SECURIFORCE INTERNATIONAL AMERICA, LLC, Plaintiff, v. UNITED STATES, Defendant.
No. 12-759C
United States Court of Federal Claims.
July 12, 2016
HORN, J.
Russell J. Upton, Trial Attorney, Commercial Litigation Branch, Civil Division, Department of Justice, Washington D.C., for defendant. With him were Robert E. Kirschman, Jr., Director, Commercial Litigation Branch, and Benjamin C. Mizer, Principal Deputy Assistant Attorney General, Civil Division, Department of Justice, Washington, D.C. Of counsel were Jeffrey M. Lowry, Trial Attorney, Commercial Litigation Branch, Civil Division, Department of Justice, Washington D.C., Kay Bushman, Senior Counsel, DLA Counsel-Energy, and Jill Rodriguez, Assistant Counsel, DLA Counsel-Energy, Ft. Belvoir, Va.
OPINION
HORN, J.
FINDINGS OF FACT
Plaintiff, Securiforce International America, LLC (Securiforce), filed two separate motions under Rule 37 of the Rules of the United States Court of Federal Claims (
A brief summary of the background of this case, including plaintiff‘s claims against defendant, provides necessary context for considering plaintiff‘s two motions. Plaintiff filed an initial complaint in this court, followed by an amended complaint, which alleged that the Department of Defense Logistics Agency Energy (DLA Energy) had awarded plaintiff a requirements contract for fuel delivery to specific sites in Iraq, that DLA Energy had committed multiple breaches of the contract, and that DLA Energy had improperly issued a partial termination for convenience of the contract, followed by an improper termination for cause. The Department of State fuel delivery sites in Iraq that were specified in the contract awarded to Securiforce were Basrah, Umm Qasar, Embassy Baghdad, Besamaya, Sather, Shield, Taji, and Prosperity. In its complaint, plaintiff did not seek money damages, but, instead, sought a declaratory judgment that DLA Energy‘s partial termination for convenience and subsequent termination for cause of Securiforce‘s contract was improper because “DLA Energy committed multiple, material breaches of its commercial-item, three-year, requirements contract with Securiforce for fuel deliveries to eight locations in Iraq.” In addition to other alleged contractual breach claims that are not relevant to the disposition of plaintiff‘s two
I. Securiforce‘s May 31, 2013 Motion to Compel Discovery and for Payment of Expenses
Plaintiff moved to compel the production of certain contract documents pursuant to
During discovery in the above-captioned case, plaintiff served document requests upon defendant that were apparently designed to support its breach of contract claims, including that defendant allegedly had repudiated
11. All documents, including but not limited to contract modifications, notices, and correspondence, related to security for other contractors awarded contracts under the Solicitation.
12. All documents related to notices issued to other contractors awarded contracts under the Solicitation requesting contractors to conduct a Proof of Principle.
In response to plaintiff‘s document requests 11 and 12, defendant objected, as follows:
The Government objected to these requests, principally on the grounds that they are overly broad and unduly burdensome, and because they call for the production of documents that are neither relevant nor reasonably calculated to lead to the discovery of admissible information.
Subsequently, defendant sent a letter to plaintiff on May 15, 2013, further clarifying its objections to plaintiff‘s document production requests 11 and 12. In the letter, defendant maintained its objection and explained that, “[t]o the extent Securiforce seeks documents relating to different contractors performing under different contracts for deliveries to different sites maintained by a different Government agency, the Department of Defense, we stand by our objections.” According to defendant, however, in order “[t]o ensure Securiforce receive[d] all documents to which it is reasonably entitled” and “to avoid burdening the Court with an unnecessary discovery dispute,” defendant offered to produce “responsive documents relating to other contractors performing under the contract originally awarded Securiforce ... which provided for deliveries of fuel to various Department of State sites in Iraq.” Approximately two weeks later, on May 31, 2013, plaintiff filed its motion to compel discovery and for reimbursement of expenses incurred in filing its motion to compel in the amount of $219,194.00.
After a status conference was held with the parties on June 25, 2013 to discuss plaintiff‘s motion to compel, the court ordered plaintiff to file a motion in limine addressing “whether the contract at issue in the above-captioned case required defendant to provide security for plaintiff‘s fuel deliveries, as well as whether the contract permitted defendant to request that plaintiff make ‘proof of principle’ deliveries,” with an opportunity for defendant to submit a reply brief. Thereafter, plaintiff filed a motion in limine and for partial summary judgment and the parties conducted briefing on the motion. After another status conference with the parties on December 4, 2013, the court issued an Order stating that “Plaintiff‘s May 31, 2013 Motion to Compel Discovery and for Payment of Expenses, July 23, 2013 Motion in Limine and for Partial Summary Judgment, and November 8, 2013 Motion to Amend the Court‘s October 30, 2013, Order are DENIED at this time.” (capitalization and emphasis in original). The court indicated to the parties during multiple status conferences that the legal and factual issues briefed in the various motions, including plaintiff‘s motion to compel and for payment of expenses, would be deferred until after the trial testimony had been taken and the court had the opportunity to hear the witnesses’ testimony and review the record, which the court considered necessary to resolve plaintiff‘s motions.
