.
The Board’s environmental review of the Uinta Basin
All told, the Board’s final EIS clocked in at more than 3,600 pages. The EIS identified and analyzed numerous “significant and adverse impacts that could occur as a result” of the railroad line’s construction and operation—including disruptions to local wetlands, land use, and recreation. App. 121; see id., at 94–105, 121–126, 206–347. The EIS likewise addressed several “minor impacts,” such as air pollution and big-game movement around the construction site. Id., at 126; see id., at 126–134, 251–259, 309–325.
The EIS also noted, but did not fully analyze, the potential effects of increased upstream oil drilling in the Uinta Basin and increased downstream refining of crude oil carried by the railroad. Id., at 135, 348–482, 511–516, 520–534, 539–543.
As to the environmental effects of upstream oil drilling, the EIS explained why further analysis of those “potential future, as yet unplanned, oil and gas development projects” was not needed. Id., at 520. To begin with, the project at issue was an 88-mile railroad line, not an oil well or a drilling permit in the Uinta Basin. Moreover, the Board possesses “no authority or control over potential future oil and gas development” in the Basin. Id., at 522. Future projects would be “subject to the approval processes of other federal, state, local, and tribal agencies.” Ibid. In any event, the environmental effects of future oil and gas development in the Basin are “speculative” and attenuated from the project at hand. Id., at 525; see id., at 525–527 (citing Department of Transportation v. Public Citizen, 541 U. S. 752, 767–768, 770 (2004)).
In December 2021, a few months after issuing the final EIS, the Board approved the construction and operation of the Uinta Basin Railway. Recognizing that “rail construction projects are in the public interest,” the Board concluded that the new railroad line would “have substantial transportation and economic benefits,” and that those benefits outweighed the environmental impacts identified in the EIS. App. to Pet. for Cert. 121a, 119a; see id., at 118a–121a.
In the wake of the Board’s final approval, a Colorado county and several environmental organizations sued by filing petitions for review in the U. S. Court of Appeals for the D. C. Circuit.
The D. C. Circuit found “numerous NEPA violations arising from the EIS.” Eagle Cty. v. Surface Transp. Bd., 82 F. 4th 1152, 1196 (2023). In the court’s view, the Board “failed” to take “the requisite ‘hard look’ at all of the environmental impacts of the Railway.” Id., at 1175.
Specifically, the Court of Appeals held that the Board impermissibly limited its analysis of upstream and downstream projects. The court concluded that the
Based on the deficiencies it found in the EIS, the Court of Appeals vacated the EIS and the Board’s final approval order. 82 F. 4th, at 1196. The Coalition and the Uinta Basin Railway sought review in this Court, and we granted certiorari. 602 U. S. ___ (2024).
II
For certain infrastructure projects that are built, funded, or approved by the Federal Government, NEPA requires federal agencies to prepare an environmental impact statement, or EIS, identifying significant environmental effects of the projects, as well as feasible alternatives. The law ensures that the agency and the public are aware of the environmental consequences of proposed projects. Properly applied, NEPA helps agencies to make better decisions and to ensure good project management.
Importantly, however, NEPA is purely procedural. In ultimately deciding whether to build, fund, or approve a project, an “agency is not constrained by NEPA from deciding that other values outweigh the environmental costs.” Robertson v. Methow Valley Citizens Council, 490 U. S. 332, 350 (1989). Otherwise stated, NEPA “does not mandate particular results, but simply prescribes the necessary process” for an agency’s environmental review of a project. Ibid.; see Department of Transportation v. Public Citizen, 541 U. S. 752, 756–757 (2004); Marsh v. Oregon Natural Resources Council, 490 U. S. 360, 370–372 (1989); Baltimore Gas & Elec. Co. v. Natural Resources Defense Council, Inc., 462 U. S. 87, 97–98 (1983); Strycker’s Bay Neighborhood Council, Inc. v. Karlen, 444 U. S. 223, 227–228 (1980); Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U. S. 519, 558 (1978); Kleppe v. Sierra Club, 427 U. S. 390, 410, n. 21 (1976).1
Here, the Board’s EIS evaluated the environmental effects of the proposed 88-mile railroad line in Utah’s rural Uinta Basin. But the D. C. Circuit, following Circuit precedent applying NEPA, concluded that the EIS did not sufficiently address the reasonably foreseeable environmental impacts of increased upstream oil drilling in the Uinta Basin, as well as the environmental effects of
As we will explain, we disagree with the D. C. Circuit’s decision on two grounds. First, the court did not afford the Board the substantial judicial deference required in NEPA cases. Second, the court incorrectly interpreted NEPA to require the Board to consider the environmental effects of upstream and downstream projects that are separate in time or place from the Uinta Basin Railway.
