SEABOARD LUMBER COMPANY, W.T. Burgеss Logging Co., Inc., Big Flat Timber Company, Manke Lumber Company, Merrill & Ring, Inc., Tomco, Inc., Alpine Veneers, Inc., Penn Timber, Inc., Times Mirror Land & Timber Company, Taylor Westbrook, Brazier Forest Products, Inc., Gateway Lumber Company, Mt. Adams Veneer Co. and Capital Development Company, Plaintiffs-Appellants, v. The UNITED STATES, Defendant-Appellee.
No. 88-1486.
United States Court of Appeals, Federal Circuit.
May 17, 1990.
Rehearing Denied Sept. 11, 1990.
903 F.2d 1560 | 58 USLW 2748 | 36 Cont.Cas.Fed. (CCH) 75,900
Paul D. Langer, Attorney, Commercial Litigation Branch, Department of Justice, Washington, D.C., for defendant-appellee. With him on the brief were John R. Bolton, Asst. Atty. Gen., David M. Cohen, Director and John W. Showalter, Asst. Director. Also on the brief was William P. McGinnies, Attorney, Office of Gen. Counsel, Dept. of Agriculture, Washington, D.C., of counsel.
Before NIES and BISSELL*, Circuit Judges, and BALDWIN, Senior Circuit Judge.
NIES, Circuit Judge.
This appeal is from a certified interlocutory order of the United States Claims Court denying appellants’ motion to dismiss the government‘s counterclaims for breach by the contractors of particular government contracts. Our jurisdiction rests on
BACKGROUND
Appellants are timber companies that individually contracted with the United States to purchase timber from National Forests. With respect to each contract, the government asserted its breach claim against the contractor by means of an appropriate contracting officer‘s decision. In each case, the contracting officer issued a decision that the contractor failed to cut, remove and pay for timber as required by the contract and assessed a specific dollar amount of damages in each instance. See
Each timber purchasing contract, as originally executed or later amended,1 contained a standard disputes clause which provides in pertinent part:
C9.2 (disputes).
(a) This contract is subject to the Contract Disputes Act of 1978 (Pub.L. 95-563).(b) Except as provided in the Act, all disputes arising under or relating to this contract shall be resolved in accordance with this provision.
....
(c)iii .... A claim by the government against the contractor shall be subject to a decision by the contracting officer.
....
(f) The contracting officer‘s dеcision shall be final unless the contractor appeals or files a suit as provided in the Act.
By the Contract Disputes Act,
Under the above clause, once the decision of the contracting officer becomes final on a government claim against the contractor, the merits of that decision cannot be judicially challenged. To prevent that preclusive effect, the contractor has two options under the contract provisions which incorporate the CDA. The contractor may either appeal within 90 days to the appropriate Board of Contract Appeals as provided in
Each appellant filed suit in the Claims Court seeking review of the contracting officer‘s decision in favor of the government as provided in
Appellants’ suits were consolidated in the Claims Court for consideration of the constitutional issues. In denying the appellants’ motion to dismiss thе government‘s counterclaims, the Claims Court held that: (1) a government contract claim was not an action at common law and therefore did not require resolution by an Article III court, Seaboard, 15 Cl.Ct. at 369-72; (2) such claim fell within the “public rights” exception to Article III and Congress could thus constitutionally provide for adjudication by a non-Article III tribunal, id., at 372-74; and (3) the
ISSUE
Whether the CDA, as originally enacted or as amended by FCIA, unconstitutionally deprives appellants of either a right to an Article III court or a jury trial on the government counterclaims for breach of contract?
OPINION
The
In Suits at common law, where the value in controversy shall exceed twenty dollars, the right of trial by jury shall be preserved, and no fact tried by a jury shall be otherwise reexamined in any Court of the United States, than according to the rules of the common law.
Seaboard and all other contractors (hereinafter Seaboard) assert that the government‘s breach of contract claim should be deemed comparable to a private contract claim which, historically must be litigated in an Article III court with a right to a jury. In support of this analogy, it asserts that prior tо the CDA, the government had to litigate a breach claim against a contractor in an Article III court (although it cites no authority for this proposition). It maintains further that waiver of sovereign immunity and the authority of an Article I court to adjudicate claims against the government are not involved here. These premises lead Seaboard to its ultimate conclusion that the CDA‘s review procedures are unconstitutional. We disagree. The premises of Seaboard‘s syllogism are fatally flawed in a number of resрects.