In its post-trial briefing, plaintiff asked the court to revisit plaintiff‘s May 31, 2013 motion to compel discovery and for payment of expenses. According to plaintiff, evidence presented at trial reinforces the relevance of the documents sought by Securiforce in its document production requests 11 and 12 and warrants the court‘s further consideration of plaintiff‘s motion for costs. Plaintiff points out, with regard to document production request 11, concerning security, that, during the trial, plaintiff was permitted to admit into evidence, as plaintiff‘s exhibit 1025 in the trial record, an e-mail discussing a contract for fuel delivery that was issued under the same solicitation as Securiforce‘s contract, but held by a different contractor, “Ram,”
II. Securiforce‘s October 31, 2014 Motion for Sanctions
Plaintiff filed a motion for sanctions under
During discovery in the above-captioned case, plaintiff propounded interrogatories, document requests, and requests for admissions to defendant to support its claim that, during the pendency of the contract, the government had improperly received fuel from sources other than Securiforce in violation of plaintiff‘s requirements contract. The contract documents sought in plaintiff‘s discovery requests related to fuel deliveries to United States Department of State locations in Iraq from September 2011 to March 2013 during a time of conflict. The relevant documents appear to have been located at DLA Energy sites both in the United States and in Iraq at on-site offices. In March 2013, plaintiff served document production requests upon defendant, including a request for:
All documents related to actual orders and/or delivery of diesel fuel and motor gasoline at the eight sites awarded under the Contract from the date of Contract award until the present, including, but not limited to, deliveries made to the eight
sites awarded under the Contract by trucking fuel from Department of Defense Stocks in Kuwait.
In response to this document request, in July 2013, defendant produced two spreadsheets which purported to show all diesel fuel and motor gasoline deliveries to the eight Department of State sites covered by plaintiff‘s contract between September 7, 2011, the date of contract award, and March 12, 2013, the date of plaintiff‘s discovery request, with no deliveries occurring prior to October 25, 2011, the day after Securiforce first failed to deliver fuel in accordance with the terms of the contract. Securiforce‘s first delivery deadline under the contract was October 24, 2011, and plaintiff failed to deliver fuel in accordance with that deadline. In an e-mail sent on November 5, 2013, plaintiff‘s counsel inquired as to whether the spreadsheets were accurate and captured all of the fuel delivery orders, electronic and hard copy, that had been placed between September and October 2011. Defendant responded by letter on November 6, 2013, and explained that “as reflected in the data produced, the Government placed no orders, electronic or otherwise, in the month of September 2011. The very first orders it placed under the contract were with Securiforce, as required, and issued verbally on October 14, 2011,” and these were “the only deliveries requested through the October 24, 2011 delivery deadline.” During discovery defendant explained:
[T]he Department of State urgently required fuel that Securiforce admittedly could not deliver. So, as authorized by the contract, the Government “covered” Securiforce‘s breach, procuring a limited quantity of fuel from elsewhere. To the best of our current knowledge, covering orders were accomplished electronically. Based on your request, however, we have asked agency personnel to search for any hardcopy orders associated with these deliveries, which are accurately reflected on the delivery spreadsheet about which you inquired. In terms of source data, it is our understanding that DLA‘s fuel database is designed to function exclusively or almost exclusively by electronic means, with data input, collected, and recorded to accurately detail the agency‘s global logistics efforts.
In addition to the document production requests, plaintiff propounded multiple requests for admissions. Plaintiff propounded its first request for admissions to defendant on April 16, 2013, in which “Securiforce sought admissions that the government had received deliveries of diesel fuel and motor gasoline” at Department of State locations, including Basrah, Umm Qasar, Besamaya, Sather AB, Shield, and Taji between the date of contract award, September 7, 2011, and the November 15, 2011 termination for cause. In its response on June 7, 2013, defendant stated that fuel had been delivered to some of these sites (Basrah, Besamaya, Shield, Taji), but only after plaintiff was unable to timely deliver the fuel ordered under the contract and had defaulted on the contract, thus, not in violation of Securiforce‘s requirements contract.
On November 20, 2013, plaintiff sent defendant a second request for admissions, this time specifically asking about an e-mail, dated October 4, 2011, sent by Colonel William Rush, which stated, in part:
we‘ve tagged our KO [contracting officer] for the Jassim contract to make mods to allow us to make deliveries to [Securiforce‘s] sites with their assets to get DoS [Department of State] and OSC-I their initial operational stocks IAW [in accordance with] MG Richardson‘s guidance.
...
Through Jassim I think I can support Taji, Prosperity, Embassy, Besmaya [sic] Shield and Umm Qasar with the orders slated for later this week.
Plaintiff alleges this e-mail indicated that, as of October 2011, DLA Energy had submitted fuel orders to sources other than plaintiff for deliveries to the sites covered by Securiforce‘s contract. In its December 23, 2013 response to plaintiff‘s request for admissions regarding the October 4, 2011 Colonel Rush e-mail, defendant denied plaintiff‘s request for admissions and stated that the e-mail did not state or indicate that as of October 4, 2011 DLA Energy had decided to use another contractor to deliver fuel to Securiforce‘s sites. Defendant asserted that the e-mail “reflects Col. Rush‘s concern that Securiforce,
As I‘m sure we‘ll discuss later, they weren‘t able to meet that time line, so I still had customers that needed fuel. And as I recall, we had to come up with other ways to get them fuel while waiting for SecuriForce to be able to bring fuel into Iraq from Kuwait. And that proof of principle I believe was bringing DOD-procured fuel that was already in Iraq, positioned in an intermediate terminal, forward to another site by KBR [Kellogg Brown & Root], an Army contractor.