A
Since the early 1970s, federal courts have reviewed NEPA cases. Over time, some courts have assumed an aggressive role in policing agency compliance with NEPA. Other courts have adopted a more restrained approach. In light of the continuing confusion and disagreement in the Courts of Appeals over how to handle NEPA cases, we think it important to reiterate and clarify the fundamental principles of judicial review applicable in those cases. As we will explain, the central principle of judicial review in NEPA cases is deference.2
As a general matter, when an agency interprets a statute, judicial review of the agency’s interpretation is de novo. See Loper Bright Enterprises v. Raimondo, 603 U. S. 369, 391–392 (2024). But when an agency exercises discretion
When a party argues that an agency action was arbitrary and capricious due to a deficiency in an EIS, the reviewing court must account for the fact that NEPA is a purely procedural statute. Under NEPA, an agency’s only obligation is to prepare an adequate report. “NEPA requires no more.” Strycker’s Bay Neighborhood Council, 444 U. S., at 228. Unlike a plethora of other federal environmental statutes (such as the Clean Air Act, the Clean Water Act, etc.), NEPA imposes no substantive constraints on the agency’s ultimate decision to build, fund, or approve a proposed project. So when reviewing an agency’s EIS, “the only role for a court” is to confirm that the agency has addressed environmental consequences and feasible alternatives as to the relevant project. Id., at 227; see Vermont Yankee, 435 U. S., at 551, 555. Because an EIS is only one input into an agency’s decision and does not itself require any particular substantive outcome, the adequacy of an EIS is relevant only to the question of whether an agency’s final decision (here, to approve the railroad) was reasonably explained.
In short, when determining whether an agency’s EIS complied with NEPA, a court should afford substantial deference to the agency.
In practice, judicial deference in NEPA cases can take several forms. For example, NEPA says that the EIS should be “detailed.”
The EIS also must identify significant environmental impacts and feasible alternatives. But there too, an agency exercises substantial discretion. An agency must make predictive and scientific judgments in assessing the relevant impacts (what are the likely impacts; do they rise to the level of “significant”?) and alternatives (what are the
In preparing an EIS, an agency also must determine the scope of the environmental effects that it will address. The textual focus of NEPA is the “proposed action”—that is, the project at hand.
In analyzing those scope questions, it is critical to disaggregate the agency’s role from the court’s role. So long as the EIS addresses environmental effects from the project at issue, courts should defer to agencies’ decisions about where to draw the line—including (i) how far to go in considering indirect еnvironmental effects from the project at hand and (ii) whether to analyze environmental effects from other projects separate in time or place from the project at hand. On those kinds of questions, as this Court has often said, agencies possess discretion and must have broad latitude to draw a “manageable line.” Public Citizen, 541 U. S., at 767 (quoting Metropolitan Edison Co. v. People Against Nuclear Energy, 460 U. S. 766, 774, n. 7 (1983)).
