Schultz Construction, Inc. v. Franbilt, Inc.Schultz Construction, Inc. v. Franbilt, Inc.
Appeal from an order of the Supreme Court (Nolan, Jr., J.), entered April 25, 2000 in Saratoga County, which, inter alia, partially denied a motion by plaintiff and third-party defendants Reliance Insurance Company and William Schultz to strike the amended answer and counterclaims of defendant Franbilt, Inc.
Plaintiff contracted for the repair of a lock on the Champlain Canal and subcontracted portions of the work, including fabri
Plaintiff, Reliance and Schultz (hereinafter collectively referred to as appellants) then moved to strike defendant’s answer, counterclaims and third-party complaint pursuant to CPLR 3024 and 3211. Supreme Court partially granted the motion and dismissed defendant’s fourth and fifth counterclaims, as well as so much of its first, second and third counterclaims as were premised upon quantum meruit or unjust enrichment. Supreme Court denied the motion to the extent that it sought to strike the answer and dismiss defendant’s causes of action for breach of contract, lien foreclosure and unlawful diversion of trust funds. As limited by their brief, appellants appeal only that part of the order as denied their CPLR 3211 motion. We affirm.
Appellants first argue that the causes of action for breach of contract asserted in the second and third counterclaims, as well as defendant’s lien foreclosure claims, are barred by releases contained in defendant’s payment requisitions. We cannot agree that defendant’s surviving claims based upon wrongful termination of the original contract come within the scope of those releases. Nor can we agree with appellants’ contention that a wrongful termination claim is nonetheless precluded by the parties’ express rescission of the termination. The amendment to the subcontract implicitly preserves this claim because the termination was plaintiff’s response to defendant’s allegedly deficient work on the gate leaves and the amendment deemed the termination to be rescinded “with the exception of work effort on the gate leaves.” To the extent that defendant bases its claims on extra work or delay, the amendment states, in pertinent part, “that the Contractor and Subcontractor reserves [sic] their respective rights to dispute any and all changes, disruptions and delays, and breaches of the original Subcontract agreement.” In light of the liberal
Appellants also contend that the second and third counterclaims should be dismissed in their entirety because they continue to rely upon the theories of unjust enrichment and quantum meruit. However, these counterclaims are now limited to breach of contract allegations and are not precluded. While quantum meruit is thus precluded here as a theory of recovery, it is nonetheless the appropriate method for calculating damages because liability is premised on “contracts terminated before completion” (Najjar Indus. v City of New York,
Finally, appellants argue that the trust diversion action, brought pursuant to Lien Law article 3-A, is both without merit and untimely commenced. However, the one-year period relevant here does not begin to run until the date of completion of all work (see, Northern Structures v Union Bank,
Cardona, P. J., Mercure, Crew III and Mugglin, JJ., concur. Ordered that the order is affirmed, with costs.