In May 2014, plaintiff propounded an additional interrogatory, identified as interrogatory 16, regarding the spreadsheets that defendant had produced in July 2013, “seeking information about who had prepared the spreadsheets, the sources of the data contained therein, and whether the government contended that the spreadsheets captured all fuel deliveries to Securiforce‘s sites” from September 7, 2011 through November 15, 2011. Interrogatory 16 asked:
For the spreadsheets produced by the government at DLA4929 and DLA4930, identify (a) the individual(s) that prepared those spreadsheets; (b) the source(s) of data and other sources of information relied upon by the individual(s) that prepared those spreadsheets; and (c) whether the government contends that these spreadsheets capture all fuel deliveries (including delivery of government-owned fuel) to Securiforce‘s sites from September 7, 2011, through the date of Securiforce‘s First Set of Document Production Requests (March 12, 2013).
Defendant responded:
Defendant objects to interrogatory 16 to the extent it violates
Rule 33(a) because it includes multiple discreet [sic] subparts. Subject to, and without waiving its objections, the defendant responds as follows: For the spreadsheets produced by the government at DLA4929 and DLA4930, the individuals who prepared those spreadsheets were, in alphabetical order: (a) Kellie Allison; (b) Thomas Cooch; (c) Kathleen Drohan; (d) Steven Hurwitz; and (e) Al Morgan. The referenced spreadsheets compiled data from the DLA Energy‘s Fuels Enterprise Server, DLA Energy‘s Defense Fuel Automated Management System, and DLA Energy‘s Automated Voucher Examination and Disbursing System. The referenced spreadsheets capture all fuel deliveries (including delivery of government-owned fuel) to Securiforce‘s sites from September 7, 2011, through the date of Securiforce‘s First Set of Document Production Requests (March 12, 2013).
Still questioning the completeness and accuracy of defendant‘s continued representations and discovery responses regarding fuel deliveries to Securiforce‘s sites, in July 2014, plaintiff notified defendant of its intent to conduct a deposition pursuant to
The information contained in the government‘s response to interrogatory No. 16.
Deliveries of diesel fuel and motor gasoline, including government-owned fuel, to the sites under Securiforce‘s Contract from the date of Contract award until the date of Securiforce‘s First Set of Document Requests.
The basis for government‘s representations that no diesel fuel or motor gasoline was delivered to Securiforce‘s sites prior to October 24, 2011. (See Responses to Request for Admissions Nos. 71, 72, 81, 82, 90, 91, 98, 99, 106, 107, 115, 116, 213, 215, 216, 217, 218, 219, 220)
The sources (i.e., country of origin) of diesel fuel and motor gasoline being delivered to Securiforce‘s sites.
Defendant designated a DLA Energy inventory program manager, Jack Whitaker, as the
Mr. Whitaker was asked whether he reviewed the contract between DLA Energy and Securiforce prior to his deposition, to which he replied “I‘ve seen it. No, I didn‘t, like, dig into it and review it like I would a—you know, when a contract‘s awarded, does it meet mission requirements, et cetera. I didn‘t look at it. Just kind of breezed through it.” Mr. Whitaker also indicated that he had seen plaintiff‘s list of topics for the deposition only the day before, and that, in order to familiarize himself with the topics, he looked at each one of the admissions and the spreadsheets produced by defendant in discovery. Plaintiff‘s counsel asked Mr. Whitaker “is it your understanding between September 7 and October 24, no fuel was delivered to any of the eight sites awarded to SecuriForce under their contract?” Mr. Whitaker replied: “Yeah, I‘m not sure. I didn‘t look these up. I mean—.” When asked whether it was his understanding that the Securiforce sites went without fuel between September 7, 2011 and October 24, 2011, Mr. Whitaker stated:
I don‘t—I don‘t know that they didn‘t have any deliveries. I mean, if they were operating—and as I said before, I‘m not sure if there were people—if those sites were occupied during that time. But I imagine if people were there, they had to have generators running, they needed fuel. You know, there was a bunch of big bases that we closed during that period. There could have been leftover fuel that was used that the Army moved to those destinations that was excess that—when they were leaving. I‘m just speculating. I don‘t know.
Following Mr. Whitaker‘s deposition on September 5, 2014, the government conduct-
it became clear that, although DLA Energy was the primary supplier of fuel for the military and the Department of State in Iraq, the Army or its contractor, Kellogg Brown & Root (KBR), would redistribute fuel it purchased from DLA Energy to its forward operating bases, including to the military located at Securiforce sites.
Defendant stated that it “immediately informed counsel for Securiforce of this new information” during a telephone call on September 18, 2014. Approximately one month later, on October 14, 2014, defendant served its amended discovery responses on plaintiff in which it admitted that some DLA Energy-owned fuel was delivered to at least four sites designated in Securiforce‘s requirements contract, including Taji, Shield, Embassy Baghdad, and Basrah, between September 7, 2011 and October 24, 2011. With regard to Umm Qasar, Besamaya, and Sather AB, defendant indicated that there were fuel deliveries,
to the extent that DLA Energy-owned fuel from Kuwait was delivered to various DLA Energy-owned stock points in Iraq. Some of that fuel was subsequently transferred to the Army. The Army then redistributed that fuel under a LOGCAP contract with KBR to military customers at various sites in Iraq, including the sites under the Securiforce contract. Furthermore, during the transition, DLA Energy turned over various fuel stocks that it held in Iraq to the Army in Iraq. The Army in turn had a policy to provide USF-I owned fuel to the Department of State for USM-I at enduring locations.
Although defendant conceded that some fuel was received at four of Securiforce‘s designated sites, and that it is possible fuel was transferred from the Army to the Department of State at Securiforce‘s other sites, the government indicated it “was unable to locate any records documenting fuel transfer from the Army to the Department of State.”