To tie all of this together: When assessing significant environmental effects and feasible alternatives for purposes of NEPA, an agency will invariably make a series of fact-dependent, context-specific, and policy-laden choices about the depth and breadth of its inquiry—and also about the length, content, and level of detail of the resulting EIS. Courts should afford substantial deference and should not micromanage those agency choices so long as they fall within a broad zone of reasonableness. As the Court has emphasized on several occasions, and we doubly underscore again today, “inherent in NEPA . . . is a ‘rule of reason,’ which ensures that agencies determine whether and to what extent to prepare an EIS based on the usefulness of any new potential information to the decisionmaking process.” Public Citizen, 541 U. S., at 767. A reviewing court may not “substitute its judgment for that of the agency as to the environmental consequences of its actions.” Kleppe, 427 U. S., at 410, n. 21.
Some courts have strayed and nоt applied NEPA with the level of deference demanded by the statutory text and this Court’s cases. Those decisions have instead engaged in overly intrusive (and unpredictable) review in NEPA cases. Those rulings have slowed down or blocked many projects and, in turn, caused litigation-averse agencies to take ever more time and to prepare ever longer EISs for future projects.
The upshot: NEPA has transformed from a modest procedural requirement into a blunt and haphazard tool employed by project opponents (who may not always be entirely motivated by concern for the environment) to try to stop or at least slow down new infrastructure and construction projects. Some project opponents have invoked NEPA and sought to enlist the courts in blocking or delaying even those projects that otherwise comply with
All of that has led to more agency analysis of separate projects, more consideration of attenuated effects, more explоration of alternatives to proposed agency action, more speculation and consultation and estimation and litigation. Delay upon delay, so much so that the process sometimes seems to “borde[r] on the Kafkaesque.” Vermont Yankee, 435 U. S., at 557. Fewer projects make it to the finish line. Indeed, fewer projects make it to the starting line. Those that survive often end up costing much more than is anticipated or necessary, both for the agency preparing the EIS and for the builder of the project. And that in turn means fewer and more expensive railroads, airports, wind turbines, transmission lines, dams, housing developments, highways, bridges, subways, stadiums, arenas, data centers, and the like. And that also means fewer jobs, as new projects become difficult to finance and build in a timely fashion.
A 1970 legislative acorn has grown over the years into a judicial oak that has hindered infrastructure development “under the guise” of just a little more process. Id., at 558. A course correction of sorts is appropriate to bring judicial review under NEPA back in line with the statutory text and common sense. Id., at 525. Congress did not design NEPA for judges to hamstring new infrastructure and construction projects. On the contrary, as this Court has stressed, courts should and “must defer to ‘the informed discretion of the responsible federal agencies.’” Marsh, 490 U. S., at 377.
Critically, as the Government and the Coalition explainеd at oral argument, courts not only must defer to
In other words, as this Court has said before, NEPA does not authorize a court to “‘interject itself within the area of discretion . . . as to the choice of the action to be taken’” by the agency. Strycker’s Bay Neighborhood Council, 444 U. S., at 227–228 (quoting Kleppe, 427 U. S., at 410, n. 21). NEPA’s procedural mandate helps “to insure a fully informed and well-considered decision, not necessarily a decision the judges of the Court of Appeals or this Court
The “role of a court in reviewing the sufficiency of an agency’s consideration of environmental factors is a limited one.” Id., at 555. The bedrock principle of judicial review in NEPA cases can be stated in a word: Deference.
B
Even apart from failing to afford sufficient deference to the Surface Transportation Board, the D. C. Circuit’s decision was mistaken on the merits under NEPA. The D. C. Circuit erroneously required the Board to address environmental effects from projects that are separate in time or place from the 88-mile railroad project at hand—that is, effects from potential future projects or from geographically separate projects. Moreover, those separate projects fall outside the Board’s authority and would be initiated, if at all, by third parties.
In its EIS, the Board determined that upstream oil drilling in the Uinta Basin and downstream oil refining along the Gulf Coast were separate from the construction and operation of the 88-mile railroad line. The Board’s EIS explained that the “proposed rail line and any future oil and gas development projects are not two phases of a single action,” but “separate, independent projects.” App. 523. Those other projects, the Board reasoned, should not be considered “part of the proposed action assessed in the EIS.” Ibid. The Board concluded that its EIS need not evaluate the possible environmental effects from separate upstream or downstream projects.5
The Board’s approach complied with NEPA and this Court’s longstanding NEPA precedents. Importantly, the textually mandated focus of NEPA is the “proposed action”—that is, the project at hand—not other future or geographically separate projects that may be built (or expanded) as a result of or in the wake of the immediate project under consideration.