I
Seaboard correctly states that the
Contrary to Seaboard‘s view, Congress has not taken away the contractor‘s right to have the government establish its breach clаim in an Article III court before a jury. By contractual agreement, the government had regularly provided (until curbed by Congress) that the decision of a contracting officer was final and not subject to review in any judicial forum. United States v. Moorman, 338 U.S. 457, 70 S.Ct. 288, 94 L.Ed. 256 (1950) (and cases cited therein). Moreover, these contractual provisions denying judicial review were specifically upheld by the Supreme Court, except for fraud on the government‘s part. Wunderlich v. United States, 342 U.S. 98, 99, 72 S.Ct. 154, 155, 96 L.Ed. 113 (1951); United States v. Holpuch Co., 328 U.S. 234, 66 S.Ct. 1000, 90 L.Ed. 1192 (1945) (contractor‘s failure to appeal per dispute resolution process in contract precluded suit in Court of Claims); United States v. Blair, 321 U.S. 730, 64 S.Ct. 820, 88 L.Ed. 1039 (1944) (same effect). Government contractors long have been held to be bound by a provision vesting dispute resolution in a nonjury/non-Article III forum. United States v. Moorman, 338 U.S. at 460-62, 70 S.Ct. at 290-91. In Wunderlich, the Supreme Court upheld the enforceability of the “finality clause” of a standard form government contract which provided that disputes between the parties “shall be decided by the contracting officer with a right of appeal to the head of the department ‘whose decision shall be final and conclusive upon the parties thereto.’ ” As stated in Wunderlich, 342 U.S. at 99-100, 72 S.Ct. at 155:
The same Article 156 of a government contract was before this Court recently, and we held, after a review of the authorities, that such Article was valid. United States v. Moorman, 338 U.S. 457 [70 S.Ct. 288, 94 L.Ed. 256 (1950) ]. Nor was the Moorman case one of first impression. Contracts, both governmental and private, have been before this Court in several cases in which provisions equivalent to Article 15 have been approved and enforced “in the absence of fraud or such gross mistake as would necessarily imply bad faith, or a failure to exercise an honest judgment....” Kihlberg v. United States, 97 U.S. 398, 402 [24 L.Ed. 1106 (1878) ]; Sweeney v. United States, 109 U.S. 618, 620 [3 S.Ct. 344, 344, 27 L.Ed. 1053 (1883) ]; Martinsburg & P.R. Co. v. March, 114 U.S. 549, 553 [5 S.Ct. 1035, 1037, 29 L.Ed. 255 (1885) ]; Chicago S.F. & C.R. Co. v. Price, 138 U.S. 185, 195 [11 S.Ct. 290, 293, 34 L.Ed. 917 (1891) ].
Thus, voluntary waiver of both Article III and
Seaboard argues that any waiver was not “voluntary” because government contracts are inherently adhesion contracts, and cites to precedent invalidating contractual provisions where the provision for a waiver resulted from the unfair bargaining positions between the parties.8 The bare fact that the contracts in question are “take it or leave it” offers by the government is not controlling on the dispute resolution provision‘s validity, as we read the precedent. The Supreme Cоurt in Wunderlich, 342 U.S. at 100, 72 S.Ct. at 156, addressed the nature of the government-contractor relationship:
Respondents were not compelled or coerced into making the contract [with the government]. It was a voluntary undertaking on their part. As competent parties they have contracted for the settlement of disputes in an arbitral manner. This, we have said in Moorman, Congress has left them free to do. United States v. Moorman, supra, 338 U.S. at 462 [70 S.Ct. at 291.] The limitation upon this arbitral process is fraud, placed there by this Court.
With respect to the voluntariness of agreeing to the dispute resolution provision in this contract, Wunderlich is controlling.
After the Wunderlich decision, Congress, as a matter of grace, provided for narrow judicial review of a contracting officer‘s decision, limiting by statute (the Wunderlich Act) the contractual options previously available to the government. See
The CDA, which followed the Wunderlich Act, further restricted the government‘s options on dispute resolution. Congress mandated that the government had to include in its contracts the broader review provisions set out in the CDA, that is, the dual avenues of review either by appeal to a Board of Contract Appeals or by a direct access suit in the Court of Claims. However, Congress confirmed the use of a finality clause in the contract with respect to a сontracting officer‘s decision in favor of the government, absent the contractor‘s resort to these review procedures. See
As in Moorman and Wunderlich, Seaboard agreed to the contract provisions spelling out the specific procedures for dispute resolution, none of which entail a jury trial in an Article III court. The effect of such agreement is that at least Seaboard prima facie voluntarily and knowingly waived any right to disputе resolution except in accordance with the contract.9
Finally, Seaboard asserts that the contractors who entered contracts prior to the FCIA cannot be held to have waived trial level adjudication by Article III judges. As indicated, FCIA amended the CDA so that direct access suits could no longer be brought in the Article III Court of Claims but would be brought in the Article I Claims Court with appeal to this Article III court. However, under the prior procedure, a trial commissioner was statutorily authorized to conduсt the trial and to file a report of factual findings. See
II
Another fallacy of Seaboard‘s position is that its challenge to the government‘s claim before the Claims Court does not implicate sovereign immunity, and therefore Congress’ power to place litigation involving the sovereign in an Article I court cannot be relied on in these cases. Sincе the venerable case of Murray‘s Lessee v. Hoboken Land and Improvement Co., 59 U.S. (18 How.) 272, 15 L.Ed. 372 (1855), it has been established that the authorization by Congress of a suit to challenge a government claim against the plaintiff can be brought only because of the consent of the sovereign. In Murray‘s Lessee, Congress enacted a statute which permitted the Treasury Department to audit and assess customs officials’ accounts, to issue a warrant of indebtedness for any delinquency, and to levy against that delinquency. Thereafter the custоms collector was allowed to contest the determination of indebtedness in district court. In upholding the constitutionality of these procedures, the Supreme Court expressly noted that they implicated sovereign immunity, stating:
When ... after the levy of the distress warrant has been begun, the collector may bring before a district court the question, whether he is indebted as recited in the warrant, it simply waives a privilege which belongs to the government, and consents to make the legality of its future proceedings dependent on the judgment of the court; .... The United States consents that this fact of indebtedness may be drawn in question by a suit against them.