Based on the deposition testimony that Mr. Whitaker offered at the
Even after the trial and plaintiff‘s decision not to depose additional witnesses, plaintiff continues to press this court to impose sanctions on defendant for allegedly providing inaccurate discovery responses for more than a year while “repeatedly and unequivocally represent[ing] that its discovery responses were accurate.” According to Securiforce, it was forced to continue investigating the responses in order to prove their inaccuracy and to conduct an unnecessary deposition of an unprepared
DISCUSSION
Plaintiff filed its motions for costs and sanctions pursuant to
I. Plaintiff‘s May 31, 2013 Motion to Compel and for Payment of Expenses
Plaintiff filed its May 31, 2013 motion to compel and for payment of expenses seeking $219,914.00 pursuant to
11. All documents, including but not limited to contract modifications, notices, and correspondence, related to security for other contractors awarded contracts under the Solicitation.
12. All documents related to notices issued to other contractors awarded contracts under the Solicitation requesting contractors to conduct a Proof of Principle.
Defendant “objected to these requests, principally on the grounds that they are overly broad and unduly burdensome, and because they call for the production of documents that are neither relevant nor reasonably calculated to lead to the discovery of admissible information.” In an effort “to avoid burdening the Court with an unnecessary discovery dispute,” however, defendant offered to “produce responsive documents relating to other contractors performing under the contract originally awarded Securiforce through Amendment 5 to the Solicitation.” Unsatisfied with defendant‘s response, plaintiff moved to compel the production of additional documents that it believed defendant should have produced in response to plaintiff‘s document requests. In a December 4, 2013 Order, the court held that “Plaintiff‘s May 31, 2013 Motion to Compel Discovery and for Payment of Expenses, July 23, 2012 Motion in Limine and for Partial Summary Judgment, and November 8, 2013 Motion to Amend the Court‘s October 30, 2013, Order are DENIED at this time.” (capitalization and emphasis in original). The court ordered that the parties work together to “pursue the discovery plan discussed at that conference in order to attempt to resolve any discovery disputes.” The court indicated that it was deferring plaintiff‘s motions until it could hear the witnesses at trial, given the difficulty at the time to determine relevancy and the need to more fully understand the facts surrounding the termination for convenience and the termination for cause which formed the basis of plaintiff‘s complaint.
In its post-trial brief, plaintiff argues that “evidence presented at trial reinforces the relevance of the documents sought by Securiforce and warrants the Court‘s reconsideration of Securiforce‘s motion for costs.” According to plaintiff, although its motion compelling certain document discovery was provisionally denied before trial, the record developed at trial demonstrates that the motion should have been granted initially. Plaintiff, however, did not argue that any additional evidence should have been introduced into the trial record or that any such evidence would have changed the result of the trial.
Although plaintiff‘s complaint was framed as a request for declaratory relief and to void the terminations for the government‘s convenience and for cause, plaintiff sought a finding from this court that the terminations were breaches of plaintiff‘s contract with DLA Energy. In reviewing a breach of contract claim, the court shall look to the language of the written agreement between the parties. See Bell/Heery v. United States, 739 F.3d 1324, 1331 (Fed. Cir. 2014); Sterling, Winchester & Long, L.L.C. v. United States, 83 Fed. Cl. 179, 183 (2008), aff‘d, 326 Fed. Appx. 568 (Fed. Cir. 2009). Where there is ambiguity in the language of a contract evidence of conduct under other, similar contracts may be admissible to prove breach. See Miller Elevator Co., Inc. v. United States, 30 Fed. Cl. 662, 689 (1994) (ex- plaining that the previous conduct between parties to an agreement can establish “a common basis of understanding for inter-
Plaintiff has argued that its document discovery requests 11 and 12 were part of its effort to prove that DLA Energy had breached its contract with Securiforce by repudiating its obligation to provide security escorts and improperly ordering proof of principle shipments. With regard to document request 11, which requested contract documents related to government-provided security for other contractors, plaintiff points to three different examples in the trial record to prove that the documents requested were relevant and, thus, the motion to compel should have been granted. First, plaintiff argues that “[t]estimony from various witnesses and trial exhibits established that other contractors, including Ram and Jassim, refused to make fuel deliveries without government-provided security.” As discussed further below, however, neither the conduct of other contractors, nor the terms of other contracts between different contractors and defendant are relevant when considering this plaintiff‘s breach of contract claim. The trial record, including the testimony of several witnesses, emphasized that the particular contract between Securiforce and defendant governed plaintiff‘s relationship with the government and that the contract did not, initially, provide for security. The trial record also did not establish the relevancy of other contractors’ agreements with the government in relation to the contract specifications contained in Securiforce‘s contract. As such, even discussion at trial of other contractors’ conduct cannot establish that plaintiff‘s document production request sought relevant information.
Second, plaintiff points to Contracting Officer Shepherd‘s trial testimony regarding discussions about security that were conducted with other offerors prior to contract award. Contracting Officer Shepherd explained at trial, however, that these discussions only concerned the contracts for Department of Defense sites, and did not address contracts issued to provide fuel to Department of State sites, such as plaintiff‘s contract. Therefore, plaintiff has failed to prove the relevance of discussions between the government and other contractors with regard to plaintiff‘s specific contract with the government. The fact that different contractors in the same war zone were operating under different contractual agreements with defendant does not change, or effect in any way, the terms of plaintiff‘s contract with the United States.