To be clear, the environmental effects of the project at issue may fall within NEPA even if those effects might extend outside the geographical territory of the project or might materialize later in time—for example, run-off into a river that flows many miles from the project and affects fish populations elsewhere, or emissions that travel downwind and predictably pollute other areas. Those so-called indirect effects can sometimes fall within NEPA, as the Government explained at oral argument. See Tr. of Oral Arg. 59–63.
But if the project at issue might lead to the construction or increased use of a separate project—for example, a housing development that might someday be built near a highway—the agency need not consider the environmental effects of that separate project. To put it in legal terms, the
Moreover, and importantly, the Board here possesses no regulatory authority over those separate projects. The Board does not regulate oil drilling, oil wells, oil and gas leases, or oil refineries. The Board approves railroad lines. See
To be sure, NEPA mandates that an agency “consult
In this case, the Uinta Basin Railway was the relevant project. NEPA therefore required the Board to consider the environmental effects of that 88-mile railroad line‘s construction and operation. To the extent that the new 88-mile railroad line could disrupt the habitat of protected species, or the new rail embankments could cause soil erosion into local bodies of water, or trains on the new line could pollute the air, NEPA dictated that the Board evaluate those effects. And consistent with NEPA, the Board here did comprehensively evaluate those effects, including via consultation with other agencies. As the D. C. Circuit itself recognized, the Board explained that “сonstruction and operation of the Railway” would affect “water resources, air quality, [and] special status species like the greater sage-grouse.” 82 F. 4th, at 1168. But nothing in NEPA required the Board to go further and study environmental impacts from upstream or downstream projects separate in time or place from the 88-mile railroad line‘s construction and operation.
Under NEPA, it also bears emphasis, a mere “‘but for’ causal relationship is insufficient to make an agency
Simply stated, a court may not invoke but-for causation or mere foreseeability to order agency analysis of the effects of every project that might somehow or someday follow from the current project. See Public Citizen, 541 U. S., at 767–768; Metropolitan Edison, 460 U. S., at 774–775. NEPA calls for the agency to focus on the environmental effects of the project itself, not on the potential environmental effects of future or geographically separate projects. A relatively modest infrastructure project should not be turned into a scapegoat for everything that ensues from upstream oil drilling to downstream refinery emissions. As Justice Rehnquist underscored in Vermont Yankee, NEPA is not a “game” where project objectors can engage in “unjustified obstructionism“—here, for example, by raising a slew of remote effects that they think “‘ought to be’ considered.” 435 U. S., at 553–554.
To be sure, in certain circumstances, other projects may be interrelated and close in time and place to the project at
In this case, in any event, the NEPA question is not close. The Board did not need to evaluate potential environmental impacts of the separate upstream and downstream projects. As to other projects upstream, the EIS rightly explained that the environmental consequences of future oil drilling in the Basin are distinct from construction and operation of the railroad line. App. 525–527. As for other projects downstream, the Board likewise correctly explained that any environmental effects from highly regulated oil refineries along the Gulf Coast are well outside the scope of the 88-mile railroad project in rural Utah. Id., at 420–423, 539–542.6
An agency may decline to evaluate environmental effects from separate projects upstream or downstream from the project at issue. Public Citizen, 541 U. S., at 770. Here, the Board‘s EIS concluded that the “proposed rail line and any future oil and gas development projects are not two phases of a single action,” but “separate, independent projects.” App. 523. So the Board concluded that they need not be considered “part of the proposed action assessed in the EIS.” Ibid. Absolutely correct.
* * *
In deciding cases involving the American economy, courts should strive, where possible, for clarity and predictability. Some courts’ NEPA decisions have fallen short of that objective. The proper judicial approach for NEPA cases is straightforward: Courts should review an agency‘s EIS to check that it addresses the environmental effects of the project at hand. The EIS need not address the effects of separate projects. In conducting that review, courts should afford substantial deference to the agency as to the scope and contents of the EIS.
