Schultz Construction, Inc. v. Franbilt, Inc.Schultz Construction, Inc. v. Franbilt, Inc.
This is the fourth appeal before this Court arising from the Thruway Authority‘s disapproval of defendant Franbilt, Inc. as a subcontractor on a rehabilitation project of Lock C-4 on the Champlain Canal due to Franbilt‘s provision of grossly nonconforming gate leaves (see Franbilt, Inc. v New York State Thruway Auth., 290 AD2d 705 [2002]; Schultz Constr. v Franbilt, Inc., 285 AD2d 936 [2001]; Matter of Franbilt, Inc. v New York State Thruway Auth., 282 AD2d 963 [2001], lv denied 97 NY2d 602 [2001]). Following the Authority‘s determination, plaintiff, the general contractor on the project, terminated its subcontract with Franbilt on the ground that the determination constituted a material default. Although Franbilt was subsequently permitted to complete work unrelated to the gate leaves, plaintiff repaired the gate leaves at its expense, with the assistance of another welding subcontractor on the project. Thereafter, plaintiff commenced this breach of contract action seeking to recover the costs incurred in repairing the gate leaves. In its answer, Franbilt asserted a number of counterclaims against plaintiff, impleaded third-party defendants Reliance Insurance Company and William Schultz, and cross-claimed against defendants M.J. Engineering & Land Surveying, Inc. and SJB Services, Inc., which provided inspection services and approved the gate leaves.
Collateral estoppel is an equitable doctrine that precludes a party from relitigating an issue raised and decided against that party or those in privity in a prior action or proceeding (see Buechel v Bain, 97 NY2d 295, 303 [2001], cert denied 535 US 1096 [2002]; Matter of Hickey v Sinnott, 277 AD2d 572, 573 [2000]). Thus, “[t]he proponent of collateral estoppel must show identity of [a decisive] issue, while the opponent must demonstrate the absence of a full and fair opportunity to litigate” (Jeffreys v Griffin, 1 NY3d 34, 39 [2003]). Here, Franbilt does not dispute plaintiff‘s claim that a critical issue to the resolution of its and plaintiff‘s breach of contract claims in this action is whether the gate leaves were in gross nonconformance with the project specifications. Franbilt maintains, however, that this issue was not decided in its prior
Even assuming, however, that the
In addition, we conclude that Supreme Court properly granted the respective motions of M.J. Engineering and SJB for summary judgment dismissing Franbilt‘s cross claim sounding in negligent misrepresentation against them. The gravamen of the cross claim is that M.J. Engineering and SJB falsely represented that Franbilt‘s performance was adequate and that Franbilt relied on these misrepresentations to its detriment. Inasmuch as there was no privity of contract between Franbilt and either M.J. Engineering or SJB, liability will attach only upon a showing of “(1) an awareness by the maker of the statement that it is to be used for a particular purpose; (2) reliance by a known
Here, the specifications governing the Authority‘s contract with Schultz indicate that the inspections were solely for the benefit of the Authority and could not constitute or imply acceptance of the work. Notably, those specifications were incorporated into the general contract, to which Franbilt agreed to be bound. Indeed, there is no evidence that reports by M.J. Engineering or SJB were submitted to Franbilt for reliance thereon. Under these circumstances, we cannot say that Franbilt raised any triable issues of fact regarding reliance to its detriment or an understanding on the part of M.J. Engineering and SJB that Franbilt intended to rely on the reports (see Marcellus Constr. Co. v Village of Broadalbin, 302 AD2d 640, 641 [2003]; Rayco of Schenectady v City of Schenectady, 267 AD2d 664, 665-666 [1999]). In any event, although Franbilt now asserts a claim for misrepresentation, it continues to assert that the reports were accurate insofar as they deemed its work satisfactory and, thus, it is unclear which portions of the reports Franbilt claims are false (see Marcellus Constr. Co. v Village of Broadalbin, supra at 642). Franbilt‘s remaining arguments are either rendered academic by our decision or, upon review, have been determined to be meritless.
Crew III, Spain, Rose and Kane, JJ., concur. Ordered that the order is affirmed, without costs.