Third, plaintiff relies on the fact that, at trial, the court admitted into evidence, over defendant‘s relevancy objection, an e-mail discussing a contract between DLA Energy and another contractor, Ram, which had been awarded under the same solicitation as plaintiff‘s contract. Plaintiff moved to admit the e-mail into evidence during its trial examination of Kathryn Fantasia, in order, according to plaintiff, to demonstrate “what a requirements contract required and what would be a breach.” In this regard, the court allowed plaintiff latitude to offer the evidence for general definition purposes. Although the court allowed this e-mail to be entered into evidence as an exhibit, plaintiff asked only a few questions about the e-mail discussing the Ram contract and did not draw a comparison between the Ram contract and plaintiff‘s contract regarding government-provided security. Moreover, in a bench trial, the court is in the position to sift through the evidence presented and to consider only the information relevant to the disposition of a case when arriving at and issuing a decision. In the March 21, 2016 opinion, the court did not utilize or refer to the e-mail discussing the Ram contract. As plaintiff itself explained at trial, the e-mail was admitted as a general
Although plaintiff tries to rely upon these three occurrences to advance its argument that the mere mention at trial of another contract or contractor connected to the same solicitation as plaintiff‘s contract necessarily should lead to the conclusion that all of the contract documents related to security for other contractors awarded contracts under the same solicitation as Securiforce‘s contract are relevant to the above-captioned case, the court issued its opinion without coming to a similar conclusion. The contract documents requested by plaintiff were not relevant to plaintiff‘s claim that DLA Energy breached the contract with Securiforce by allegedly repudiating its obligation to provide security escorts, and the instances at trial that plaintiff points to in support of its position do not prove the relevancy of those contract documents.
Similarly, with regard to document request 12, which asked for contract documents related to proof of principle orders placed with other contractors, plaintiff argues that defendant‘s “conduct with respect to requiring POP [proof of principle] deliveries from other awardees under the same Solicitation is relevant to this matter.” Plaintiff points to Colonel Musgrove‘s trial testimony acknowledging that DLA Energy did not place any proof of principle orders with any of the other contractors that were awarded a contract under the same solicitation as Securiforce. Colonel Musgrove‘s trial testimony regarding proof of principle orders placed with other contractors was during Securiforce‘s own examination of Colonel Musgrove and came in response to the question: “Can you with certainty identify a single order... to a vendor, other than Securiforce, that was a proof of principle order?” Simply because plaintiff‘s counsel asked whether other contractors received proof of principle orders, however, does not establish that all “documents related to notices issued to other contractors awarded contracts under the Solicitation requesting contractors to conduct a Proof of Principle” are relevant to the above-captioned case. Also, Colonel Musgrove‘s testimony does not establish that defendant‘s actions in relation to other contractors operating under different contracts is relevant to plaintiff‘s contract with the government.
Plaintiff Securiforce moved to compel defendant to produce contract documents pertaining to contracts to which it was not a party. Plaintiff‘s requests were overly broad and not likely to produce evidence relevant to interpreting plaintiff‘s contract with the government. Plaintiff was not a party, nor has it alleged it was a party, to any of the contract documents requested in document requests 11 or 12. Plaintiff‘s document requests and submissions to the court indicate that plaintiff wished to receive contract documents held by other contractors in order to draw a comparison between contract performance under Securiforce‘s contract and performance under contracts held by other contractors issued under the same solicitation as Securiforce‘s contract, at least in part, to support plaintiff‘s breach of contract allegations. Such comparisons, however, would not have been helpful to plaintiff‘s case because the terms of the contracts held by other contractors and the performance obligations thereunder could not be imposed onto plaintiff‘s contract with DLA Energy. The terms and conditions between DLA Energy and other contractors would not have served to aid in resolving the issues of whether defendant was obligated to provide security escorts or permitted to place proof or principle orders with plaintiff under the terms of the contract between Securiforce and DLA Energy. In the above-captioned case, in order to succeed on its breach of contract claims regarding security escorts and proof of principle orders, plaintiff would have had to demonstrate that DLA Energy breached a duty on these issues arising out of the terms of the particular contract between Securiforce and DLA Energy, which was the only contract relevant to plaintiff‘s claims. See Carlos Irr. & Drainage Dist. v. United States, 877 F.2d 957, 959 (Fed. Cir. 1989).
As previously stated,
Based on the above discussion, plaintiff‘s May 13, 2013 motion to compel is DENIED. Discovery in this case was protracted, contentious, and difficult. The circumstances of discovery in this case, and the actions of all parties, including DLA Energy, lead the court to conclude that both sides should bear the costs of their own discovery. As is further discussed below, the difficulties during discovery in this case do not warrant reward to either party.