Plaintiffs’ policy objections to this 88-mile Utah railroad may or may not be persuasive. But neither “the language nor the history of NEPA suggests that it was intended to give citizens a general opportunity to air their policy objections to proposed federal actions. The political process, and not NEPA, provides the appropriate forum in which to air policy disagreements.” Metropolitan Edison, 460 U. S.,
We reverse the judgment of the Court of Appeals and remand the case for further proceedings consistent with this opinion.
It is so ordered.
The National Environmental Policy Act improves agency decisionmaking by requiring agencies to consider environmental impacts for which their decisions would be responsible. I agree with the Court that the Surface Transportation Board would not be responsible for the harms caused by the oil industry, even though the railway it approved would deliver oil to refineries and spur drilling in the Uinta Basin. I reach that conclusion because, under its organic statute, the Board had no authority to reject petitioners’ application on account of the harms third parties would cause with products transported on the proposed railway. The majority takes a different path, unnecessarily grounding its analysis largely in matters of policy. Accordingly, I write separately to explain why the result in this case follows inexorably from our precedent.
I
A
The Uinta Basin spans thousands of square miles across northwestern Utah and Colorado. Bookended by the Uinta Mountains in the north and the Roan Cliffs in the south,
Petitioners, the Seven County Infrastructure Coalition and the Uinta Basin Railway, LLC, plan to build a railway connecting the Uinta Basin with the Union Pacific Railroad Company station in Kyune, Utah, and from there to the national rail network. As the Coalition recognizes, “the Railway‘s predominant and expected primary purpose would be” to enable Basin oil producers to transport, with greater ease and in greater quantities, waxy crude to refineries in the Gulf Coast. Ibid. Nearly all the waxy crude transported by train out of the Uinta Basin would continue its travels over the Union Pacific track from Kyune to Denver, which runs through Eagle County, Colorado, and closely abuts the Colorado River.
B
No person may “construct an additional railroad line” or “provide transportation over . . . an еxtended or additional railroad line” without a certificate of approval from the Surface Transportation Board.
In May 2020, petitioners requested permission to build
After soliciting public comment, the Board completed its environmental impact statement on August 6, 2021.1 App. to Pet. for Cert. 76a. The statеment recognized that “between 3.68 and 10.52 trains” would travel daily on the proposed new railway, which would be used “primarily to transport crude oil from the Basin to markets across the United States.” Final EIS 1–4. Consistent with its obligations under NEPA, the Board discussed the comparative environmental merits of alternative railway routes as well as the environmental consequences common to all alternatives. Among other things, the Board analyzed the Railway‘s likely impact on the Basin‘s natural environment and the impacts increased freight traffic from the Railway would have on the existing Union Pacific line running through Eagle County.
Of particular relevance here, the Board recognized that “[r]efiners would refine the crude oil transported by the proposed rail line into various fuels,” which in turn would be1
After completing this analysis, the Board issued a decision approving the railway. With respect to the anticipated increase in oil production, the Board again concluded that it had “no authority or jurisdiction over development of oil and gas in the Basin nor any authority to control or mitigate the impacts of any such development.” App. to Pet. for Cert. 108a. Board member Oberman dissented. In his view, the Board did have “the power to deny construction approval based on weighing all of the environmental impacts that will arise from oil and gas development in the Basin,” particularly because the Railway‘s “‘entire purpose‘” would be to stimulate such production. Id., at 124a.
C
Several environmental groups filed a petition for review of the Board‘s decision to approve the railway, arguing principally that the Board should have further considered the consequences of increased oil drilling and refining that the Railway‘s construction would enable. Eagle County separately petitioned for review of the Board‘s decision, alleging that the Board‘s environmental analysis was deficient because it ignored or underestimated the Railway‘s impacts, through increased rail traffic, on the County and the nearby Colorado River. Petitioners intervened in support of the Board‘s decision.