Murray‘s Lessee, 59 U.S. (18 How.) at 284. Similarly, the complaints in this appeal are pursuant to a structural system set up by the CDA, which is dependent on waiver of sovereign immunity. Indeed, the CDA review procedures attacked here provide a more expansive waiver than the prior procedures provided in the Wunderlich Act. It is not disputed that the government may condition its consent to suit upon a plaintiff suing only in an Article I court, on waiving а jury trial, or on other conditions including provision for counterclaims to be asserted by the government. See United States v. Mitchell, 463 U.S. 206, 103 S.Ct. 2961, 77 L.Ed.2d 580 (1983) (Tucker Act,
It has also long been the law that an Article I court without a jury may adjudicate fact issues related to a counterclaim by the government against the plaintiff. In McElrath v. United States, 102 U.S. 426, 440, 26 L.Ed. 189 (1880), the Supreme Court held that counterclaims by the government in a suit brought in the Court of Claims (then deemed to be an Article I court) is not controlled by the
The government cannot be sued, except with its own consent. It can declare in what court it may be sued, and prescribe the forms of pleading and the rules of practice to be observed in such suits. It may restrict the jurisdiction of the court to a consideration of only certain classes of claims against the United States. Congress, by the act in question, informs the claimant that if he avails himself of the privilege of suing the government in the special court organized for that purpose, he may be met with a set-off, counter-claim, or other demand of the government, upon which judgment may go against him, without the intervention of a jury, if the court, upon the whole case, is of [the] opinion that the government is entitled to such judgment. If the claimant avails himself of the privilege thus granted [to sue the sovereign], he must do so subject to the conditions annexed by the government to the exercise of the privilege. Nothing more need be said on this subject. [Emphasis added.]
Seaboard has invoked the privilege of suing the government by filing its complaint in the Claims Court for review of the contracting officer‘s decision. Absent the wаiver of sovereign immunity provided by the CDA, Seaboard could not have filed that complaint. Having invoked that privilege, Seaboard is subject to the conditions of such waiver, one of which is that it subjects itself to the possibility of a government counterclaim to be tried in a non-jury/Article I tribunal, conditions which Congress may impose. The Supreme Court has spoken unequivocally on this point in McElrath.
Appellants rely on Tull v. United States, 481 U.S. 412, 107 S.Ct. 1831, 95 L.Ed.2d 365 (1987), in support of a result contrary to McElrath. In Tull, the United States sued a violator of the Clean Air Act, 62 Stat. 1155, as amended
In sum, it is only as a matter of legislative grace that Seaboard has access to any Article I or III forum. Before Congress’ restriction of the government‘s contract options, the government, by contract provisions, could and did avoid litigation of the merits of its contract claims in any tribunal. Thus, the basis for Seaboard‘s suit in the Claims Court is a statutory right, which involves a waiver of sovereign immunity. That review is de novo, rather than limited, is also a matter of legislative grace. Seaboard is not, as it would have it, merely facilitating the government‘s obligation to litigate a contract claim for a determination of the government‘s rights. Seaboard is asserting its own right, a right to review that is given to Seaboard by the contract provisions incorporating the CDA which waives sovereign immunity to that extent.
Conclusion
In conclusion, we agree with the government that under the lawful terms of the contract, Seaboard has agreed to only limited rights of review of the government‘s counterclaim. Under these circumstances, assuming it has the rights it asserts in the absence of its contract, Seaboard has waived any right to have the government counterclaim litigated in an Article III court before a jury. Moreover, the CDA‘s non-Article III/non-jury review procedures, enacted to restrict the government‘s dispute resolution options, are, under controlling precedent, constitutionally permissible as a condition on the waiver of sovereign immunity. The order of the Claims Court denying Seaboard‘s motion to dismiss is
AFFIRMED.
Notes
ARTICLE 15. Disputes--Except as otherwise specifiсally provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed with the work as directed.
Wunderlich, 342 U.S. at 99, 72 S.Ct. at 155.