II. Plaintiff‘s October 31, 2014 Motion for Sanctions
In its motion on October 31, 2014, plaintiff moved for sanctions against defendant based on defendant‘s allegedly inadequate discovery responses and for producing an allegedly unprepared
In response to plaintiff‘s motion for sanctions, defendant argues that “Securiforce is not entitled to its fees under Rule 37(c)(2) when the Government‘s responses to Securiforce‘s requests for admission were based on a reasonable understanding of the only evidence the Government believed available.” According to defendant, “sanctions are unwarranted when the Government had a reasonable belief that its answers represented the best available evidence and amended its answers once it learned from newly discovered information that its admissions did not tell the complete story.” Additionally, defendant asserts that “[b]ecause the Government produced a qualified and knowledgeable Rule 30(b)(6) witness who answered some, but admittedly not all, of Securiforce‘s questions, and because Securiforce has declined the Government‘s repeated offer of additional
a. Defendant‘s Responses to Plaintiff‘s Discovery Requests from June 2013 to October 2014
As explained above, during discovery in the above-captioned case, plaintiff propounded interrogatories, document requests, and requests for admissions to defendant from March 2013 to May 2014 designed to support its claim that, during the life of the contract, the government had improperly received fuel from sources other than Securiforce in violation of plaintiff‘s requirements contract. In defendant‘s discovery responses beginning in June 2013, defendant stated that fuel had been delivered to some of Securiforce‘s designated sites (Basrah, Besamaya, Shield, Taji), but only after plaintiff defaulted on the contract and, thus, the deliveries were not in violation of Securiforce‘s requirements contract. In July 2013, in response to plaintiff‘s document requests on March 12, 2013, defendant produced spreadsheets that purportedly captured all diesel fuel and motor gasoline deliveries to the eight sites under the contract between September 7, 2011 (the date of contract award) and March 12, 2013 (the date of plaintiff‘s first discovery request). The spreadsheets indicated that there were no deliveries of fuel to Securiforce‘s eight sites before October 24, 2011, the date on which Securiforce failed to deliver fuel ordered by DLA Energy in accordance with the terms of the requirements contract. Approximately one year after producing the spreadsheets, defendant confirmed that the spreadsheets “capture[d] all fuel deliveries (including delivery of government-owned fuel) to Securiforce‘s sites from September 7, 2011, through the date of Securiforce‘s First Set of Docu-
In October 2014, defendant produced revised discovery responses which stated that fuel apparently had been received at four of the sites designated in Securiforce‘s requirements contract, including Taji, Shield, Embassy Baghdad, and Basrah prior to October 24, 2011. Defendant also admitted that fuel may have been delivered to Umm Qasar, Besamaya, and Sather AB,
to the extent that DLA Energy-owned fuel from Kuwait was delivered to various DLA Energy-owned stock points in Iraq. Some of that fuel was subsequently transferred to the Army. The Army then redistributed that fuel under a LOGCAP contract with KBR to military customers at various sites in Iraq, including the sites under the Securiforce contract.... Furthermore, during the transition, DLA Energy turned over various fuel stocks that it held in Iraq to the Army in Iraq. The Army in turn had a policy to provide USF-I owned fuel to the Department of State for USM-I at enduring locations.
Plaintiff now moves to sanction defendant for its inaccurate discovery responses and recover its costs under
1. RCFC 37(c)(1)
Plaintiff argues, therefore, that its deposition of Mr. Whitaker proved that defendant‘s prior discovery responses were inaccurate and seeks to recover the costs incurred in conducting the deposition. Plaintiff argues that, pursuant to
As I‘m sure we‘ll discuss later, they [Securiforce] weren‘t able to meet that time line, so I still had customers that needed fuel. And as I recall, we had to come up with other ways to get them fuel while waiting for SecuriForce to be able to bring fuel into Iraq from Kuwait. And that proof of principle I believe was bringing DOD-procured fuel that was already in Iraq, positioned in an intermediate terminal, forward to another site by KBR, an Army contractor.
...
KBR is Kellogg Brown & Root. It just means using—the Army used Kellogg Brown & Root to deliver fuel. We would deliver fuel, DOD procured fuel, we own it, buy it in Kuwait, move it through Jassim by our transportation contractor.
When asked whether it was his understanding that the Securiforce sites went without fuel between September 7, 2011 and October 24, 2011, Mr. Whitaker stated at his deposition, nine months later:
I don‘t—I don‘t know that they didn‘t have any deliveries. I mean, if they were operating—and as I said before, I‘m not sure if there were people—if those sites were occupied during that time. But I imagine if people were there, they had to have generators running, they needed fuel. You know, there was a bunch of big bases that we closed during that period. There could have been leftover fuel that was used that the Army moved to those destinations that was excess that—when they were leaving. I‘m just speculating. I don‘t know.
Plaintiff argues that Mr. Whitaker‘s deposition testimony corroborated other evidence that the government‘s discovery responses were inaccurate. In its submissions to the court, defendant does not specifically address the nine month period between Colonel Rush‘s deposition in January 2014 and Mr. Whitaker‘s deposition in September 2014, and argues that “it was Mr. Whitaker‘s testimony that made clear the potential existence of [the] informal support system [between the Army and the Department of State] and that DLA‘s records would not reflect any such fuel transfers.” The information that defendant originally produced during discovery appears to have been based on DLA‘s records, as DLA was the party with which plaintiff entered into the contract and with which plaintiff interacted during contract performance. Defendant argues that “the Government‘s denial that fuel was delivered to Securiforce‘s contract sites prior to October 25, 2011 was based on the only information available to it in response to a reasonable inquiry into DLA Energy‘s fuel delivery records.” Defendant argues also that plaintiff “should have recognized that the Department of States’ [sic] presence at the various sites Securiforce was contracted to supply was negligible at first and would materialize only
Notwithstanding plaintiff‘s argument that it is entitled to recover costs pursuant to
While defendant was able to learn this information from its investigation, it was “unable to locate any records documenting fuel transfer from the Army to the Department of State.” Thus, given the information gained from Mr. Whitaker‘s deposition testimony and defendant‘s follow on investigation, it does not appear that defendant was disingenuous when it previously responded to and denied plaintiff‘s requests for admission based on its earlier reasonable search of DLA Energy‘s records in response to plaintiff‘s discovery requests.