The D. C. Circuit rejected several claims no longer at issue here, but it sided with the challengers on others. With regard to the environmental respondents’ challenge, the court held that the Board should have more carefully considered the deleterious environmental effects of increased oil production made possible by the Railway‘s construction. 82 F. 4th, at 1180. Among other things, the court explained, the Board should have “estimate[d] the emissions or other environmental impacts” of oil refining as localized for the “specific regions that will receive the oil based on expected train traffic.” Id., at 1179. The court rejected the Board‘s argument “that it lacks authority to prevent, control, or mitigate those developments.” Id., at 1180. Instead, in the D. C. Circuit‘s view, the Board‘s statutory obligation to consider whether the Railway would serve the “‘public convenience and necessity‘” encomрassed “reasonably foreseeable environmental harms,” including those resulting from the increase in oil production on the Gulf Coast. Ibid.
Moving to the County‘s claims, the D. C. Circuit agreed the Board‘s analysis of the Railway‘s effect on the Union Pacific track and the Colorado River contained serious, unexplained errors and omissions. The court further concluded that the Board had failed to comply with several
Petitioners asked this Court to review only one part of the D. C. Circuit‘s decision: whether NEPA required the Board to study the environmental impacts of oil wells and refineries that lie outside the Board‘s regulatory authority. Pet. for Cert. i. This Court granted review to decide that question.
II
A
NEPA requires agencies to prepare and publish a “detailed statement” reviewing the environmental impact of any major federal action.
Because NEPA‘s central aim is to improve agency decisionmaking, an agency need not consider every conceivable environmental consequence of a proposed federal action. Rather, agencies need only analyze environmental impacts
Precedent makes these abstract principles concrete. In Public Citizen, this Court evaluated the Federal Motor Carrier Safety Administration‘s environmental analysis of regulations establishing an application process for Mexican motor carriers who wanted to operate in the United States. 541 U. S., at 758–763. The application system itself had only minimal environmental impacts (related to anticipated roadside inspections of the Mexican trucks and buses). Yet the agency developed it at the direction of the President, who had decided to lift a long-running moratorium on Mexican carriers’ operation in the United States following the system‘s completion. Id., at 760. Thus, promulgation of the agency‘s regulations would enable a substantial influx of new trucking, which in turn would have major environmental implications.
This Court concluded that, though the agency‘s regulations would be a “but-for” cause of the new trucking, it did not need to consider the related environmental impacts because it had “no authority to prevent” them. Id., at 766–767. After all, the decision to lift the moratorium had been the President‘s, not the agency‘s, and the agency could not lawfully refuse to issue its regulations in order to block the President‘s decision. Id., at 761. The agency had no means to prevent, and thus was not responsible for, the consequences of lifting the moratorium. Hence NEPA did not require it to analyze those consequences.
The Court‘s decision in Metropolitan Edison illustrates the companion principle: Some environmental impacts are connected to an agency action by way of so “attenuated” a causal chain that the agency may reasonably dismiss them as ancillary to its decision. 460 U. S., at 774. In Metropolitan Edison, the Court considered whether the Nuclear Regulatory Commission had to analyze not only the risk that a proposed nuclear plant would cause an accident, but also the psychological concern nearby residents might experience when they learned about that risk. Ibid. Although the psychological concern would be “caused by” the nuclear plant, the Court held that NEPA did not require the agency to consider it. Id., at 774–775. That makes sense: Preventing nuclear accidents is a core element of the Commission‘s statutory task; preventing psychological distress is not. See id., at 776 (noting that “psychiatric expertise” is “not otherwise relevant to [the agency‘s] congressionally assigned functions“). Because the agency could reasonably disregard psychological distress in deciding whether to approve a power plant, it could disregard that risk in its environmental analysis as well.