Although plaintiff argues that defendant should have been on notice of the fuel deliveries to Securiforce‘s sites prior to October 24, 2011 based on the deposition testimony of Colonel Rush in 2014, in his testimony, Colonel Rush described the government‘s efforts as occurring only after Securiforce indicated that it could not comply with the delivery timeline of October 24, 2011, which was plaintiff‘s first delivery deadline. It is not clear that Colonel Rush was discussing the possibility of fuel transfers prior to October 24, 2011, and his testimony was not definitive. In the excerpt of Colonel Rush‘s deposition that plaintiff submitted in support of its motion for sanctions, Colonel Rush discussed how the government devised other ways to get fuel to Securiforce‘s sites after Securiforce indicated it would not be able to meet its October 24, 2011 delivery deadline. Colonel Rush specifically indicated that he was describing the government‘s delivery of fuel “while waiting for SecuriForce to be able to bring fuel into Iraq from Kuwait” because Securiforce had indicated that it could not deliver fuel before October 24, 2011: “[T]hey weren‘t able to meet that time line, so I still had customers that needed fuel.” In contrast, Mr. Whitaker‘s deposition testimony specifically discussed fuel delivery to Securiforce‘s sites in September 2011, prior to October 24, 2011. Mr. Whitaker was directly asked whether it was his “understanding that these sites went without any fuel from September 7 through October 24?” Mr. Whitaker answered that it was possible the sites were receiving government-owned fuel in September 2011. As discussed previously, based on Mr. Whitaker‘s response, defendant conducted a follow on investigation concerning fuel deliveries before October 24, 2011. Plaintiff‘s argument that Colonel Rush‘s deposition testimony, which discussed fuel delivery after October 24, 2011, should have triggered further investigation into deliveries to Securiforce‘s designated sites before October 24, 2011, as Mr. Whitaker‘s deposition prompted, is not sufficient to cause this court to impose sanctions on defendant. Discovery in this case was protracted and adversarial, and the contract records were created during an international conflict, dispersed, and stored in multiple locations, and, apparently, not easily retrievable if available at all. The record demonstrates that defendant made a good faith effort to comply with plaintiff‘s discovery requests and further investigated Mr. Whitaker‘s statements promptly following his deposition in September 2014. Defendant also promptly produced supplemental discovery responses approximately five weeks later. Moreover, although defendant produced its supplemental discovery responses in October 2014, plaintiff received the corrected responses at least four months before trial, with time for plaintiff to conduct any follow
Based on the record in the above-captioned case, defendant initially supplied information based on a reasonable review of what was identified by the agency as the available records. Defendant also met its obligation under
2. RCFC 37(c)(2)
The court must impose sanctions against a party that fails to admit what is requested in a discovery request for admissions if the party that initially propounded the request for admissions later proves the matter to be true and no exceptions under
In considering the imposition of sanctions pursuant to
In the above-captioned case, plaintiff argues that, under
Mr. Whitaker‘s deposition raised the possibility that the Army was a source of fuel for the Department of State. Following the deposition, the Government conducted a follow-on investigation and amended its admissions to reflect that, although there was no supporting documentation, it was likely the Army supplied the Department of State without the involvement of DLA Energy.
(citations omitted). Defendant argues further that “the Government‘s denial that fuel was delivered to Securiforce‘s contract sites prior to October 25, 2011 was based on the only information available to it in response to a reasonable inquiry into DLA Energy‘s fuel delivery records.” Defendant explains that “DLA Energy maintained the Government‘s stock of fuel for Iraq and was solely responsible for the contracts for direct delivery of fuel to Department of State locations in Iraq,” thus, “there were reasonable grounds to believe that its denial would prove true at trial,” as it was based on the records maintained by DLA Energy.
As discussed above, defendant supplemented its discovery responses in October 2014 in order to provide more accurate and more complete discovery responses after it conducted a follow on investigation to the September 2014
to the extent that DLA Energy-owned fuel from Kuwait was delivered to various DLA Energy-owned stock points in Iraq. Some of that fuel was subsequently transferred to the Army. The Army then redistributed that fuel under a LOGCAP contract with KBR to military customers at various sites in Iraq, including the sites under the Securiforce contract.... Furthermore, during the transition, DLA Energy turned over various fuel stocks that it held in Iraq to the Army in Iraq. The Army in turn had a policy to provide USF-I owned fuel to the Department of State for USM-I at enduring locations.
Plaintiff points to defendant‘s October 2014 admissions and Mr. Whitaker‘s deposition testimony to assert that it, Securiforce, was the party that proved fuel deliveries were made to Securiforce‘s sites between the contract award date, September 7, 2011, and October 24, 2011, notwithstanding defendant‘s denials throughout discovery. According to Securiforce, because plaintiff proved that such deliveries took place, it is thereby entitled to recover the cost of proving the truth of such deliveries pursuant to
Notwithstanding plaintiff‘s argument, it is clear from the record in this case that the
Additionally, to the extent that plaintiff‘s discovery requests asked for information about the delivery of government-owned fuel to Securiforce‘s sites in Iraq, those requests, likely, would be irrelevant to plaintiff‘s claim that the government breached its contract. The requirements contract between plaintiff and DLA Energy included the
Notwithstanding plaintiff‘s allegations, it was not plaintiff that proved fuel was delivered to the sites identified in Securiforce‘s requirements contract. Instead, it was the result of defendant‘s follow on investigation after Mr. Whitaker‘s tentative testimony at his deposition, which suggested to defendant that it should further review the issue due to the responses provided to plaintiff. Mr. Whitaker stated:
I don‘t—I don‘t know that they didn‘t have any deliveries. I mean, if they were operating—and as I said before, I‘m not sure if there were people—if those sites were occupied during that time. But I imagine if people were there, they had to have generators running, they needed fuel. You know, there was a bunch of big bases that we closed during that period. There could have been leftover fuel that was used that the Army moved to those destinations that was excess that—when they were leaving. I‘m just speculating. I don‘t know.
(emphasis added). Accordingly, because defendant‘s Department of Justice counsel promptly initiated a follow on inquiry after Mr. Whitaker‘s deposition, and then promptly supplemented its discovery responses, defendant met its discovery obligations. Based on the record before the court, defendant‘s conduct during discovery does not warrant sanctions and plaintiff is not entitled to recover its expenses.
b. RCFC 30(b)(6) Deposition of Jack Whitaker
Plaintiff also moves for sanctions against defendant pursuant to
the Government identified Jack Whitaker, DLA Energy inventory program manager, as the witness most likely to have knowledge about the fuel inventory process and any possible transfer of fuel to Department of State sites during the transition to a commercial supply based fuel system from a system based on delivery of Government-owned fuel.
Defendant argues that “Mr. Whitaker‘s extensive involvement in DLA Energy‘s fuel inventory management for the Middle East made him the best witness available to the Government at the time to explain how Department of State sites in Iraq received fuel when Securiforce failed to provide any.” While defendant acknowledges that Mr. Whitaker could not answer every question posed by Securiforce, defendant argues that “Securiforce is not entitled to a single, all-knowing Rule 30(b)(6) witness.”
In the above-captioned case, plaintiff identified the following broad topics for the
The information contained in the government‘s response to interrogatory No. 16.
Deliveries of diesel fuel and motor gasoline, including government-owned fuel, to the sites under Securiforce‘s Contract from the date of Contract award until the date
of Securiforce‘s First Set of Document Requests. The basis for government‘s representations that no diesel fuel or motor gasoline was delivered to Securiforce‘s sites prior to October 24, 2011. (See Responses to Request for Admissions Nos. 71, 72, 81, 82, 90, 91, 98, 99, 106, 107, 115, 116, 213, 215, 216, 217, 218, 219, 220)
The sources (i.e., country of origin) of diesel fuel and motor gasoline being delivered to Securiforce‘s sites.
Plaintiff alleges that Mr. Whitaker was not prepared for his
Plaintiff points to different statements made by Mr. Whitaker during his
The transcript of Mr. Whitaker‘s deposition demonstrates that he offered a thorough knowledge of the spreadsheets prepared by DLA and previously turned over to plaintiff. The spreadsheets purportedly captured the fuel deliveries to the Securiforce Department of State sites in Iraq during the relevant time period according to defendant‘s information when the spreadsheets were prepared. Mr. Whitaker stated that he was familiar with the various databases listed on the spreadsheets, including “DLA Energy‘s fuels enterprise server, DLA Energy‘s defense fuel, automated management system, and DLA Energy‘s automated voucher examination and dispersing system” and was able to explain the systems to plaintiff‘s counsel when asked. The dialogue contained in the deposition transcript indicates that Mr. Whitaker could speak intelligently about the information contained in the spreadsheets. Mr. Whitaker answered many questions posed by plaintiff‘s counsel about specific, detailed information contained in the spreadsheets based on his ability to decipher the spreadsheets. Specifically, Mr. Whitaker could read the codes used in the spreadsheets to identify countries of origin, invoice numbers, billing codes, delivery sites, delivery dates, funding codes, stock numbers, fuel quantities, and fuel grades. Mr. Whitaker‘s knowledgeable deposition testimony about the spreadsheets and fuel deliveries in Iraq indicates that he was prepared to discuss a broad range of the topics plaintiff included in the
Plaintiff, however, argues that Mr. Whitaker had no personal knowledge of actual deliveries to the Securiforce sites or of how the spreadsheets were prepared, and had done nothing to verify the accuracy of the information contained in the spreadsheets. Mr. Whitaker testified that, prior to his deposition, he had not spoken with any of the individuals who prepared the spreadsheets containing the fuel delivery information, nor had he spoken with anyone at the sites in Securiforce‘s contract as to whether fuel was received between September 7, 2011, the contract award date, and November 15, 2011, the contract termination date. Although Mr.
I reviewed them, I looked at them and I know how the process works. I know what the origin is—if you put parameters in and say give me a list of deliveries from these origins, that this document captures the origins that the fuel came from. So on that basis, I think they‘re accurate.
In their briefs regarding plaintiff‘s motion for sanctions, the parties submitted different portions of Mr. Whitaker‘s deposition transcript to support their opposing positions. A review of these combined submissions of Mr. Whitaker‘s deposition testimony indicates that Mr. Whitaker was not, as plaintiff argues, effectively a “No-show” witness. Given the breadth of the topics identified in Mr. Wagman‘s e-mail noticing the deposition, which, in the e-mail, Mr. Wagman explained was sent to “identify the appropriate
Although plaintiff argues that Mr. Whitaker was not prepared to discuss all of the topics that plaintiff identified prior to the
Plaintiff cites Dairyland Power Co-op v. United States to support its argument that it should recover the costs incurred in conduct-
CONCLUSION
For the foregoing reasons, plaintiff‘s May 31, 2013 motion to compel and for payment of expenses is DENIED. Plaintiff‘s October 31, 2014 motion for sanctions also is DENIED.
IT IS SO ORDERED.