As these cases show, the dual limitations on an agency‘s duty to сonsider information under NEPA yield a “‘rule of reason,’ which ensures that agencies determine whether and to what extent to prepare an EIS based on the usefulness of any new potential information to the decisionmaking process.” Public Citizen, 541 U. S., at 767 (quoting Marsh v. Oregon Natural Resources Council, 490 U. S. 360, 373–374 (1989)). NEPA requires consideration of environmental impacts only if such consideration would result in information on which the agency could act.
B
Consistent with these principles, judicial review of an agency‘s environmental impact statement involves a two-step analysis. First, courts must consider the grounds on which an agency may rely under its organic statute to modify (by mitigation) or reject a proposed federal action. If the organic statute precludes consideration of a particular issue, the agency may set it aside for purposes of its NEPA review as well. That is the rule of Public Citizen.3
Second, if an agency decided not to review an environmental impact because (in its judgment) the impact was too causally attenuated from the question at hand, courts must ask whether the agency “acted arbitrarily” in doing so. Kleppe, 427 U. S., at 412. That deferential standard of review is appropriate here, as it is across substantive areas of administrative law, because “[a]gencies . . . have ‘unique expertise,’ often of a scientific or technical nature, relevant to applying a regulation ‘to complex or changing circumstances.‘” Kisor v. Wilkie, 588 U. S. 558, 571 (2019) (plurality opinion). Thus, as the majority points out, agencies often are “better equipped to assess what facts are relevant to the[ir] . . . own decision than a court is.” Ante, at 10; cf. Loper Bright Enterprises v. Raimondo, 603 U. S. 369, 456 (2024) (KAGAN, J., dissenting) (“[A]gencies often know things about a statute‘s subject matter that courts could not hope to“).4
Review of the Board‘s organic statute, the Interstate Commerce Commission Termination Act, confirms the Board‘s understanding of the scope of its review. “As common carriers, railroads subject to the Board‘s jurisdiction are required to provide ‘transportation or service on reasonable request’ to any person or commodity.” Ante, at 20, n. 6 (quoting
common carrier mandate prevented the Board from mitigating, by limiting the transport of crude oil, the Railway‘s spurring of the oil industry. See
The environmental respondents concede that the Board correctly understood the scope of its decisionmaking authority. See Tr. of Oral Arg. 84–85. Instead, they argue that the Board should have analyzed even environmental impacts it could not lawfully prevent. Yet Public Citizen squarely forecloses that position. See supra, at 9–10. Even a foreseeable environmental effect is outside of NEPA‘s scope if the agency could not lawfully decide to modify or reject the proposed action on account of it. NEPA thus did not require the Board to consider the effects of oil drilling and refining.
* * *
Under NEPA, agencies must consider the environmental impacts for which their decisions would be responsible. Here, the Board correctly determined it would not be responsible for the consequences of oil production upstream or downstream from the Railway because it could not lawfully consider those consequences as part of the approval process. For that reason, I concur in the Court‘s judgment reversing the D. C. Circuit‘s holding requiring the Board to consider in further detail harms caused by the oil industry.
Notes
The final statement consisted of a 600-page report accompanied by supporting appendixes and responses to the public comments. See www.uintabasinrailwayeis.com (Board-created website containing the complete EIS and all related documentation); cf. ante, at 2, 4, 15, n. 5, 22 (asserting that the EIS spanned more than 3,600 pages of analysis).“include in every recommendation or report on proposals for legislation and other major Federal actions significantly affecting the quality of the human environment, a detailed statement by the responsible official on—
“(i) the environmental impact of the proposed action,
“(ii) any adverse environmental effects which cannot be avoided should the proposal be implemented,
“(iii) alternatives to the proposed action,
“(iv) the relationship between local short-term uses of man’s environment and the maintenance and enhancement of long-term productivity, and
“(v) any irreversible and irretrievable commitments of resources which would be involved in the proposed action should it be implemented.
“Prior to making any detailed statement, the responsible Federal official shall consult with and obtain the comments of any Federal agency which has jurisdiction by law or special expertise with respect to any environmental impact involved.” §102(2)(C), 83 Stat. 853, as amended,
42 U. S. C. §4332(2)(C) (2018) .